Part Submission Warrant - Customer Requirements for PSW Submission

Moncia

Quite Involved in Discussions
#1
Hello

Nice to see you all in here again

I have a question on PSW

My company is not ISO/TS 16949, but we do supply to some automotive companies so occasionally we are asked to complete PSW or do PPAP ( I've only done two so far - so still learning)

One of the companies i just did PPAP for just informed me that they are in talks with some new automotive customers and they would need me to do PSW each time they (our customer ) will get new customer or contract for our products.

So my question is - am i responsible for doing PSW each time my customer is getting new customer of their own?
Or i am only responsible for supplying PSW to MY customer only. If they then get new customers, new business - they should either do their own PSW or forward mine ???

All this PPAP business is quite confusing to me

Thank you all in advance for your help

:bigwave:
 
Elsmar Forum Sponsor

Emmyd

Involved In Discussions
#2
Re: Part Submission Warrant

In my experience, you shouldn't have to resubmit a new PSW each time your customer gets a new customer. Your PPAP is generic to your customer and is only up for renewal annually. Your customer will have to resubmit their PPAP for each new customer, but should just include a current copy of your PPAP with their submission.
Good luck!
 

Moncia

Quite Involved in Discussions
#3
Re: Part Submission Warrant - Customer Requirements For

Ohhh i like the answer

Thank you Emmyd

Is there any book, standard that i can show to my customer

I have the PPAP 4th edition - but this one only tell you how to complete PSW - does not explain much how its used.
 

Golfman25

Trusted Information Resource
#4
Re: Part Submission Warrant - Customer Requirements For

Ohhh i like the answer

Thank you Emmyd

Is there any book, standard that i can show to my customer

I have the PPAP 4th edition - but this one only tell you how to complete PSW - does not explain much how its used.
That's because many make it up as they go along. If you're only asked for a PSW consider yourself lucky. It's a simple one pager.
 

Ron Rompen

Trusted Information Resource
#5
Re: Part Submission Warrant - Customer Requirements For

Dont fall into that trap - depending on what LEVEL of PPAP you put on the warrant, you are still required to do a lot of work 'behind the scenes'. Remember, what you submit and what you have to COMPLETE and RETAIN are not always the same thing.

Monica, it sounds like your customers don't really understand the PPAP process. Ask them to clarify why they are asking for a warrant.
 

howste

Thaumaturge
Super Moderator
#6
Re: Part Submission Warrant - Customer Requirements For

So my question is - am i responsible for doing PSW each time my customer is getting new customer of their own?
Or i am only responsible for supplying PSW to MY customer only. If they then get new customers, new business - they should either do their own PSW or forward mine ???
In my mind, the correct answer is whatever you have contractually agreed to provide to them. If they expect you to jump through hoops every time they get a new order or customer you may run out of time to do your day job.

Since there's a question about what you need to do, it sounds like it wasn't give to you in writing. I would ask them to clarify in writing what they are asking for. Once they send you the information in writing, it should be more clear what they expect.

You can also evaluate their request and determine if it sounds reasonable to do for free (cost of doing business) or if you should start charging them for your time and effort. Some customers will ask for a ton of information until they start having to pay for it... :frust:
 
#7
Re: Part Submission Warrant - Customer Requirements For

Dont fall into that trap - depending on what LEVEL of PPAP you put on the warrant, you are still required to do a lot of work 'behind the scenes'. Remember, what you submit and what you have to COMPLETE and RETAIN are not always the same thing.

Monica, it sounds like your customers don't really understand the PPAP process. Ask them to clarify why they are asking for a warrant.
Ron is completely correct. Your automotive customer will dictate what you need by the level of PPAP required.
For example:
Level 1 - Warrant Only (And for designated appearance items, an appearance approval report) Submitted to the customer.
Level 2 - Warrant with product samples and limited supporting data submitted to the customer.
Level 3 - Warrant with product samples and complete supporting data submitted to the customer
Level 4 - Warrant and other requirements as defined by the customer
Level 5 - Warrant with product samples and complete supporting data reviewed at your location by the customer.

Your automotive supplier should have some type of guideline such as this. If they have a portal you're sure to find it there. If not, then ask them for it.
They are more than willing to work with you and help most of the time.

Thanks,
Tim
 

Golfman25

Trusted Information Resource
#8
Re: Part Submission Warrant - Customer Requirements For

Dont fall into that trap - depending on what LEVEL of PPAP you put on the warrant, you are still required to do a lot of work 'behind the scenes'. Remember, what you submit and what you have to COMPLETE and RETAIN are not always the same thing.

Monica, it sounds like your customers don't really understand the PPAP process. Ask them to clarify why they are asking for a warrant.
The op indicated they did the PPAP. So they should have all the documentation. Updating the PSW is the easy part.
 
Thread starter Similar threads Forum Replies Date
J PSW (Part Submission Warrant) and Design Requirements APQP and PPAP 14
S Looking for a PPAP PSW, Part Submission Warrant, in Chinese APQP and PPAP 5
D PSW (Part Submission Warrant) Question for Part Number Change APQP and PPAP 9
V Safety and/or Government Regulation question on a PSW (Part Submission Warrant) APQP and PPAP 6
V Is it OK to put 2 Part Numbers on 1 PSW (Part Submission Warrant)? APQP and PPAP 12
V What has more weight: Master Print or Part Submission Warrant? APQP and PPAP 4
A Does the PSW (Part Submission Warrant) need to be a controlled document? APQP and PPAP 7
automoto PPAP Forms - Part Submission (Warrant) form .xls Document Control Systems, Procedures, Forms and Templates 2
E PSW (Part Submission Warrant) for Service Parts APQP and PPAP 4
P PPAP Approval - Customer approval of PSW (part submission warrant) APQP and PPAP 5
S Material Supplier Part Submission Warrant (PSW) APQP and PPAP 2
I Confused on PPAP re-submission - Help on PSW (Part Submission Warrant) APQP and PPAP 3
M Spanish PSW (Part Submission Warrant) Needed APQP and PPAP 8
W Better Understanding of PSW (Part Submission Warrant) APQP and PPAP 7
B New PSW (Part Submission Warrant) - 4th Edition PPAP Manual APQP and PPAP 38
G Part Submission Warrant (PSW) dispute APQP and PPAP 19
S Can anybody tell me what the legal status of the Part Submission warrant (PSW) is? APQP and PPAP 3
D Seeking CURRENT PPAP Part Submission Warrant APQP and PPAP 7
M Part Submission Warrant - Omitting Parts of APQP and PPAP 5
D Truck Industry Part Submission Warrant APQP and PPAP 6
G Gage R&R - Where am I going wrong? Part of a FAIR submission (Aerospace) Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 2
JoCam Approving a Test House on a Medical Device as a part of a 510k Submission 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 3
S Is a Quality Manual part of a 510k Submission? Other US Medical Device Regulations 1
C Who in the supplier organization has to sign the PSW (Part Submission Warranty)? APQP and PPAP 6
P Part Submission Form - Need to submit PSW only once? APQP and PPAP 5
T Who signs PSW's? (PPAP Part Submission Warrants) APQP and PPAP 1
shimonv Bench Testing as part of 510(k) Submission US Food and Drug Administration (FDA) 1
B Salary Requirements as part of initial resume/CV submission Career and Occupation Discussions 13
B Quality Stand Down form - Part of a PPAP submission to Johnson Controls Document Control Systems, Procedures, Forms and Templates 12
C New PPAP submission required when changing part number? APQP and PPAP 11
J PPAP (Production Part Approval Process) Submission Level Differences - Forms attached APQP and PPAP 17
W PPAP (Production Part Approval Process) - Clarify When submission is required APQP and PPAP 10
D Is PMCF really a continuous activity per Annex XIV,Part B? EU Medical Device Regulations 5
M 21 CFR 820 vs 21CFR820 vs 21 CFR Part 820 Document Control Systems, Procedures, Forms and Templates 3
N BF-type applied part MOPP vs secondary IEC 60601 - Medical Electrical Equipment Safety Standards Series 2
D Relabelling a component that will be sold as a spare part - Do I become legal manufacturer? EU Medical Device Regulations 2
T Single Fault Condition IEC 60601 Clause 8.7.1 shorting Cr/Cl in Patient Applied Part IEC 60601 - Medical Electrical Equipment Safety Standards Series 7
D Partial FAI - AS9102 - One single drawing has 10 part numbers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
Anonymous16-2 21 CFR Part 11 - Steps to take if we want to validate an electronic system Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 2
T ISO 13485 8.3 - Non-Conforming Materials - on-line rework or part of process? ISO 13485:2016 - Medical Device Quality Management Systems 11
DuncanGibbons Should the requirements FAA/EASA Part 21 be addressed within the QMS and AS9100D quality manual? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
K IEC 62304 compliance - Code reviews as part of verification strategy IEC 62304 - Medical Device Software Life Cycle Processes 5
A 21 CFR part 11 - section 11.100 - Electronic Signature Certification Other US Medical Device Regulations 6
M AS9102B Detail Part/Assembly FAI Form 1 box 13; AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
M 2xMOPP insulation for Applied Part B. IEC 60601 - Medical Electrical Equipment Safety Standards Series 4
A ISO 41001:2018 - Clause No.8 Operations Part Quality Management System (QMS) Manuals 2
NDesouza Getting Rid of Part Marking Errors Benchmarking 39
L Wearables 21 CFR Part 11 compliance Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 1
DuncanGibbons How are part cut out specimens made and tested? Manufacturing and Related Processes 1
S Internal calibrations - Part of an ISO 17025 accredited testing laboratory (Automotive) ISO 17025 related Discussions 3