We are a contract manufacturer and added the use of PFMEA's and Control Plans to our new product introduction process in 2018, in a recent certification audit we received a finding because we had not gone back and performed these on our older products. Some of these date back to 2012. The finding was against ISO 13485 clause 7, since this clause is related to "Product Realization" and our procedure for when to use them is in our NPI process is this a legitimate finding?
Thanks,
 
Elsmar Forum Sponsor

Tagin

Trusted Information Resource
#2
1) What specific point in clause 7 was cited? And/or, provide us the full text of the NC from the auditor.
2) What do your process docs say for FMEA/CP requirements? Do you say you will do it on "all products", or on "all new products going forward", etc.?
 

John C. Abnet

Teacher, sensei, kennari
Staff member
#3
Good day @tbaker ;
Please allow me to cause us to think beyond what the auditor is "asking for" and instead think about what your organization wishes.

Do corrective actions ever take place on the legacy products/processes? What do you use to confirm the current controls when performing corrective actions? What does your update to ensure any corrective actions are sustained?

Do any change points take place on the legacy products/processes? What does your organization update to ensure any change points are sustained?

See where I'm going here ? Instead of asking "what can we avoid", I would challenge your organization to consider instead "what do we need".

Be selfish. Management systems should first and foremost serve the need of your organization and its customers.

Hope this helps.
Be well.
 
#4
Here is the finding:
Non-conformance description:
Risk management process and documentation are inadequately established

Requirement:
ISO 13485:2016

- 7.1-d) "records needed to provide evidence that the realization processes and resulting product meet requirements"
- 4.2.4-a) "review and approve documents for adequacy prior to issue

Objective Evidence:

- Not all processes/products have documented risk management files.
- Risk Management File 536571 Ferrite Holder include irrelevant information related to PFMEA and Control Plan dated 10 Sep 2019 for 530581 Rev H Molded, 543631 Rev B Foam Pads Installed.

In the audit while looking for obj evidence we found a couple files with the wrong part number in the file name, the files were in the correct folders (electronic) but it looked like the file creator had modified an existing file for a new part but forgot to change the file name.

Our procedures have PFMEA and CP done during NPI processes and then updated whenever there is a rev change to the part.
 
#5
Thanks John C,

As a low volume high mix contract supplier we would need to do hundreds of PFMEA's and CP's on well established products and processes, I struggle to see the reward on the effort and cost.
 

John C. Abnet

Teacher, sensei, kennari
Staff member
#6
we would need to do hundreds of
Good day @tbaker ;
Understood.
The focus of the finding (likely your organization's priority) is specific to identifying risk.

Is it possible your organization could benefit from foundational (or family) PFMEA? For example, if an organization makes zip ties in multiple lengths and colors, the process steps (mix, extrude, cut, etc....) and the associated risks with each step are same/similar. It would not make sense, therefore to have a separate PFMEA for each item number. In the above example, foundational PFMEA could simply be created for the various process steps.

Just a thought.

Hope this helps.
Be well.
 
Thread starter Similar threads Forum Replies Date
T Linking Control Plans and PFMEA's FMEA and Control Plans 3
S Seeking Ballooned PFMEA and Control Plans for Training FMEA and Control Plans 4
5 Changes to Control Plans or PFMEA's (Process FMEA) FMEA and Control Plans 6
B PFMEA's and control plans from something like an Access database for TS 16949:2000 Quality Assurance and Compliance Software Tools and Solutions 2
G Control Plan & PFMEA Review Procedure? FMEA and Control Plans 1
A Redesigning our process flow chart, PFMEA and Control Plan Process Maps, Process Mapping and Turtle Diagrams 4
N Control plan evaluation methods - Which methods should be carried over from the PFMEA? FMEA and Control Plans 3
M Control Method correspondence between PFMEA and CP FMEA and Control Plans 8
O Difference Between PFMEA & Control Plan FMEA and Control Plans 3
L Simple Example for PFMEA / Control Plan Training Training - Internal, External, Online and Distance Learning 1
B PFMEA and Control Plan Links APQP and PPAP 2
A Corrective Action Column in Control Plan and aligning PFD, PFMEA and Control Plan FMEA and Control Plans 6
I Any recommendations on software for managing the APQP, PPAP, PFMEA, Control Plan etc? Quality Assurance and Compliance Software Tools and Solutions 2
K Control Plan vs PFMEA Control Methods FMEA and Control Plans 1
S PFMEA - Control Plan Sample IATF 16949 - Automotive Quality Systems Standard 4
M Need Machining Low Volume Family Control Plan and PFMEA APQP and PPAP 1
M Process Flow Diagram -> PFMEA -> Control Plan Linkage IATF 16949 - Automotive Quality Systems Standard 17
K PFMEA and Control Plan Examples wanted FMEA and Control Plans 6
F Please review my Process Flow / PFMEA / Control Plan FMEA and Control Plans 12
D PFMEA and Control Plan Core Team Changes FMEA and Control Plans 4
A PFMEA and Control Plan Connections - TS 16949 Clause 7.3.3.2 FMEA and Control Plans 24
R Any of you have blank PFMEA and Control plan form that I could use? Document Control Systems, Procedures, Forms and Templates 2
B Need a Process Flow Diagram, Control Plan and PFMEA for Automotive Wiring Harness FMEA and Control Plans 10
J Product Failure - PFMEA/Control Plan actions FMEA and Control Plans 4
M Confused about Control Plan and PFMEA Retention Period Document Control Systems, Procedures, Forms and Templates 2
J Are the Pre-Launch Control Plan and Pre-Launch PFMEA obligatory? FMEA and Control Plans 3
P DFMEA, PFMEA and Control Plan examples (e.g.: for a pen) wanted for training FMEA and Control Plans 2
G Manufacturing -> Warehouse -> Tier 1/OEM - Process flow, PFMEA, & Control Plan FMEA and Control Plans 9
A DFMEA, PFMEA and KCC's (Key Control Characteristics) Relationships FMEA and Control Plans 11
Kales Veggie Informational How to develop a Control Plan from a PFMEA (Process FMEA) FMEA and Control Plans 57
D Automotive Core Tools - Developing PPAP, PFMEA and Control Plan Work Instructions APQP and PPAP 3
V PFMEA's and CONTROL PLAN Examples for aerospace sector APQP and PPAP 1
Anerol C How to Audit Shop Floor without Flow Diagram, Control Plan/PFMEA? Internal Auditing 5
J The real Link between a PFMEA (Process FMEA) and the Control Plan FMEA and Control Plans 19
K DCP (dynamic control plan) and PFMEA - Effectiveness of the DCP method FMEA and Control Plans 6
M Connections between PFMEA (Process FMEA) and the Control Plan. FMEA and Control Plans 20
J Plastics molding control plan and PFMEA - Example wanted FMEA and Control Plans 17
W Plastic Part Painting/Spray Failure Mode - Sample PFMEA or control plan Manufacturing and Related Processes 7
J Software which links Process FMEA (PFMEA), Control Plan and Flow Chart Quality Assurance and Compliance Software Tools and Solutions 9
A Same Process Different Part - Control Plan, PFMEA, etc. All the Same APQP and PPAP 9
K PFMEA & Control Plan Software - Advantages over Excel? Suggestions? Recommendations? Quality Assurance and Compliance Software Tools and Solutions 1
D Process Control Plan Content: Relationship to PFMEA and Flow Diagram FMEA and Control Plans 3
P Equipment URS, pFMEA and dFMEA ISO 14971 - Medical Device Risk Management 3
W Pfmea function requirement and failure mode FMEA and Control Plans 6
M Material incoming to the production process reflected in PFMEA FMEA and Control Plans 9
R Power Failure or Cold Start Situation in PFMEA FMEA and Control Plans 6
M "Issue & continuous improvement" columns in AIAG-VDA PFMEA form FMEA and Control Plans 4
C AIAG-VDA PFMEA - 1st special Characteristics? [5step vs. 6step] FMEA and Control Plans 3
R DFMEA/PFMEA mitigation of high severity (9-10) in low volume products IATF 16949 - Automotive Quality Systems Standard 1
T Annual Validation as a detection mode on a PFMEA? FMEA and Control Plans 5

Similar threads

Top Bottom