Dimension result report

I have a question about the dimension result in PPAP manual 1.2.2.7.
This is the way we are doing now: QA pick two samples from PSW finished parts after they were sent to us. We measure all the dimensions on drawing. But how about the dimension we can not measure from finished parts. For example: The drawing have a length spec before bending and after bending a pipe. These two dimention are all on drawing. How can we measure the length before bending from finished parts? Also some dimension on drawing is just for process control? After finished, These dimension are covered by other component. We cannot see them.
If we have to take all the dimension, We have to follow those two parts from the beginning to the end of process? Does it sound a little funny?

Anybody can shed aome light on me? Thanks.
 
Elsmar Forum Sponsor
B

Bill Ryan - 2007

#2
Richard said:
If we have to take all the dimension, We have to follow those two parts from the beginning to the end of process?
In my experience, the answer is YES. 100% dimensional layout means just that. I guess you COULD "back engineer" with the thing that if all the bends and distances between bends are to print, the O/A length must have been OK, but that doesn't sit right with me.

Richard said:
Also some dimension on drawing is just for process control? After finished, These dimension are covered by other component. We cannot see them.
If, in fact, they are for Process Control, you are probably monitoring them (?)and should already have measurements from upstream in your process. Just transfer those to the dimensional results sheets. Otherwise, you would need to "birddog" the parts through your process and take measurements at appropriate steps so that you CAN measure those "hidden" features.

We have a couple of parts that have multiple part drawings with different customer part numbers. We PPAP to each drawing even though the customer only buys the "highest order" part. Just a fact of life we deal with for certain customers. Yes it can be a pain, but......... que sera.

Bill
 
R

Richard

#3
So I can just elaborate those particular samples for customer.
I thought we were supposed to pick samples radomly from finished parts so samples can represent whole the lot quality. This is where my confuse from.
I take dimension for some SPC process study if they are SC.
What is the real purpose to these samples and that report? Help me to think it through. Thanks
 
B

Bill Ryan - 2007

#4
Richard said:
What is the real purpose to these samples and that report?
I guess my answer would be derived (quoted?) from the PPAP manual - "The supplier shall provide evidence that dimensional verifications required by the design record and the Control Plan have been completed and the results indicate compliance with specified requirements." It states further that you need results at each "unique manufacturing process." That seems pretty straightforward to me.

As a "side bar" - More than once we have been "saved" by the dimensional results sheets and proving compliance to specifications when a Design Engineer has performed a stack-up analysis incorrectly.

Hope that helps.

Bill
 
Thread starter Similar threads Forum Replies Date
S Service Parts PPAP AIAG Manual - Opinions APQP and PPAP 4
O Significant Production Run - 2.1 in Section 2 of the PPAP Manual fourth edition APQP and PPAP 3
CalRich Requirement from the PPAP Manual or from GM to add a PPAP Report with Shipment? Customer and Company Specific Requirements 1
O Ordering an AIAG PPAP Manual - Europe (Sweden) APQP and PPAP 7
C Yearly resubmission of PPAP - Required by the PPAP manual? APQP and PPAP 7
D AIAG PPAP Manual Forms: CFG-1003, CFG-1004, CFG-1005 APQP and PPAP 3
F Notification of Change of Material Supplier - PPAP Manual 4th Edition APQP and PPAP 15
O Numbers of units tested for Material/Performance Test - PPAP manual chapter 2.2.10.1 APQP and PPAP 1
O A few questions about the PPAP Manual (4th edition) APQP and PPAP 6
B What is the Latest Revision Of the AIAG PPAP Manual? APQP and PPAP 1
P Bulk Materials PPAP / FMEA - Appendix F of the PPAP manual APQP and PPAP 1
A APQP/ PPAP Manual Revision Control APQP and PPAP 2
Jim Wynne 4th Edition PPAP manual - Bulk Materials - Can you guess what this means? APQP and PPAP 12
J PPAP Marking - Polymeric Parts - AIAG PPAP Manual 4th edition, page 4, Clause 2.2.1.2 APQP and PPAP 5
Howard Atkins Informational AIAG PPAP Manual 4th Edition Forms (including Control Plan) APQP and PPAP 68
T I want a copy of the AIAG PPAP Manual 4th edition APQP and PPAP 4
K PPAP Manual Fourth Edition will be available to order in advance on February 24 APQP and PPAP 4
B New PSW (Part Submission Warrant) - 4th Edition PPAP Manual APQP and PPAP 38
G AIAG PPAP Manual Fourth Edition will be available exclusively from AIAG March 1, 2006 APQP and PPAP 6
M Difficult to do according to PPAP Manual? Big plastic parts, over 100 dimensions APQP and PPAP 5
X Seeking PPAP manual (English Edition) APQP and PPAP 1
K TS 16949 PPAP - What it means: SQAM Forms? Supplier Quality Assurance Manual? IATF 16949 - Automotive Quality Systems Standard 4
S AIAG's PPAP Manual - New version due soon APQP and PPAP 3
S AIAG PPAP Manual pg 16 - PPAP requirements shall be retained at appropriate locations APQP and PPAP 2
J AIAG PPAP (Production Part Approval Process) Manual Fourth Edition Released APQP and PPAP 69
A PPAP (Production Part Approval Process) - Where can I buy the AIAG Manual? Preventive Action and Continuous Improvement 2
S Is there any site where I can get PPAP and SPC manual in PDF form QS-9000 - American Automotive Manufacturers Standard 2
M Gap Analysis of the AIAG's PPAP Manual 2nd vs. 3rd Edition APQP and PPAP 3
C PPAP required by Customer not the same as the AIAG's PPAP Manual Requirements APQP and PPAP 2
J Bulk Materials Checklist form - 3rd Edition PPAP Manual APQP and PPAP 3
J Supplier not responding to PPAP request APQP and PPAP 5
J Part submission warrant for Level 1 PPAP APQP and PPAP 1
K Should APQP/PPAP has its own section in a QM? Quality Management System (QMS) Manuals 1
B Toyota PPAP Process - Three Questions APQP and PPAP 3
G Supplier delivered recent PPAP, should he deliver yearly layout inspection? IATF 16949 - Automotive Quality Systems Standard 4
F How to submit a PPAP when a subcontractor is the sole manufacturer IATF 16949 - Automotive Quality Systems Standard 2
P PPAP samples retention time IATF 16949 - Automotive Quality Systems Standard 5
K Updated MSA with the Annual PPAP validations APQP and PPAP 8
P Managing How PPAP Requirements are Communicated in the Manufacturing Process and to Suppliers APQP and PPAP 5
E Annual PPAP+ deviation request ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
K OEM specific requirements - PPAP was rejected by STA Customer and Company Specific Requirements 5
T PPAP for distributors? APQP and PPAP 1
A PPAP for Fire extinguisher APQP and PPAP 2
S PPAP Progress - Visual Status Board APQP and PPAP 0
C AS9145 Appendix D PPAP Approval Form APQP and PPAP 2
Pau Calvo PPAP customer requirements in the APQP APQP and PPAP 25
V 3 PQ lots mentioned as requirement in PPAP. Is this necessary? APQP and PPAP 2
B What is the role of Quality Engineer in APQP and PPAP APQP and PPAP 3
F How to submit PPAP without IMDS APQP and PPAP 10
GreatNate Excel PPAP Tracking templates or tool wanted APQP and PPAP 1

Similar threads

Top Bottom