We have lost a supplier. What level of PPAP is required to be submitted to our Customers for our new supplier?
 

Jim Wynne

Leader
Admin
We have lost a supplier. What level of PPAP is required to be submitted to our Customers for our new supplier?

Welcome to the Cove. :D

The PPAP submission level is determined by your customer(s). What customers expect in situations like this varies--some expect a submission at the default level (usually 3) while others want to be notified of the change and will assign a PPAP level.

Remember also that the PPAP submission level tells you which elements must be submitted, not which elements have to be done. Regardless of the submission level you still must do all of the default requirements and retain what doesn't get submitted.
 
Thread starter Similar threads Forum Replies Date
B TS16949 Annual PPAP Submission Requirements for Ford and Chrysler Parts IATF 16949 - Automotive Quality Systems Standard 2
B PPAP Document Submission and Retention requirements APQP and PPAP 21
Y PPAP requirements: Submission date and PSW (Statistical Process Package) APQP and PPAP 6
A Help needed for PPAP submission requirements including contents APQP and PPAP 3
J GM PPAP Specific Requirements - How many pieces for layout, submission - Gage R&R? Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 4
C PPAP requirements for consumer product APQP and PPAP 2
R PPAP Requirements for Tool Repair or Refurbishment APQP and PPAP 5
P Managing How PPAP Requirements are Communicated in the Manufacturing Process and to Suppliers APQP and PPAP 5
K OEM specific requirements - PPAP was rejected by STA Customer and Company Specific Requirements 5
Pau Calvo PPAP customer requirements in the APQP APQP and PPAP 25
eule del ayre List of Level 3 PPAP requirements for automotive suppliers APQP and PPAP 20
P Paint shop vs PPAP requirements IATF 16949 - Automotive Quality Systems Standard 5
Sidney Vianna AS9100 News PPAP in the Aerospace Sector - What is it? AS9145 - Requirements for Advanced Product Quality Planning and Production Part Approval Process AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
M Annual Layout requirements for PPAP/Control Plan FMEA and Control Plans 6
G Supply Chain PPAP Requirements APQP and PPAP 11
P Automotive Supplier PPAP Level Requirements Supplier Quality Assurance and other Supplier Issues 12
G PPAP 4th edition or VDA - VW Requirements APQP and PPAP 2
Y Customer Specific PPAP Level 3/4 Requirements - Fastener Manufacturer APQP and PPAP 2
A Cost of Deviating Away From PPAP Requirements APQP and PPAP 3
V Inactive Gauge Retention Time - PPAP Section 6 Requirements APQP and PPAP 1
I AS9100 PPAP requirements for outside Heat Treat vendors/suppiers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
M PPAP requirements when adding Part Transfer Robots between Machines APQP and PPAP 1
P Bulk Material Requirements Checklist to send along with my PPAP APQP and PPAP 2
B Bulk Materials (Lead {Pb} Alloys) PPAP Requirements APQP and PPAP 5
T PPAP Requirements for Contract Manufacturers APQP and PPAP 4
J PPAP (Production Part Approval Process) Requirements for Annual Revalidations APQP and PPAP 1
V PPAP Requirements including GMW 3179 Zinc Plating Specification Requirements APQP and PPAP 3
V PPAP Requirements for Plating a "Family of Parts" APQP and PPAP 8
P PPAP Requirements for Sub-Assemblies APQP and PPAP 6
V Plating Supplier PPAP Revalidation Requirements - A-Coat GM 9984132 Plating Process APQP and PPAP 1
V PPAP - Requirements when Cpk is <1.67 - 100% Sort for Defectives APQP and PPAP 8
R Does anyone have the list of Toyota PPAP requirements? APQP and PPAP 6
M For Bulk Material (eg. paint), are there any guidelines for Ford PPAP Requirements? APQP and PPAP 1
B TS 16949 PPAP/ Layout Inspection Frequency Requirements APQP and PPAP 8
Q Level of PPAP - Bulk Chemicals Supplier Requirements APQP and PPAP 2
F PPAP Material Test Results Requirements - Material Supplier Identification QS-9000 - American Automotive Manufacturers Standard 1
Q Supplier PPAP Requirements - TS 16949 Clause 7.3.6.3 IATF 16949 - Automotive Quality Systems Standard 12
S Can PPAP be submitted when not all customer requirements can be met? APQP and PPAP 5
K Supplier PPAP Requirements - Level 3 or Level 4 APQP and PPAP 6
J PPAP Requirements - Suppliers who are changing their Suppliers APQP and PPAP 7
L PPAP List Requirements - Molds, Tools or the Checking Tools? APQP and PPAP 5
J Requirements for Retaining PPAP Master Samples APQP and PPAP 2
J Prior Notice of Sub-Supplier or Material Source Change - PPAP Requirements Question APQP and PPAP 13
J PPAP Requirements Question APQP and PPAP 4
S PPAP requirements for sub-suppliers APQP and PPAP 5
C Honda PPAP requirements APQP and PPAP 12
H Requirements in TS for PPAP - Full PPAP or as per Customer Requirement? IATF 16949 - Automotive Quality Systems Standard 14
S Are the AIAG document (FMEA, PPAP, SPC, MSA, APQP) guidelines or requirements FMEA and Control Plans 6
K PPAP Requirements for Raw / Bulk Materials? APQP and PPAP 6
R GM revised its Specific Requirements for TS16949 and PPAP 4th, effective immediately Customer and Company Specific Requirements 4

Similar threads

Top Bottom