I'm new here and I am new to this "strict" and "challenging" quality world of the automotive industry.
Recently, a new customer came up and is on the process of establishing a contract to buy automotive cables from my company.
They requested me for a level 3 PPAP submission for a type of wire that we are currently producing.
We were already approved by our other customer previously, a couple of years ago.
My questions are:
1. Do I need to prepare new sets of the required attachments, e.g., performance test results, material test results, MSA studies, etc? or will it be okay if I'll use the attachments used previously during the initial approval (dated several years back)?
2. Do I need to create another prototype/pre-launch control plan? or will it be okay if I will just submit the production control plan?
Please advise.
I'm new here and I am new to this "strict" and "challenging" quality world of the automotive industry.
Recently, a new customer came up and is on the process of establishing a contract to buy automotive cables from my company.
They requested me for a level 3 PPAP submission for a type of wire that we are currently producing.
We were already approved by our other customer previously, a couple of years ago.
My questions are:
1. Do I need to prepare new sets of the required attachments, e.g., performance test results, material test results, MSA studies, etc? or will it be okay if I'll use the attachments used previously during the initial approval (dated several years back)?
2. Do I need to create another prototype/pre-launch control plan? or will it be okay if I will just submit the production control plan?
Please advise.