I have just received 2 PPAP submissions from a new supplier for two different size steel tubes. Going through the GR&Rs I noticed that the Inside Diameter GR&R for both size tubes are identical, number for number. I have looked for the gauge that they have listed on the report (Mitutoyo 3 pt bore gauge Model# 92865) but after contacting Mitutoyo :evidence: there is no 92865 (they said that number might be a serial number off of the indicator).

The ID of the 2 tubes are 42mm and 53mm (approx). Mitutoyo :evidence: told me that they do not have a bore gauge which covers both dimensions at the same time without changing gauging heads. This looks like a cookie cutter GR&R to me. So the question is; would you accept these GR&Rs knowing that they probably were not done on the material listed but done on a similar material with an unknown diameter.
To boot the % R&R was 17.1%

:thanks:
 
Elsmar Forum Sponsor

Jim Wynne

Staff member
Admin
#2
cslauenwhite said:
I have just received 2 PPAP submissions from a new supplier for two different size steel tubes. Going through the GR&Rs I noticed that the Inside Diameter GR&R for both size tubes are identical, number for number. I have looked for the gauge that they have listed on the report (Mitutoyo 3 pt bore gauge Model# 92865) but after contacting Mitutoyo evidence.gif there is no 92865 (they said that number might be a serial number off of the indicator).

The ID of the 2 tubes are 42mm and 53mm (approx). Mitutoyo evidence.gif told me that they do not have a bore gauge which covers both dimensions at the same time without changing gauging heads. This looks like a cookie cutter GR&R to me. So the question is; would you accept these GR&Rs knowing that they probably were not done on the material listed but done on a similar material with an unknown diameter.
To boot the % R&R was 17.1%

thankyou.gif
You don't say whether the GR&R was performed on one of the parts in question or not. If so, and the same gage and operators are used on both parts, it might be OK. It also might be OK if the study was just performed on a similar part. If surrogate data was used, it should have been discussed with you beforehand. Some other observations:

  • Repeatability is usually an issue with bore gages. My guess is that most of the 17% is due to it. 17% might be OK, depending on the application. Note that the fact that the supplier is reporting 17% is evidence that the results weren't fudged; fudged results will almost always be < 10%.
  • If the operators are responsible for setting the gage prior to use, they should also set it prior to the GR&R study. If someone else sets the gage, that person should set it for the study.
  • Is a bore gage necessary? There's an awful lot of variability involved, and the ID isn't going to be consistent along its entire length. Can pins be used instead?
  • Is the probe being used long enough to check at least half the entire lengths of the parts? There's no point in using a bore gage if the entire length of the part isn't being checked, in most cases.
  • Be aware that there may be conditions at the ends of the bore that the gage might not detect. The probes aren't fixed (i.e., they "telescope") so in inserting the gage it's easy to bypass displaced material at the ends.
 
G

gaugefixer

#3
The GR&R # of 17% sounds entirely possible using a 3 pt. bore gauge. I would ask them what the actual model # of the gauge was. It's possible they have said this gauge is #?????? and confused it with the actual model #.

One way to find out: Phone them and ask! :)
 
Thread starter Similar threads Forum Replies Date
C PPAP Submissions for Thermoplastic Resins (Bulk Material) APQP and PPAP 3
V PPAP Workbooks - Tool to help me organize my PPAP submissions APQP and PPAP 3
A PSO & PPAP Which one? Chrysler Submissions Customer and Company Specific Requirements 6
Z Are PPAP Submissions required to be in English? PPAP Language APQP and PPAP 6
J Machine issue in Cpk/Ppk and Control Plan - PPAP Submissions APQP and PPAP 5
antoine.dias Customer Specific Requirements and PPAP submissions APQP and PPAP 13
D Destructive Testing with respect to PPAP submissions APQP and PPAP 4
J Supplier not responding to PPAP request APQP and PPAP 5
J Part submission warrant for Level 1 PPAP APQP and PPAP 1
K Should APQP/PPAP has its own section in a QM? Quality Management System (QMS) Manuals 1
B Toyota PPAP Process - Three Questions APQP and PPAP 3
G Supplier delivered recent PPAP, should he deliver yearly layout inspection? IATF 16949 - Automotive Quality Systems Standard 4
F How to submit a PPAP when a subcontractor is the sole manufacturer IATF 16949 - Automotive Quality Systems Standard 2
P PPAP samples retention time IATF 16949 - Automotive Quality Systems Standard 5
K Updated MSA with the Annual PPAP validations APQP and PPAP 8
P Managing How PPAP Requirements are Communicated in the Manufacturing Process and to Suppliers APQP and PPAP 5
E Annual PPAP+ deviation request ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
K OEM specific requirements - PPAP was rejected by STA Customer and Company Specific Requirements 5
T PPAP for distributors? APQP and PPAP 1
A PPAP for Fire extinguisher APQP and PPAP 2
S PPAP Progress - Visual Status Board APQP and PPAP 0
C AS9145 Appendix D PPAP Approval Form APQP and PPAP 2
Pau Calvo PPAP customer requirements in the APQP APQP and PPAP 25
V 3 PQ lots mentioned as requirement in PPAP. Is this necessary? APQP and PPAP 2
B What is the role of Quality Engineer in APQP and PPAP APQP and PPAP 3
F How to submit PPAP without IMDS APQP and PPAP 10
GreatNate Excel PPAP Tracking templates or tool wanted APQP and PPAP 1
M Where can I find examples of PPAP? APQP and PPAP 6
R Process Specification - What is the name of this PPAP form? APQP and PPAP 15
I PPAP Assembly and Components Manufacturing and Related Processes 3
F PPAP Documentation Control APQP and PPAP 8
K PPAP Phases Vs PPAP Levels APQP and PPAP 2
R Plan to Volvo Cars for capacity verification in Phase 3 of PPAP Customer and Company Specific Requirements 3
G Job interview - So I have to do a presentation on PPAP APQP and PPAP 16
J AIAG PPAP: 2.2.11.3 Acceptance Criteria for Initial Study (page 9, 4th edition) APQP and PPAP 1
M Level 3 PPAP submission of intentional defective parts APQP and PPAP 4
L Reasons to submit a new PPAP or notify the customer APQP and PPAP 3
eule del ayre List of Level 3 PPAP requirements for automotive suppliers APQP and PPAP 20
A New Supplier implementation - PPAP vs APQP APQP and PPAP 9
E Nissan (Renault) PPAP Acronyms (DNote , KFD, IR) APQP and PPAP 2
N How to deal with catalog parts suppliers who refuse to submit PPAP documents? APQP and PPAP 0
N PPAP material certificate date IATF 16949 - Automotive Quality Systems Standard 4
P Paint shop vs PPAP requirements IATF 16949 - Automotive Quality Systems Standard 5
N How to resolve discrepancies in Level 3 PPAP supplier dimensional reports? APQP and PPAP 11
Sidney Vianna AS9100 News PPAP in the Aerospace Sector - What is it? AS9145 - Requirements for Advanced Product Quality Planning and Production Part Approval Process AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
D PPAP a Rebranded Purchased Product (we don't manufacture) IATF 16949 - Automotive Quality Systems Standard 6
E Solder thermal profiles for PPAP - Automotive IATF 16949 - Automotive Quality Systems Standard 1
P Automotive Customer asking PPAP for catalogue parts IATF 16949 - Automotive Quality Systems Standard 16
V PPAP documentation - Submission required in English APQP and PPAP 3
H Informational What is PPAP (Production Part Approval Process)? APQP and PPAP 26

Similar threads

Top Bottom