Process FMEA Ranking Table for for Landing Door of an Elevator

K

K.M.MOORTHI

#1
Dear frds,

I want to create the PFMEA for Landing door of Elevator. It is an non auto sector. Can anyone help me to rank the severity, occurence, and detection.

Pls give ur advice in this. Thanks in advance.

Regards,
K.M.Moorthi:bonk:
 
Elsmar Forum Sponsor

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#2
Re: FMEA Ranking Table for for Landing Door of an Elevator

To suggest rankings you would have to list the potential failure modes for us to look at.

And you have to decide how many levels - e.g. 1 through 5, or 1 through 10.
 
K

K.M.MOORTHI

#3
Dear Mr.Marc,

Thanks for your reply.. herewith i attached one excel file. I am not ranking it just simply filled it.
U can go thro it and suggest to ranking
how to rank?
 

Attachments

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#4
First thing to comes to my mind is a lot of high severity and low detection items. I did work with an elevator car manufacturer in 2002, but I'll look it over a bit closer later today.
 

Chennaiite

Never-say-die
Trusted Information Resource
#5
Dear Mr.Marc,

Thanks for your reply.. herewith i attached one excel file. I am not ranking it just simply filled it.
U can go thro it and suggest to ranking
how to rank?
With very little Customization, the Ranking Criteria provided in AIAG manual will hold good for your application, I guess. Have you tried applying them? And did you run into some difficulties in applying them?

Whatsoever is the criteria you will apply, just take a step back at the end of it and give opportunity for the intuition(of team) to judge the Rank (Risk). If the Ranking number does not line up with your intuition, more often your intuition could be right, in my view.
 
K

K.M.MOORTHI

#6
Dear marc,
thanks for ur immediate rly. I m also using the aiag manual. Nobody is experienced in FMEA in my organisation. Anyway thank u for ur input.

Regards,
K.M.Moorthi
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#7
I though I may have had something from 2002 but checked my files and no process FMEA. Sorry. If I remember correctly, the stuff on your FMEA was on theirs.

But - Like I said, I think you might want to think about detection methods.
 
K

K.M.MOORTHI

#8
Since our manufacturing is a project oriented. We are not manufacturing standard parts. Thats why we cant do any patrol or first off inspection. It will affect the production. Because there will be 30 or 40 setting per day. We can do only final inspection or self inspection by the operator.

Thats why i want to do a generic FMEA.

Regards
K.M.Moorthi
 
Thread starter Similar threads Forum Replies Date
N Process FMEA Occurrence Ranking for New Process FMEA and Control Plans 3
A Process FMEA - Help in deciding "detection ranking" of a failure mode FMEA and Control Plans 5
J Process FMEA Template with examples - Cold and Hot Forged components FMEA and Control Plans 4
C FMEA Process assessment In the Draft for the AIAG/VDA FMEA Manual is gone FMEA and Control Plans 0
Jimmy123 Example of a P-Diagram for Process FMEA - Uncontrollable noises FMEA and Control Plans 39
eule del ayre Merging FMEA and Quality Control Process Flow FMEA and Control Plans 0
K AIAG/VDA FMEA & Process Control Plans FMEA and Control Plans 0
S New AIAG FMEA Process - How to complete the new format FMEA and Control Plans 32
K PFMEA (Process FMEA) - Can be common for 3000 products? FMEA and Control Plans 2
D Where does FMEA fit in your ISO 14971 Risk Management process? ISO 14971 - Medical Device Risk Management 13
N In-Process Production Test Stations in PFMEA (Process FMEA) FMEA and Control Plans 18
G AIAG FMEA - Major customers of the FMEA process FMEA and Control Plans 3
E How do I create a FMEA for the Internal Audit process? Internal Auditing 11
D How to fill a Process FMEA - Three columns - Severity, occurrence and Detection FMEA and Control Plans 16
L Injection & Extrusion Process FMEA FMEA and Control Plans 1
S Pilot Process FMEA Occurence Rankings FMEA and Control Plans 4
G Severity in Process FMEA for Rework Process FMEA and Control Plans 1
R Is PFMEA (Process FMEA) for OEM sufficient to address Risk? ISO 13485:2016 - Medical Device Quality Management Systems 7
H FMEA sample for complete CNC machining process FMEA and Control Plans 1
T Software for linking Process Flow Diagram, Process FMEA and Control Plan APQP and PPAP 9
V Process FMEA for Stamping Process FMEA and Control Plans 5
G FMEA for Steel Tube Process for Automotive FMEA and Control Plans 4
L Most appropriate Auditor to check the FMEA & PCP of a Manufacturing Process IATF 16949 - Automotive Quality Systems Standard 5
C List Error Proofing in the Process FMEA or the Control Plan FMEA and Control Plans 2
J Process FMEA w/ Contracted Manufacturing ISO 14971 - Medical Device Risk Management 2
B FMEA example for Cokemaking Process at a integrated Iron and Steelmaking Plant IATF 16949 - Automotive Quality Systems Standard 3
S FMEA Process Step or Current Control FMEA and Control Plans 3
Z Pass-Though Characteristics in PFMEA (Process FMEA) FMEA and Control Plans 2
Q Chrysler required FMEA and Control Plan Document Audit Forms and Process Audit Check FMEA and Control Plans 7
V Examples of Design and Process FMEA for Pharmaceutical Product Development ISO 14971 - Medical Device Risk Management 7
S Galvanize and Chrome Plating Process FMEA wanted FMEA and Control Plans 2
S Product FMEA vs. Process FMEA - Aerospace Industry Machine Shop FMEA and Control Plans 5
R PFMEA (process FMEA) for Incoming Material stage FMEA and Control Plans 7
P PFMEA (Process FMEA) Recommended Actions help FMEA and Control Plans 9
J What is Incorporation in Assembly/Manufacturing Process in FMEA? FMEA and Control Plans 4
A Will Inspection Process need an FMEA? FMEA and Control Plans 7
F Process FMEA for Welding and Laser Cutting FMEA and Control Plans 3
G Very Basic PFMEA (Process FMEA) Guidelines FMEA and Control Plans 17
R Process to use Special Characteristics as FMEA Inputs IATF 16949 - Automotive Quality Systems Standard 3
M PFMEA (Process FMEA) - What is the best approach? FMEA and Control Plans 14
F FMEA Optimization for our Die Setup Process FMEA and Control Plans 2
M PFMEA (Process FMEA) for Attribute Data Inspection Process FMEA and Control Plans 2
A Current Control Periodic Document Reviews - Process Updates in the FMEA FMEA and Control Plans 3
T PFMEA (Process FMEA) Recommended Actions Column FMEA and Control Plans 10
B Process FMEA (PFMEA) Same Multiple Causes for Different Effects FMEA and Control Plans 6
M Changing PFMEA (Process FMEA) RPN Values based on a Rejection FMEA and Control Plans 5
Chennaiite FMEA for Business Process Imported Legacy Blogs 6
K Does FMEA include Inspection Process? FMEA and Control Plans 11
Q Using a Custom Process FMEA (PFMEA) Form FMEA and Control Plans 4
H What should be included in a Machining Process FMEA? FMEA and Control Plans 8

Similar threads

Top Bottom