Is there a requirement of a revision of FMEA once in six month this was what one of our customers raised during the audit?
No, there is no six months review requirement (unless this is written in your customer specific requirements,). However, the FMEA records are to be treated as living documents and should be reviewed and updated when changes in the design/process occur. (For good or bad). In short: your FMEA records must reflect the current state of the Process and/or Design.

Hope this helps.

Stijloor.
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#3
Re: FMEA Revision Requirements

Is there a requirement of a revision of FMEA once in six month this was what one of our customers raised during the audit?
Just to clarify since you do not specify, you are referring to Process FMEAs, correct?
 
D

Duke Okes

#4
Re: FMEA Revision Requirements - Every six months?

FMEAs should be updated when:

- design of product is changed
- design of process is changed
- information becomes available that indicates a failure mode is missing, or a severity ranking is inaccurate, or a cause is missing, or probability of occurrence is inaccurate, etc. Such information may come about based on field failures, computer modeling, statistical studies, etc.
 
S

suffelde

#5
Re: FMEA Revision Requirements - Every six months?

Some companies also require that when there is corrective action taken, the preventive action is documented in the FMEA whether the action be product (DFMEA) or process related. Also, for Critical or Key Characteristics which have high RPN numbers, it is hard to justify not applying improvement over a long period of time.
 

paomaxb

Starting to get Involved
#7
Re: FMEA Revisions

I dare to refer about some TS Auditor's reports asking of minimum yearly update or review PFmea of automotive components. In your opinion is this a right request or only a little abuse of power?
 
S

suffelde

#8
Re: FMEA Revisions

Unless it is a specific customer's requirement, then there is no specified time period. It is a living document and one should expect that it doesn't lie dormant with no activity. As a part of the continuous improvement process one could show a review of the PMEA documenting any actions to take no actions so to speak. Documentation of this sort would show that the PFMEA process is effectively implemented. Be careful that the audit trail doesn't go to the Nonconformance Log to see if all failure modes indeed have been captured and dealt with on the PFMEA.
 
D

Duke Okes

#9
Re: FMEA Revisions

I dare to refer about some TS Auditor's reports asking of minimum yearly update or review PFmea of automotive components. In your opinion is this a right request or only a little abuse of power?
It is most likely an auditor trying to push his/her opinion on the company, rather than allowing the company to meet the TS requirements as it requires and they deem useful for their organization. Unfortunately this introduction of auditor requirements/expectations happens a lot more often than it should.
 

paomaxb

Starting to get Involved
#10
Re: FMEA Revisions

ok, Dave. My doubt was if in any of the sacred books by AIAG there is a requirements about periodicity. I think anyway it's hard to claim that in a long period (1 year but maybe even in 6 months) no change has occured in any component (material, procedure, HR, machine) of the process in order to update last PFMEA.
 
Thread starter Similar threads Forum Replies Date
J Process FMEA Template with examples - Cold and Hot Forged components FMEA and Control Plans 4
C FMEA Process assessment In the Draft for the AIAG/VDA FMEA Manual is gone FMEA and Control Plans 0
Jimmy123 Example of a P-Diagram for Process FMEA - Uncontrollable noises FMEA and Control Plans 39
eule del ayre Merging FMEA and Quality Control Process Flow FMEA and Control Plans 0
K AIAG/VDA FMEA & Process Control Plans FMEA and Control Plans 0
S New AIAG FMEA Process - How to complete the new format FMEA and Control Plans 32
K PFMEA (Process FMEA) - Can be common for 3000 products? FMEA and Control Plans 2
D Where does FMEA fit in your ISO 14971 Risk Management process? ISO 14971 - Medical Device Risk Management 13
N In-Process Production Test Stations in PFMEA (Process FMEA) FMEA and Control Plans 18
N Process FMEA Occurrence Ranking for New Process FMEA and Control Plans 3
G AIAG FMEA - Major customers of the FMEA process FMEA and Control Plans 3
E How do I create a FMEA for the Internal Audit process? Internal Auditing 11
D How to fill a Process FMEA - Three columns - Severity, occurrence and Detection FMEA and Control Plans 16
L Injection & Extrusion Process FMEA FMEA and Control Plans 1
S Pilot Process FMEA Occurence Rankings FMEA and Control Plans 4
K Process FMEA Ranking Table for for Landing Door of an Elevator FMEA and Control Plans 7
G Severity in Process FMEA for Rework Process FMEA and Control Plans 1
R Is PFMEA (Process FMEA) for OEM sufficient to address Risk? ISO 13485:2016 - Medical Device Quality Management Systems 7
H FMEA sample for complete CNC machining process FMEA and Control Plans 1
T Software for linking Process Flow Diagram, Process FMEA and Control Plan APQP and PPAP 9
V Process FMEA for Stamping Process FMEA and Control Plans 5
G FMEA for Steel Tube Process for Automotive FMEA and Control Plans 4
L Most appropriate Auditor to check the FMEA & PCP of a Manufacturing Process IATF 16949 - Automotive Quality Systems Standard 5
C List Error Proofing in the Process FMEA or the Control Plan FMEA and Control Plans 2
J Process FMEA w/ Contracted Manufacturing ISO 14971 - Medical Device Risk Management 2
B FMEA example for Cokemaking Process at a integrated Iron and Steelmaking Plant IATF 16949 - Automotive Quality Systems Standard 3
S FMEA Process Step or Current Control FMEA and Control Plans 3
Z Pass-Though Characteristics in PFMEA (Process FMEA) FMEA and Control Plans 2
Q Chrysler required FMEA and Control Plan Document Audit Forms and Process Audit Check FMEA and Control Plans 7
V Examples of Design and Process FMEA for Pharmaceutical Product Development ISO 14971 - Medical Device Risk Management 7
S Galvanize and Chrome Plating Process FMEA wanted FMEA and Control Plans 2
S Product FMEA vs. Process FMEA - Aerospace Industry Machine Shop FMEA and Control Plans 5
R PFMEA (process FMEA) for Incoming Material stage FMEA and Control Plans 7
P PFMEA (Process FMEA) Recommended Actions help FMEA and Control Plans 9
J What is Incorporation in Assembly/Manufacturing Process in FMEA? FMEA and Control Plans 4
A Will Inspection Process need an FMEA? FMEA and Control Plans 7
F Process FMEA for Welding and Laser Cutting FMEA and Control Plans 3
G Very Basic PFMEA (Process FMEA) Guidelines FMEA and Control Plans 17
R Process to use Special Characteristics as FMEA Inputs IATF 16949 - Automotive Quality Systems Standard 3
M PFMEA (Process FMEA) - What is the best approach? FMEA and Control Plans 14
F FMEA Optimization for our Die Setup Process FMEA and Control Plans 2
M PFMEA (Process FMEA) for Attribute Data Inspection Process FMEA and Control Plans 2
A Current Control Periodic Document Reviews - Process Updates in the FMEA FMEA and Control Plans 3
T PFMEA (Process FMEA) Recommended Actions Column FMEA and Control Plans 10
B Process FMEA (PFMEA) Same Multiple Causes for Different Effects FMEA and Control Plans 6
M Changing PFMEA (Process FMEA) RPN Values based on a Rejection FMEA and Control Plans 5
Chennaiite FMEA for Business Process Imported Legacy Blogs 6
K Does FMEA include Inspection Process? FMEA and Control Plans 11
Q Using a Custom Process FMEA (PFMEA) Form FMEA and Control Plans 4
H What should be included in a Machining Process FMEA? FMEA and Control Plans 8

Similar threads

Top Bottom