Quality planning sign-off in AIAG APQP Manual

hopech

Involved In Discussions
hello,
please I need some clarifications about Appendix F-Quality planning summary and sign-off
I read its instructions but i'm pretty confused and I don't understand exactly how to fill in it

thak you in advance !
 

morteza

Trusted Information Resource
Hi,
Appendix E is for sign-off.
The form is clear for filling. Your question is general and if you specify which sections need to be clarified, it would be easier to comment.
 

hopech

Involved In Discussions
Hi,
thanks for replying
i would like to know how to fill in tables
for example : 1. Ppk
spaciel characteristics
under required I mention the value of Ppk for each special characteristic

If you have an exemple of a completed quality sign off it would be very helpfull
thank you
 

morteza

Trusted Information Resource
Hi,
For Ppk, under the "required" you should write the number of characteristics which have to be studied,
"Acceptable" shows the number of the characteristics which their capability results are acceptable.
"Pending" shows the number of the characteristics which their capability results are not acceptable.

1643306197656.png
 

hopech

Involved In Discussions
Hello,
thak you for the clarification
what about the last two tables
process monitoring and packaging/shipping

thank you
 

morteza

Trusted Information Resource
Hi,
These tables are the same as each other. For example, in the process monitoring table:
How many visual aids shall be provided (i.e. required)? 10
How many have been provided and accepted? 9
How many have not been accepted? 1
 
Top Bottom