Hi All

We currently have a flow chart for incoming goods inspection which details the process from start to finish.

The lady that looks after this process used to follow the flow chart, but it seems that she has has not being applying the inspection labels. The detail on the labels is basic - Item which is essentially a 'COTS' number, Qty received and initials and a 'Green' Sticker which states that it has been checked for basics...correct item, correct quantity.
Other items where required go through a 'Special Inspection'.

On a recent internal audit of one of our areas I found some goods that had come in that bear no labels whatsoever, it's only that the area use these on a regular basis that they knew what they were. So I wrote them up an NCR. When I spoke to the lady she said she no longer applies labels 'it's too time consuming'!

I have no support from management, they just say well it's not the end of the world, we're only a small company - but that is not the point! (Insert angry/frustrated face) :argue:

What should I do?

How do other manufacturing businesses treat incoming goods?
FYI we have no real lean system here we use basic excel spreadsheets and Reckon Quickbooks for Purchase Orders, so it is a very manual system.

Any advice would be appreciated. BTW the QM is away on Annual Leave
 
Last edited:
Elsmar Forum Sponsor

howste

Thaumaturge
Super Moderator
#2
Hi All

We currently have a flow chart for incoming goods inspection which details the process from start to finish.

The lady that looks after this process used to follow the flow chart, but it seems that she has has not being applying the inspection labels. The detail on the labels is basic - Item which is essentially a 'COTS' number, Qty received and initials and a 'Green' Sticker which states that it has been checked for basics...correct item, correct quantity.
Other items where required go through a 'Special Inspection'.

On a recent internal audit of one of our areas I found some goods that had come in that bear no labels whatsoever, it's only that the area use these on a regular basis that they knew what they were. So I wrote them up an NCR. When I spoke to the lady she said she no longer applies labels 'it's too time consuming'!

I have no support from management, they just say well it's not the end of the world, we're only a small company - but that is not the point! (Insert angry/frustrated face) :argue:

What should I do?

How do other manufacturing businesses treat incoming goods?
FYI we have no real lean system here we use basic excel spreadsheets and Reckon Quickbooks for Purchase Orders, so it is a very manual system.

Any advice would be appreciated. BTW the QM is away on Annual Leave
Why does management have you do internal audits if they don't want to take action on the results? :confused: It certainly seems that the NCR is justified just based on them not following their instructions. In addition, if there is a possibility of them using the wrong part/product due to lack of labeling, it could be a much bigger issue.

Is your company certified to ISO 9001 or another QMS standard? If so you can go to ISO 9001:2008 clause 7.5.3 which says "Where appropriate, the organization shall identify the product by suitable means throughout product realization. The organization shall identify the product status with respect to monitoring and measurement requirements throughout product realization."
 

Ninja

Looking for Reality
Trusted Information Resource
#3
From my distant vantage point, you have two options:
Both result in correcting the situation, and both close out your NC effectively.

1. Do what it takes to have the current approved process requirement followed by all employees "following" that process.

2. Change the requirement to fit current practice.

If Mgmt says "it's not the end of the world, we're only a small company", then this is an indication that there is a documented requirement that Mgmt doesn't necessarily care about...it begs the question why it is a requirement anymore.

A. Verify with Mgmt that it is OK for ALL employees to skip this step from now on.
B. If not...no one can.
B2. If so, update the procedure accordingly, retrain, and close out your NC.

We tend to look for "management support" in a limited way...
I would take (but verify) that Mgmt DID support the QMS by changing a requirement to more closely fit what the company places value on.
If this is the case (make sure).... clean up the paperwork behind the policy change.
 

Ninja

Looking for Reality
Trusted Information Resource
#5
LOL...good one.
Preaching to the choir: It is never OK to skip the step of following written instruction. The written instructions can be pointless though.

One of my tenets -
One should disagree from a position of obedience in order to create change.
Disagreement from a position of disobedience is not called "change", it is called "justification"...and rarely accomplishes much.

"I just wasted 2 hours complying" is a more effective tool than "It was a waste of time so I didn't do it".

In the case of the OP...I would look at both changing the system (if that's what mgmt actually wants) together with some form of discipline.
It could have been just a system change...
 

auditorsos

Starting to get Involved
#6
Thanks for your input. Quite the QM really doesn't want ISO9001, but we have to have it for the nature of the business, supply to, in the main military.

It is a lacks approach, and I find it really frustrating; in a conversation either you want me to audit the areas and do it correctly, or not do it at all.

The QM just responds with 'we look when I am back'! :mad: He doesn't allow me to think on my own two feet and address the issue - that's the issue with this company they are so set in their ways and do not like change!

Rant over, but will take on board your views, thank you.
 

Ninja

Looking for Reality
Trusted Information Resource
#7
There is a way you want to be.
There is a way that it is.

The friction between these two is where both frustration and opportunity come from.

1. Take your moment of frustration for as long as you want.
2. When you're over it...plan your path from one to the other.
3. Then get others on board with your plan...or let them suggest modifications to your plan...or both.
4. Then get on with the progress.

Stopping in the zone of frustration helps no one...least of all, you.
You don't have to spend your career in that zone, and who would want to?
:2cents:

{Don't skip step 3, or you're right back in the frustration zone}
 

6 SIGMA

Inactive Registered Visitor
#9
Everybody must follow procedure. If applying labels it too time consuming, she cannot just stop doing it. See if the labels offer value and enforce the procedure if they do.

At our location we have our suppliers place all necessary labels on the containers and, once they have been successfully through receiving inspection three times, we make them dock to stock.

Some may perceive this as a risk, but our suppliers are previously approved, know what is expected, proven to pass the review and receiving processes and are all ISO registered so they know what to do.
 
Thread starter Similar threads Forum Replies Date
Q Inventory and FIFO in our goods receiving area Lean in Manufacturing and Service Industries 3
R AS9100 - 8.4.2 - Receiving Inspection Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
Skooma Receiving Inspection - Boss trying to save money AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 7
J Requirements for Layered Process Audits including Maintenance, Shipping, Receiving IATF 16949 - Automotive Quality Systems Standard 4
I Receiving Inspection Requirement in IATF IATF 16949 - Automotive Quality Systems Standard 3
D Incoming (Receiving) Inspection - General form for incoming part inspection Document Control Systems, Procedures, Forms and Templates 17
D Minor non-conformance for not receiving a CofC from a heat treater Manufacturing and Related Processes 10
V Receiving Inspection AQL - Am I allowed to just pick a AQL? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 10
M Controls for Suppliers of Translation Services - Receiving and Verification Supplier Quality Assurance and other Supplier Issues 5
C Receiving Gage Design Inspection, Prints (Drawings), Testing, Sampling and Related Topics 3
J Receiving Inspection for Metal Strips & Wires Inspection, Prints (Drawings), Testing, Sampling and Related Topics 7
T Example Training Checklist for Receiving Inspector Training - Internal, External, Online and Distance Learning 3
L Objectives for Receiving Inspection (Resources) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
J Hardware Receiving Inspection AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 12
N Receiving Inspection - Who should receive raw material Inspection, Prints (Drawings), Testing, Sampling and Related Topics 12
J ISO 17025 testing laboratory - Receiving lab supplies - What really needs a C of A? ISO 17025 related Discussions 2
kedarg6500 Use of safety glasses at receiving inspection Occupational Health & Safety Management Standards 7
L How do you specify your receiving inspection parameters? Misc. Quality Assurance and Business Systems Related Topics 2
R Warehouse and shipping/receiving activities need to be part of our scope? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 28
A Receiving paper from the customer and never knowing when it will arrive Quality Manager and Management Related Issues 1
D Receiving Inspection Training Materials Inspection, Prints (Drawings), Testing, Sampling and Related Topics 7
S So Annoyed with Receiving Inspection! Inspection, Prints (Drawings), Testing, Sampling and Related Topics 16
A MIL STD 105 D or ISO 2859-2? Receiving Metal Sheets Quality Tools, Improvement and Analysis 6
C ISO13485 Incoming Receiving Parts Verification ISO 13485:2016 - Medical Device Quality Management Systems 13
R Minimum Essential Receiving Inspection (M.E.R.I.) Inspection, Prints (Drawings), Testing, Sampling and Related Topics 3
M Definition Receiving Inspection of Parts, finished products, service parts etc. Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 6
kedarg6500 Receiving Inspection Documentation Best Practices Supplier Quality Assurance and other Supplier Issues 2
L Must we do Receiving Inspection for everything? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 15
M Does 21 CFR 820.80 (b) require a Supplier to have Receiving Inspection? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 13
M Calculating Adequate Receiving Inspection Sample Size Statistical Analysis Tools, Techniques and SPC 2
L How to define R & D Receiving (Incoming) Inspection Plan Design and Development of Products and Processes 18
M Receiving Inspection of Customer Owner Property IATF 16949 - Automotive Quality Systems Standard 5
M Partial Incoming (Receiving) Inspection Delivery Inspection. Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
alonFAI Establishing a Receiving Inspection Procedure Document Control Systems, Procedures, Forms and Templates 5
R Where are shipping & receiving processes covered under TS 16949 IATF 16949 - Automotive Quality Systems Standard 3
F Receiving a new Gage Block Set with an old Certificate Calibration Frequency (Interval) 3
S Ensuring Print Dimensions are in Control Plans, WI's and Receiving Inspection Document Control Systems, Procedures, Forms and Templates 3
S How to calculate Supplier PPM at Receiving Inspection Document Control Systems, Procedures, Forms and Templates 2
C Supplier Management and Receiving Inspection Improvement Statistical Analysis Tools, Techniques and SPC 20
D Centralizing the Receiving and Storage of Electronic Customer Data Document Control Systems, Procedures, Forms and Templates 1
Q Receiving Inspection - Quantity Received different from Pack List & C of C AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
D Can we Advertise ISO/TS 16949:2009 Certification before receiving the Certificate? IATF 16949 - Automotive Quality Systems Standard 19
JoCam Moisture Control - Receiving Moisture Sensitive Electronic Components AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 11
C Receiving Raw Materials, Inspection, Release Inspection, Prints (Drawings), Testing, Sampling and Related Topics 8
G Reduced Receiving Inspection - Now What Inspection, Prints (Drawings), Testing, Sampling and Related Topics 12
M Incoming (Receiving) Inspection Procedure - Please Review Supplier Quality Assurance and other Supplier Issues 7
P Random Sampling at Receiving Inspection: A Practical Implementation needed Inspection, Prints (Drawings), Testing, Sampling and Related Topics 13
M How to Eliminate Receiving Inspection Supplier Quality Assurance and other Supplier Issues 10
K LEAN in the Incoming/Receiving Department Lean in Manufacturing and Service Industries 9
A Receiving Inspection - One drum leaks - Should entire lot be rejected? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 5

Similar threads

Top Bottom