Our transition from ISO 9001 to AS 9100 (revision B) meant that we had to create and document several new processes (Raw Material Validation, Production Tool Validation, etc.). Even though we have known the certification schedule for several months, things being what they are, the processes weren't documented until recently.
I was very concerned that I wouldn't have records of these new processes for our upcoming certification audit. However I have been told that you just need to have the process documented for the certification audit and evidence for the following surveillance audit. Sound correct?