#11
Remember that you don't have to create all new documents everytime. You can carry over pertinent records from previous submissions.
That's correct as long as they reflect "the current state of affairs."

Many PPAP documents are considered "living" documents and must represent the current state of the product/process.

Stijloor.
 
Elsmar Forum Sponsor

Kales Veggie

People: The Vital Few
#12
Re: Requirements in TS for PPAP

PPAP is required.

From ISO/TS 16949:2002:

7.3.6.3 Product approval process

The organization shall conform to a product and manufacturing process approval procedure recognized by the customer.

NOTE Product approval should be subsequent to the verification of the manufacturing process.

This product and manufacturing process approval procedure shall also be applied to suppliers.


The PPAP manual provides the details.

The Customer determines the submission level.

You must have all PPAP items available, whether or not the Customer requires submission. (See PPAP for the specifics.)

Stijloor.
To be sure. TS does not require AIAG PPAP. It requires a product approval process. The CSR (such as Ford, published on the IATF / IAOB website) invokes the AIAG PPAP manual.

Any AIAG PPAP submission level requires you to do all the work. There is a table in the PPAP manual with R (retain) and S (submit) for the different levels. CSR usually defines the default PPAP level. Other submission level is only valid if you receive it in writing from your customer (authorized person, for example for Ford it is the STA).

TS allows another customer product approval process (such as VDA PPA).
 

Stijloor

Staff member
Super Moderator
#13
Re: Requirements in TS for PPAP

To be sure. TS does not require AIAG PPAP. It requires a product approval process. The CSR (such as Ford, published on the IATF / IAOB website) invokes the AIAG PPAP manual.

Any AIAG PPAP submission level requires you to do all the work. There is a table in the PPAP manual with R (retain) and S (submit) for the different levels. CSR usually defines the default PPAP level. Other submission level is only valid if you receive it in writing from your customer (authorized person, for example for Ford it is the STA).

TS allows another customer product approval process (such as VDA PPA).
Kees,

I responded with the OP's situation in mind. I should have mentioned that.

Jan.
 
C

chaosweary

#15
Whew, I am glad Kales replied with that. I just had a meeting last week where I told people in MFG that they didn't have to do an AIAG PPAP to get ISO TS certified. In fact I told them if the customer requirements are not in the contract and specifically cite the AIAG requirements we don't have to follow them. Too many times we have are in full production and some smart butt supplier quality engineer shows up with a PHD degree (VDO), telling us we have to do PPAPs to the AIAG after the fact. I head straight to the contractual agreement, boy does that give off a frown. Luckily we have a monopoly on the patent...:D
 
Thread starter Similar threads Forum Replies Date
P Managing How PPAP Requirements are Communicated in the Manufacturing Process and to Suppliers APQP and PPAP 5
K OEM specific requirements - PPAP was rejected by STA Customer and Company Specific Requirements 5
Pau Calvo PPAP customer requirements in the APQP APQP and PPAP 25
eule del ayre List of Level 3 PPAP requirements for automotive suppliers APQP and PPAP 20
P Paint shop vs PPAP requirements IATF 16949 - Automotive Quality Systems Standard 5
Sidney Vianna AS9100 News PPAP in the Aerospace Sector - What is it? AS9145 - Requirements for Advanced Product Quality Planning and Production Part Approval Process AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
M Annual Layout requirements for PPAP/Control Plan FMEA and Control Plans 6
G Supply Chain PPAP Requirements APQP and PPAP 10
P Automotive Supplier PPAP Level Requirements Supplier Quality Assurance and other Supplier Issues 12
G PPAP 4th edition or VDA - VW Requirements APQP and PPAP 2
Y Customer Specific PPAP Level 3/4 Requirements - Fastener Manufacturer APQP and PPAP 2
A Cost of Deviating Away From PPAP Requirements APQP and PPAP 3
V Inactive Gauge Retention Time - PPAP Section 6 Requirements APQP and PPAP 1
I AS9100 PPAP requirements for outside Heat Treat vendors/suppiers AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
M PPAP requirements when adding Part Transfer Robots between Machines APQP and PPAP 1
P Bulk Material Requirements Checklist to send along with my PPAP APQP and PPAP 2
B Bulk Materials (Lead {Pb} Alloys) PPAP Requirements APQP and PPAP 5
T PPAP Requirements for Contract Manufacturers APQP and PPAP 4
J PPAP (Production Part Approval Process) Requirements for Annual Revalidations APQP and PPAP 1
V PPAP Requirements including GMW 3179 Zinc Plating Specification Requirements APQP and PPAP 3
V PPAP Requirements for Plating a "Family of Parts" APQP and PPAP 8
P PPAP Requirements for Sub-Assemblies APQP and PPAP 6
V Plating Supplier PPAP Revalidation Requirements - A-Coat GM 9984132 Plating Process APQP and PPAP 1
V PPAP - Requirements when Cpk is <1.67 - 100% Sort for Defectives APQP and PPAP 8
R Does anyone have the list of Toyota PPAP requirements? APQP and PPAP 6
M For Bulk Material (eg. paint), are there any guidelines for Ford PPAP Requirements? APQP and PPAP 1
B TS16949 Annual PPAP Submission Requirements for Ford and Chrysler Parts IATF 16949 - Automotive Quality Systems Standard 2
B TS 16949 PPAP/ Layout Inspection Frequency Requirements APQP and PPAP 8
Q Level of PPAP - Bulk Chemicals Supplier Requirements APQP and PPAP 2
F PPAP Material Test Results Requirements - Material Supplier Identification QS-9000 - American Automotive Manufacturers Standard 1
S PPAP Requirements for Submission to our Customers for a New Supplier APQP and PPAP 1
Q Supplier PPAP Requirements - TS 16949 Clause 7.3.6.3 IATF 16949 - Automotive Quality Systems Standard 12
S Can PPAP be submitted when not all customer requirements can be met? APQP and PPAP 5
K Supplier PPAP Requirements - Level 3 or Level 4 APQP and PPAP 6
J PPAP Requirements - Suppliers who are changing their Suppliers APQP and PPAP 7
L PPAP List Requirements - Molds, Tools or the Checking Tools? APQP and PPAP 5
J Requirements for Retaining PPAP Master Samples APQP and PPAP 2
J Prior Notice of Sub-Supplier or Material Source Change - PPAP Requirements Question APQP and PPAP 13
J PPAP Requirements Question APQP and PPAP 4
S PPAP requirements for sub-suppliers APQP and PPAP 5
C Honda PPAP requirements APQP and PPAP 8
S Are the AIAG document (FMEA, PPAP, SPC, MSA, APQP) guidelines or requirements FMEA and Control Plans 6
K PPAP Requirements for Raw / Bulk Materials? APQP and PPAP 6
R GM revised its Specific Requirements for TS16949 and PPAP 4th, effective immediately Customer and Company Specific Requirements 4
B PPAP Document Submission and Retention requirements APQP and PPAP 21
B PPAP Requirements - Laboratory results and IMDS system RoHS, REACH, ELV, IMDS and Restricted Substances 12
M DaimlerChrysler (DCX) Customer Specific Requirements for PPAP 4th Edition Customer and Company Specific Requirements 8
Sidney Vianna Chrysler Customer Specific Requirements For PPAP 4th Edition IATF 16949 - Automotive Quality Systems Standard 10
antoine.dias Customer Specific Requirements and PPAP submissions APQP and PPAP 13
T PPAP requirements - Supplier's supplier's quality certificate and IMDS documentation RoHS, REACH, ELV, IMDS and Restricted Substances 31

Similar threads

Top Bottom