Elsmar Forum Sponsor

Ron Rompen

Trusted Information Resource
#2
I would question the 'Does not require customer approval' statement. Although this may (generally) be true, there may be exceptions to that.

Eg. Parts are electroplated and are stored in WIP for a period of 45 days. Prior to shipment, dock audit detects that the surface roughness of the parts is unacceptable.

In consultation with the coating supplier, it is determined that parts need to be stripped and replated.

Strip method is to acid wash, followed by 'burn', followed by wash, followed by re-plate and reinspect.

Parts are SAE4130, hardened to HRc 38-44. There is a potential risk for the following failures:
i) Hydrogen embrittlement (yeah, I know, but they raised that one one me)
ii) Tempering of hardness to below the lower limit (hardness is an SC)
iii) Pitting of part surface, leading to stress risers (this one is a REAL stretch on the part of the design engineer, but I don't have the knowledge to refute it).

The reasons above (if nothing else) are sufficient cause to notify the customer of your 'rework' process, and obtain acquiesence, if not outright approval.

JMO
 

Jim Wynne

Staff member
Admin
#3
Ron,

You raise an excellent point. I have been in situations where bad things happened because of exactly the sort of metallurgical phenomena you describe. Speaking from a customer standpoint, I want to know when rework is going on for this type of reason, but also because if it gets to be a habit, sooner or later I'm going to pay for it. Realistically, suppliers aren't going to notify customers when they've screwed up, especially if they think that they can rework material without causing any problems for the customer. But as this case shows, there are times when the supplier may lack the expertise or general knowledge to know when what seems to be innocuous rework can cause problems. The solution? A contractual obligation for the supplier to divulge. That won't cause the supplier to divulge in every instance, but it does provide a measure of liability protection if something goes wrong.
 
J

Jim Howe

#5
rework vs. repair

Ron Rompen said:
I would question the 'Does not require customer approval' statement. Although this may (generally) be true, there may be exceptions to that.

Eg. Parts are electroplated and are stored in WIP for a period of 45 days. Prior to shipment, dock audit detects that the surface roughness of the parts is unacceptable.

In consultation with the coating supplier, it is determined that parts need to be stripped and replated.

Strip method is to acid wash, followed by 'burn', followed by wash, followed by re-plate and reinspect.

Parts are SAE4130, hardened to HRc 38-44. There is a potential risk for the following failures:
i) Hydrogen embrittlement (yeah, I know, but they raised that one one me)
ii) Tempering of hardness to below the lower limit (hardness is an SC)
iii) Pitting of part surface, leading to stress risers (this one is a REAL stretch on the part of the design engineer, but I don't have the knowledge to refute it).

The reasons above (if nothing else) are sufficient cause to notify the customer of your 'rework' process, and obtain acquiesence, if not outright approval.

JMO
Ron,
Your example is exactly why the rework/repair and/or MRB authority is negotiated upfront with the customer. I doubt that the original specification for the plate called for an acid wash to strip. This very act would classify this as a repair not a rework (imo) and so would require customer approval.

Again, imo, (from many years on MRB) these kind of situations were exactly why MRB was composed of a cross section of talent including design engineering, quality engineering and yes in many cases the customer. It helped prevent the declaration of rework in the face of a repair.

I might add that some WS (weapon specifications) for soldering considered the act of reflowing a solder joint on a PCB a repair where MIL-S solder specs considered this to be rework. The WS's position was that the very act of putting heat to the solder joint could very well degrade the fiberglass board material. Under the WS a simple solder touch up was often referred to MRB. In another version of WS when solder joint touch ups surpassed three the PCB was then sent to MRB for disposition. Again all pre-negotiated with the Customer. :2cents:
 
W

wslabey

#6
All are excellent points. We also do aviation work governed by the FAA here at our facility. Rework / repair all have to be approved according to the original design (which always includes the blueprint dimensions and how the part or component is made). A non-conforming part (at any stage of manufacture) is dispositioned in the MRB and any rework or repair must follow a specific, pre-approved procedure (if allowed at all). If rework is done without approval the part or parts are quarantined until the customer (FAA or other) approves the rework or repair procedure.

Why so stringent? The answer is simple. No one wants to be asked to explain a smoking hole in the ground when a airplane crashes due to your rework or repair procedure.
 
Last edited by a moderator:
S

shala

#8
Hi
I have a question regarding rework or reprocess. When we want to remove the wrong labels and replace it with correct one, is it considered as rework or reprocess?
we will do the same steps for printing out and attaching labels but what about removing the wrong labels?
Thank you.
 
Q

qpled

#9
Hi
I have a question regarding rework or reprocess. When we want to remove the wrong labels and replace it with correct one, is it considered as rework or reprocess?
we will do the same steps for printing out and attaching labels but what about removing the wrong labels?
Thank you.
Hi Shala,
When I need to do this I use the term "rework" in my records.
 
P

PaulJSmith

#10
Hi, shala:
I suppose it really depends on what exactly encompasses your "relabeling" process. If it's as simple as peeling off one label and applying another, calling it rework would be just fine. If it's a more involved process, requiring assertive cleaning or scraping which might potentially harm the product, then the answer is no longer a basic issue of semantics.

As for using the word "reprocess," that almost always insinuates the reapplication of some special process (e.g. heat treating), so this probably wouldn't be the best use for that word.
 
Thread starter Similar threads Forum Replies Date
A Definition Rework vs. Repair - ISO 13485 definition Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 11
J Rework or Recall 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 10
T ISO 13485 8.3 - Non-Conforming Materials - on-line rework or part of process? ISO 13485:2016 - Medical Device Quality Management Systems 11
G Rework, Reprocess, or Correction - A simple blurred letter on the legible etching ISO 13485:2016 - Medical Device Quality Management Systems 4
A AS9102 Delta FAI Require after Rework stock item from stock AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
N Generic Rework/Reprocessing Procedure Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 1
L I need an example rework procedure/instruction for injected plastic parts Document Control Systems, Procedures, Forms and Templates 2
M IATF 16949 Cl. 8.7.1.4 - Risk analysis for decision making about rework IATF 16949 - Automotive Quality Systems Standard 2
T Is Sorting a kind of Rework? IATF 16949 - Automotive Quality Systems Standard 3
M IATF 16949 Clause 8.3 - Rework Records Requirements IATF 16949 - Automotive Quality Systems Standard 1
G Severity in Process FMEA for Rework Process FMEA and Control Plans 1
M What is the value of documenting in-process rework for easily-detectable issues? Quality Manager and Management Related Issues 4
G Rework requirement in ISO 13485 ISO 13485:2016 - Medical Device Quality Management Systems 5
R How to document the Risk Management on Rework activities ? ISO 14971 - Medical Device Risk Management 6
S Regulatory Approval(s) for Rework Dispositions Nonconformance and Corrective Action 2
B Definition Sort vs. Rework - Differences and Definitions Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 9
B Form to use for Rework including Verification of Effectiveness of the Rework Inspection, Prints (Drawings), Testing, Sampling and Related Topics 2
S How to establish a Sampling Plan from the Rework percentage? AQL - Acceptable Quality Level 6
A Nonconformances and Rework in a Machine Shop Nonconformance and Corrective Action 6
X Help with ISO 13485 Clause 8.3 "Rework" as applicable to Medical Device Servicing ISO 13485:2016 - Medical Device Quality Management Systems 39
D Rework Authorization Form example Manufacturing and Related Processes 5
R Medical Device Circuit Board Component Changes - Is this rework or not? ISO 13485:2016 - Medical Device Quality Management Systems 8
M Rework Devices placed on the market - IEC 60601-1 Requirements 3rd edition IEC 60601 - Medical Electrical Equipment Safety Standards Series 7
D Lean Management applied to Rework Zones Lean in Manufacturing and Service Industries 8
Q Documenting the Review of Adverse Effects from Rework ISO 13485:2016 - Medical Device Quality Management Systems 4
Q ISO 9001 Clause 8.3 Rework Verification - Re-verification to demonstrate conformity ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
B Soldering Training (specific to Rework and Repair of PCBs) - Long Island Training - Internal, External, Online and Distance Learning 5
P Requirements for Approval of Rework Work Instructions ISO 13485:2016 - Medical Device Quality Management Systems 6
Q Dispositions In Claims and Complaints - "Use as is, Repair, Rework, etc" ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
Q Use As Is, Repair, Rework - Useful when categorizing? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
Q ISO 9001 Clause 8.3: Scrap, Rework, Repair, Why? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
M Can sorted returns be returned to stock. Do they need a rework label? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
J Definition Servicing circuit boards - Differences between Rework and Repair Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 9
A Is Rework "Inspecting Quality In"? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 7
B Overhaul vs. Repair vs. Rework - FAA Definitions Federal Aviation Administration (FAA) Standards and Requirements 7
G Numbers that will help us understand what the Cost of Rework is Misc. Quality Assurance and Business Systems Related Topics 7
T Definition Rework vs. Repair in ISO/AS9100 Definitions, Acronyms, Abbreviations and Interpretations Listed Alphabetically 8
B Define "Rework" Under Medical Device Standards ISO 13485:2016 - Medical Device Quality Management Systems 10
P Rework Notification - Is it sufficient to show how we control rework process Manufacturing and Related Processes 1
T Rework Traceability System Manufacturing and Related Processes 8
A Scrap vs. Rework Classification - Scraping the resistor or reworking the PCB board? Quality Tools, Improvement and Analysis 10
L Quality Objectives Ideas - Currently we have Scrap & rework, OTD, survey results, etc Manufacturing and Related Processes 50
M Identifying Rework in Maintenance or Craftsman Operations Lean in Manufacturing and Service Industries 12
C How to document rework being completed at Suppliers on Medical Devices? ISO 13485:2016 - Medical Device Quality Management Systems 3
Z Rework Reduction Six Sigma Project - Need help Six Sigma 5
E Medical Device Software - Control of Nonconforming Product and Rework ISO 13485:2016 - Medical Device Quality Management Systems 4
C Calculate DPPM/PPM for second yield rework Quality Tools, Improvement and Analysis 1
E Calculating the MTBF for an assembly, Failure and Rework Prediction Reliability Analysis - Predictions, Testing and Standards 6
eternal_atlas Audit Technique to find rework in a process area? General Auditing Discussions 17
V Looking for Rework Form examples Document Control Systems, Procedures, Forms and Templates 3

Similar threads

Top Bottom