Rolls-Royce SABRe2 - Shift Handover Procedure

P

pearson114

#1
Hi all,

I'm hoping someone may be able to assist with the Shift Handover procedure requirement in SABRe2, I've been tasked with developing the procedure, however I'm not entirely sure how much detail is required in it.

Could anybody please provide an example of a shift handover procedure or advise on how they might have satisfied this clause for their company?

Thanks in advance.
 
Elsmar Forum Sponsor

Mikishots

Trusted Information Resource
#3
Hi all,

I'm hoping someone may be able to assist with the Shift Handover procedure requirement in SABRe2, I've been tasked with developing the procedure, however I'm not entirely sure how much detail is required in it.

Could anybody please provide an example of a shift handover procedure or advise on how they might have satisfied this clause for their company?

Thanks in advance.
Sec. A2.2 (b) states that for shift changes, all necessary info is communicated (verbally and written) between the outgoing and incoming personnel. In order to satisfy this, you need to have a method in place that ensures that these activities take place. What we do where I work: shifts overlap by 15 minutes, which is used for this activity. With both shifts present, the cell lead reviews what was done during the previous shift, then reviews NCMs, snags, performance (number of work orders closed) and equipment status reviews.

This has also had another benefit - the amount of griping done by a shift in regard to the previous one has dropped dramatically. It's harder to badmouth your co-workers when they're standing in front of you!

In short, the level of detail is up to you, as long as you state how you will accomplish the requirement. Start with who (position) is responsible for the communication, when it is to occur, and how you will record the information that you cover.
 