I am working at small company 50 employees.
We have been audited last month with three minor NCs.

One of them is:
"Internal Audit process not fully implemented, QMS was not covered in its entirety during the last 12 month period. Production process not audited in the last 12 month."

Frankly said we miss them for no special reason. Just I was lazy auditor, whatever.

Can anyone advise me some "good" root cause, why these audit haven't be performed.

Sorry for english.
 
Last edited:
Elsmar Forum Sponsor
K

keres

#2
Re: Root Cause for minor Non-Conformities

One of them is:
"Internal Audit process not fully implemented, QMS was not covered in its entirety during the last 12 month period. Production process not audited in the last 12 month."
And this is noncoformity against what?

Frankly said we miss them for no special reason. Just I was lazy auditor, whatever.

Can anyone advise me some "good" root cause, why these audit haven't be performed.
The reason for your NC is somewhere here. :)
 
T

treesei

#3
Hello,
I am working at small company 50 employees.
We have been audited last month with three minor NCs.

One of them is:
"Internal Audit process not fully implemented, QMS was not covered in its entirety during the last 12 month period. Production process not audited in the last 12 month."

Frankly said we miss them for no special reason. Just I was lazy auditor, whatever.

Can anyone advise me some "good" root cause, why these audit haven't be performed.

Sorry for english.
Almost all system failures can be tracked back to "poor management". :)

You may try to see if there was lacking of resources, undefined requirements, etc.
 

Jen Kirley

Quality and Auditing Expert
Staff member
Admin
#4
Good day Booker, I have some questions:

1) Which standard is this NC against?

2) What does your procedure say about how often you will audit what process?

3) What does your schedule say about how often you will audit what process?
 

Booker

Starting to get Involved
#6
Auditor put it under 8.2.2.1, but this is regarding to Process Audit which is 8.2.2.2.

We have Audit Schedule along with Process Audits for our main three production processes (each process have to be audited one per year) and only one Process Audit was performed, other two not.
 
P

pearsonow

#7
So WHY were the other 2 not done?

That is what needs to be root caused, corrected and eliminated as a future source of none-conformities.

Olly
 
T

tomvehoski

#8
I ran into this my last place. As far as ISO 9001 and TS-16949 go, there is not a requirement to audit your system annually as far as I can tell. The wording for TS is rather vague about "an annual schedule", and I never got a good interpretation as to "audit everything every 12 months" or "have a schedule every 12 months". There is a thread about it here somewhere.

The second time it came up I did not fight it as audits were not even done per our schedule. Root cause was a lack of resources (auditors and time) provided by top management. We had lost a couple auditors and the others were busy getting parts out the door with record sales. Formalizing an audit to report stuff I already knew (very small place) and knew I couldn't fix (other lacking resources) was not the #1 priority. I also thought it would wake management up if they took a hit from a TS auditor since they wouldn't listen to me. Corrective action - I don't know. My last day was the day of that audit (I had stayed to get them through it).
 
S

ssz102

#9
the best way you can do is prepare plan for improvement and find out some important items to do somthing actions as implement programme recently
 

somashekar

Staff member
Admin
#10
Hello,
I am working at small company 50 employees.
We have been audited last month with three minor NCs.

One of them is:
"Internal Audit process not fully implemented, QMS was not covered in its entirety during the last 12 month period. Production process not audited in the last 12 month."

Frankly said we miss them for no special reason. Just I was lazy auditor, whatever.

Can anyone advise me some "good" root cause, why these audit haven't be performed.

Sorry for english.
Your English is good enough and we understand what you said ....
You are supposed to have your process and interactions described per 4.2.2 c) of ISO9001., and if you have detailed it well, then you can see that the internal audit process would be interacting with all your other processes, including itself, ie: your internal audit process will also consider auditing the internal audit.
As you see this and make your audit program, you will not miss any process even if you are lazy. One of the good use of this " a description of the interaction between the processes of the quality management system." is audit planning.

>>> Can you get your root cause from here >>>
 
Thread starter Similar threads Forum Replies Date
B NADCAP Rejection Response to Root Cause Analysis and Corrective Action. Nonconformance and Corrective Action 1
Q IATF audit - Root Cause Analysis results IATF 16949 - Automotive Quality Systems Standard 5
T Tactics for Root Cause Analysis Problem Solving, Root Cause Fault and Failure Analysis 4
T Root Cause Failure Analysis - Not following Customer packaging Specification Problem Solving, Root Cause Fault and Failure Analysis 9
I Root Cause Analysis as Training ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
F Struggling with a root cause analysis - Customer Returns - Escape issue Problem Solving, Root Cause Fault and Failure Analysis 15
I Root Cause Analysis when someone simply stops performing a task? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 16
S Root cause analysis - The system of developing a work instruction is not effective Problem Solving, Root Cause Fault and Failure Analysis 1
I What if your root cause analysis is -- they just didn't do it?" Nonconformance and Corrective Action 3
P Examples of Nonconformance, Corrective Action Requests, and Root Cause Analysis Nonconformance and Corrective Action 2
Q Loss of Personnel - Root Cause Analysis ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
Q Risk Tools in ISO 31010 - Root Cause Analysis vs. Cause-and-effect Analysis ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
E Root Cause Analysis - Is Insufficient Understanding an acceptable Root Cause? General Auditing Discussions 9
W Root Cause Analysis Requirements per TS 16949:2009 Problem Solving, Root Cause Fault and Failure Analysis 8
J Required on-site training on writing deviations & root-cause analysis Training - Internal, External, Online and Distance Learning 3
D Root Cause Analysis done on the wrong observation Problem Solving, Root Cause Fault and Failure Analysis 9
I What's special about your RCAs (Root Cause Analysis)? Problem Solving, Root Cause Fault and Failure Analysis 11
K Quality Manual Problem Root Cause Analysis Nonconformance and Corrective Action 8
E Using Facebook to discuss Root Cause Analysis (8D) ! Nonconformance and Corrective Action 3
F Need advise on Root Cause analysis for printing issue Problem Solving, Root Cause Fault and Failure Analysis 3
P Is it necessary to perform Root Cause Analysis for each failed part? Problem Solving, Root Cause Fault and Failure Analysis 16
B Root Cause Analysis and Corrective Action Program for Inventory Inaccuracies Nonconformance and Corrective Action 8
R Root Cause Analysis of Audit Findings - New Quality Manager Quality Manager and Management Related Issues 20
A Recommend good Root Cause Analysis Training Courses in the UK Training - Internal, External, Online and Distance Learning 8
J Nadcap finding Inadequate Procedure and Inadequate Root Cause Analysis Nonconformance and Corrective Action 4
S Root Cause Analysis of Motor Performance Failure Manufacturing and Related Processes 5
R Triggering Root Cause Analysis for Hardware Returns Nonconformance and Corrective Action 3
Fender1 Corrective Action and Root Cause Analysis for a Missing Assembly Part ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
D Root Cause Analysis and "Comprehensive List of Causes" Nonconformance and Corrective Action 4
P Which Root Cause Analysis Method is the most Effective? Quality Tools, Improvement and Analysis 16
K Complex Cause Root Cause Analysis Quality Tools, Improvement and Analysis 3
P Smart or Sexy (CAR) - Poor Root Cause Analysis and Poor Effectiveness Check Nonconformance and Corrective Action 8
Moncia How to do a Root Cause Failure Analysis ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 72
R Assembling a Cross Functional Root Cause Analysis Team Problem Solving, Root Cause Fault and Failure Analysis 4
T Lollipop Production Line Problems - Defectives and Root Cause Analysis Reliability Analysis - Predictions, Testing and Standards 6
K Do all Customer Complaints require Root Cause Analysis? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
K Incident Investigation vs. Root Cause Analysis ? What?s the difference? Customer Complaints 16
Anerol C Root Cause Analysis Coding System Nonconformance and Corrective Action 11
J Root Cause Analysis in a ISO 17025 Testing Laboratory ISO 17025 related Discussions 6
M Root Cause Analysis and Personal Blame ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7
S Noneffective Root Cause Analysis: 6M Fish-Bone Template Problem Solving, Root Cause Fault and Failure Analysis 1
L Root Cause Analysis Training Training - Internal, External, Online and Distance Learning 12
W What can be Root Cause Analysis Methodology - Heat Treatment of Carbon-based Products Problem Solving, Root Cause Fault and Failure Analysis 5
Z Root Cause Failure Analysis for NADCAP AMS2750D Audit Finding help wanted AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
S Root Cause Analysis & Cause and Effect Diagram Customer Complaints 5
J Root Cause Failure Analysis of a Shipping Error Problem Solving, Root Cause Fault and Failure Analysis 37
S Root Cause Analysis Taxonomy - Categorising the reasons for non-conformances ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
D Do all Non Conformance Reports need a detailed Root Cause Analysis? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 13
D Root Cause Analysis (Medical Devices) - Management Support Quality Manager and Management Related Issues 14
F Root Cause Analysis Problem Case Study for Exercise? Problem Solving, Root Cause Fault and Failure Analysis 10

Similar threads

Top Bottom