QualitySpirit
Involved In Discussions
Hello friends,
Once again I have a headache topic which should actually be clear and understood uniformly among all IATF certified auditors. But I found each CB/auditor has so much different interpretation.
The concern is about rules 5.2h site separation as quoted below.
if a portion of the site is dedicated to automotive, then the headcount from that portion can be used to determine audit time when the following conditions are met:
- all automotive manufacturing processes are physically separated from non-automotive manufacturing (e.g. separate building, permanent barrier in between auto and non- ' automotive lines/machines, etc.),
- personnel working in the automotive manufacturing process areas are completely dedicated,
Note: If automotive manufacturing processes are integrated on the manufacturing floor with nonautomotive manufacturing processes, then this requirement cannot be applied.
Example scenario:
A client has two buildings that is obviously physically separated from each other. This is called building no.1 and building no.2.
In building no.1, there are metal pressing process of an automotive product, and also the same operators and machines are used for pressing process of a nonautomotive product too. There is not any physical separation in this building. Total headcount of building no.1 is 150 persons.
In building no.2, there are metal casting process of nonautomotive product 100%. There is completely no activities related to automotive in building no.2. Total headcount of building no.2 is 5000 persons.
In this scenario: I have been told different opinions regarding 5.2h applicability to this site.
Opinion 1: In this case, rules 5.2h cannot be applied to any portion of the site. The audit manday shall be calculated from the total headcount of both buildings e.g. 150 + 5000 = 5150 persons.
The reason of this opinion is that
1) as rule requires that "a portion of the site is dedicated to automotive" in this site we can not find such portion, building no.1 is a mixed area of automotive and nonautomotive and thus not a portion dedicated to automotive" .
2) for the requirement that all automotive manufacturing processes are physically separated from non-automotive manufacturing, although building no.1 and building no.2 are physically separated to each other. As a result all automotive manufacturing processes are physically separated from non-automotive manufacturing in building no.2 e.g. non automotive metal casting. However the automotive manufacturing processes are not physically separated from non-automotive manufacturing in building no.1 itself e.g. nonautomotive pressing. Therefore rule 5.2h definitely cannot be applied to this site and the whole headcounts in both building must be included.
Opinion 2: In this case, rules 5.2h can be applied to separate building no.1 and building no.2. The waiver must be requested. The audit manday shall be calculated from the total headcount of building no.1 only e.g. 150 persons.
The reason of this opinion is that
1) Since all automotive pressing manufacturing processes are physically separated from nonautomotive metal casting processes in building no.2. We can apply rule 5.2h here.
2) For the inside building no.1 where there is a mixed automotive/nonautomotive manufacturing processes we will not apply rule 5.2h here. All headcounts within building no.1 must be included but we can exclude headcounts within building no.2.
As the conclusion, waiver must be requested to separate building no.1 and building no.2. And headcounts of building no.1 only will be used for manday calculation.
Opinion 3: In this case, you don't even have to request for a waiver. You can proceed to use headcounts of only building no.1 of 150 persons in manday calculation and ignore completely building no.2.
The reason for this opinion is that: refer to Rules FAQ no.3. IATF gives examples of a client with 20 sites of which 9 sites producing nonautomotive, and another client has two locations across the street of which one is producing nonautomotive. In such scenarios, in this situation, an application form for “portion of the site dedicated to automotive” is not required.
Could you let me know you opinion which one is the right one and acceptable at your CB?
Thank you very much.
Once again I have a headache topic which should actually be clear and understood uniformly among all IATF certified auditors. But I found each CB/auditor has so much different interpretation.
The concern is about rules 5.2h site separation as quoted below.
if a portion of the site is dedicated to automotive, then the headcount from that portion can be used to determine audit time when the following conditions are met:
- all automotive manufacturing processes are physically separated from non-automotive manufacturing (e.g. separate building, permanent barrier in between auto and non- ' automotive lines/machines, etc.),
- personnel working in the automotive manufacturing process areas are completely dedicated,
Note: If automotive manufacturing processes are integrated on the manufacturing floor with nonautomotive manufacturing processes, then this requirement cannot be applied.
Example scenario:
A client has two buildings that is obviously physically separated from each other. This is called building no.1 and building no.2.
In building no.1, there are metal pressing process of an automotive product, and also the same operators and machines are used for pressing process of a nonautomotive product too. There is not any physical separation in this building. Total headcount of building no.1 is 150 persons.
In building no.2, there are metal casting process of nonautomotive product 100%. There is completely no activities related to automotive in building no.2. Total headcount of building no.2 is 5000 persons.
In this scenario: I have been told different opinions regarding 5.2h applicability to this site.
Opinion 1: In this case, rules 5.2h cannot be applied to any portion of the site. The audit manday shall be calculated from the total headcount of both buildings e.g. 150 + 5000 = 5150 persons.
The reason of this opinion is that
1) as rule requires that "a portion of the site is dedicated to automotive" in this site we can not find such portion, building no.1 is a mixed area of automotive and nonautomotive and thus not a portion dedicated to automotive" .
2) for the requirement that all automotive manufacturing processes are physically separated from non-automotive manufacturing, although building no.1 and building no.2 are physically separated to each other. As a result all automotive manufacturing processes are physically separated from non-automotive manufacturing in building no.2 e.g. non automotive metal casting. However the automotive manufacturing processes are not physically separated from non-automotive manufacturing in building no.1 itself e.g. nonautomotive pressing. Therefore rule 5.2h definitely cannot be applied to this site and the whole headcounts in both building must be included.
Opinion 2: In this case, rules 5.2h can be applied to separate building no.1 and building no.2. The waiver must be requested. The audit manday shall be calculated from the total headcount of building no.1 only e.g. 150 persons.
The reason of this opinion is that
1) Since all automotive pressing manufacturing processes are physically separated from nonautomotive metal casting processes in building no.2. We can apply rule 5.2h here.
2) For the inside building no.1 where there is a mixed automotive/nonautomotive manufacturing processes we will not apply rule 5.2h here. All headcounts within building no.1 must be included but we can exclude headcounts within building no.2.
As the conclusion, waiver must be requested to separate building no.1 and building no.2. And headcounts of building no.1 only will be used for manday calculation.
Opinion 3: In this case, you don't even have to request for a waiver. You can proceed to use headcounts of only building no.1 of 150 persons in manday calculation and ignore completely building no.2.
The reason for this opinion is that: refer to Rules FAQ no.3. IATF gives examples of a client with 20 sites of which 9 sites producing nonautomotive, and another client has two locations across the street of which one is producing nonautomotive. In such scenarios, in this situation, an application form for “portion of the site dedicated to automotive” is not required.
Could you let me know you opinion which one is the right one and acceptable at your CB?
Thank you very much.