Another question is still related to audit hours of manufacturing process
FAQ # 10 issued in May 2014
The rounding of audit days always occurs at the end of the audit day calculation result – see example below.
Example:
Client?s key data:
- single site with 225 employees
- non-design responsible
- 9 monthly surveillance audit interval
The next audit is the 2nd surveillance audit. A translator is needed for auditing in the manufacturing / production area only, which is estimated as 1.5 total hours (or 1.5 hours / 8 hours =.19 days) at the next audit.
From the initial audit day Table 5.2, minimum audit days for 225 employees is equal to 8.0.
The correct calculation (for a 9-monthly surveillance interval) is: 8.0 audit days – 15% discount = 6.8 days / 3 surveillance audits = 2.27
2.27 (min. audit days) + .19 (for translation) = 2.46 rounded up to 2.5 days for the 2nd surveillance audit.
If we ignore the translator issue, is it allowed to allocate 1.5 hours to manufacturing / production area in the case of total min. audit day is 2.5md?
As I understand, it shall be 2.5/3 = 0.8333 md = 6.67 hours
Thanks
Jelly
FAQ # 10 issued in May 2014
The rounding of audit days always occurs at the end of the audit day calculation result – see example below.
Example:
Client?s key data:
- single site with 225 employees
- non-design responsible
- 9 monthly surveillance audit interval
The next audit is the 2nd surveillance audit. A translator is needed for auditing in the manufacturing / production area only, which is estimated as 1.5 total hours (or 1.5 hours / 8 hours =.19 days) at the next audit.
From the initial audit day Table 5.2, minimum audit days for 225 employees is equal to 8.0.
The correct calculation (for a 9-monthly surveillance interval) is: 8.0 audit days – 15% discount = 6.8 days / 3 surveillance audits = 2.27
2.27 (min. audit days) + .19 (for translation) = 2.46 rounded up to 2.5 days for the 2nd surveillance audit.
If we ignore the translator issue, is it allowed to allocate 1.5 hours to manufacturing / production area in the case of total min. audit day is 2.5md?
As I understand, it shall be 2.5/3 = 0.8333 md = 6.67 hours
Thanks
Jelly