we are having some heated discussion internally ....

Is Run and Rate mandatory in automotive industry if is not required by the customer?

Let say, that our customer does not request a Run and Rate to be performed, do we need to do it anyway?

We had a preliminary audit from customer X who wanted to see a Run and Rate performed on customer Y's product. Since customer Y did not request a Run and Rate, we did not have one, but customer X defined this as non-conformity.


Thanks!
 
Elsmar Forum Sponsor

Ashland78

Involved In Discussions
#2
I believe it is run at rate and it is a requirement of the PPAP package that is required (18 elements). Can someone else confirm my thought? This would be done when doing capability for capacity.
 

Blaz123

Starting to get Involved
#3
If I rely on your comment, what if the customer does not require capacity calculation in the PPAP requirements? Is there any automotive requirement (IATF, ISO9001,...) that we have to mandatory perform Run & Rate by ourselves?
 

Sebastian

Trusted Information Resource
#4
Not R&R, but IATF 16949 8.3.5.2 f)
For me it is and will be one of TOP organizational activities, even if it wasn't required by any of management standards.
Capacity analysis is crucial element of internal validation of newly developed manufacturing process.
Generally poorly managed worldwide and therefore "abilities of quality department staff to manage post-SOP quality meetings are essential for proper management of product quality level".
 

Blaz123

Starting to get Involved
#5
Sebastian, you probably are right.

8.3.5.2 Manufacturing process design output

The organization shall document the manufacturing process design output in a manner that enables verification against the manufacturing process design inputs. The organization shall verify the outputs against manufacturing process design input requirements. The manufacturing process design output shall include but is not limited to the following:

a) specifications and drawings;
b) special characteristics for product and manufacturing process;
c) identification of process input variables that impact characteristics ;
d) tooling and equipment for production and control, including capability studies of equipment and process(es);
e) manufacturing process flow charts/layout, including linkage of product, process, and tooling;

f) capacity analysis;
g) manufacturing process FMEA;
h) maintenance plans and instructions;
i) control plan (see Annex A );
j) standardised work and work instructions;
k) process approval acceptance criteria;
l) data for quality, reliability, maintainability, and measurability;
m) results of error-proofing identification and verification, as appropriate;
n) methods of rapid detection, feedback, and correction of product/manufacturing process nonconformities.
 

Ashland78

Involved In Discussions
#6
I think you would have to get a waiver from all your customers or allowed deviation, otherwise you are not compliant with IATF. I agree with Sebastian...
 
#10
There's much confusion here.
  • Run @ Rate is a specific type of capacity analysis, and capacity analysis can take many forms.
  • There is no specific requirement for [email protected] in 16949. [email protected] is a General Motors thing (although there are other varieties). It's described in GM standard GP9. It's typically performed after PPAP approval, as confirmation of the production rate claimed on the PPAP warrant. It may or may not be witnessed by a customer representative.
  • If it's not specifically required by a customer, it's not required of the supplier. Waivers aren't needed for "requirements" that don't exist.
As far as the OP's question is concerned, customer auditors should never be allowed to audit anything but their own requirements and products. Someone else's products and records are none of their business, quite literally.
 
Thread starter Similar threads Forum Replies Date
G Need Help with Run @ Rate for Medical Devices ISO 13485:2016 - Medical Device Quality Management Systems 0
M Difference between "Production Trial Run" and "Run at Rate" IATF 16949 - Automotive Quality Systems Standard 8
E Translating from Automotive to Medical Device industry - [email protected] Other Medical Device Related Standards 2
U Run & rate for bulk materials IATF 16949 - Automotive Quality Systems Standard 6
N Can you use parts from Run at Rate to use in your PPAP? APQP and PPAP 4
E What's the difference: AIAG-PPAP's "Significant Production Run" and "Run @ Rate"? APQP and PPAP 11
W Production Trial Run in AIAG APQP and Run at Rate (GP-9) GM 1927 APQP and PPAP 2
I How Run at Rate should be carried out for assembly line? APQP and PPAP 10
C Sub-Supplier compliance to Ford Phase 0 PPAP (Run at Rate) APQP and PPAP 3
G Production rate demonstration? APQP Manual 4.1 ? Significant Production Run APQP and PPAP 7
T Templates or latest form for Ford [email protected] APQP and PPAP 2
D Run at Rate guidelines IATF 16949 - Automotive Quality Systems Standard 6
H OEE (Overall Equipment Effectiveness) and Run at Rate IATF 16949 - Automotive Quality Systems Standard 5
O FORD Run at Rate ([email protected]) Procedure Customer and Company Specific Requirements 11
J How to Determine Run At Rate: Steel Coil Processing Customer and Company Specific Requirements 19
R PPAP and Run @ Rate - We have a run at rate coming up soon for a visiting customer APQP and PPAP 1
N Is [email protected] part of PPAP? APQP and PPAP 1
R QSR 3rd Edition, section II Run at Rate ([email protected]) - What do they want? QS-9000 - American Automotive Manufacturers Standard 3
J Run Down Adapters Calibration Processes General Measurement Device and Calibration Topics 4
H Is it a requirement for run charts to have inspection data or can it have just a pass/fail check mark Records and Data - Quality, Legal and Other Evidence 4
K ISO 2859-5 (single run production) control plan issues FMEA and Control Plans 2
H Can I just forget physical run charts and start digital? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
O Production run inventory sell-by expiration date? APQP and PPAP 3
P Arena simulation, How can my Arena model have exactly the same output each time I run it? Process Maps, Process Mapping and Turtle Diagrams 0
Q CQI-26 SPC Short Run Supplement Capability, Accuracy and Stability - Processes, Machines, etc. 1
S Where do l get calibration standards to run a calibration lab? Other ISO and International Standards and European Regulations 2
L Significant Production Run - How 300 was determined to be the minimum quantity APQP and PPAP 2
V Supplier wants to perform pre-qualifications prior to every run instead of locking in parameters. Supplier Quality Assurance and other Supplier Issues 7
I New to LEAN but not to Quality - How to run Kaizen events Lean in Manufacturing and Service Industries 1
J Sample size definition in an Automotive SMT pilot lot run Misc. Quality Assurance and Business Systems Related Topics 1
M Has anyone heard of Run at Risk? Manufacturing and Related Processes 15
F Bayes Success run Theorem for sample size during OQ&PQ Qualification and Validation (including 21 CFR Part 11) 4
Q How to run a Management Review Management Review Meetings and related Processes 10
M Informational Team-NB published a press release regarding the survey run among its members to analyse the certificates being issued Medical Device and FDA Regulations and Standards News 0
M What is required to run human clinical trials in France EU Medical Device Regulations 9
M Case study - If the restaurant (ISO 9001:2015 certified) was run by 2 persons covering cooking and purchasing processes (Mother and Father) supported ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7
S Designing the experiment with minimum run Statistical Analysis Tools, Techniques and SPC 0
S Designing the experiment with minimum run Statistical Analysis Tools, Techniques and SPC 0
L Formulas to be able to answer these Run Chart questions Statistical Analysis Tools, Techniques and SPC 7
R What testing would you run to determine if a device is "Clean"? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 4
J Design Control - Can Validation be based on a limited/first Production Run ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
W AS9100 Clause 8.5.1.3 Production Run Verification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
V When and How to apply the Bayes Success Run approach for Sample Size Determination Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
T Supplier Sample Run Rejection ISO 13485:2016 - Medical Device Quality Management Systems 3
I Run a batch every year to revalidate the validated condition? Qualification and Validation (including 21 CFR Part 11) 4
P SPC Short Run Advice of a Stamping Process Statistical Analysis Tools, Techniques and SPC 3
W AS9100C registration - How long does the system have to run before initial audit? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 9
B Bayes Success-Run on Attribute Data - Determining Sample Size Statistical Analysis Tools, Techniques and SPC 2
M Standardized P Chart for Short Run Production Statistical Analysis Tools, Techniques and SPC 13
B How to Demonstrate Stability and Repeatability in very Short Run Process AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10

Similar threads

Top Bottom