Hi there!

I'm have been set in charge of setting up a QA Program specifically the M1003 for the AAR. I'm basically looking for any one who has experience with the AAR or the M1003 QA program to help get our program started and on the right path.

Right now we are in the research phase trying plan for timelines and cost estimates.
We've made a few calls and have been told that the AAR is really backed up.

We had a few more questions and I think you might be able to help us piece them together.

So far we know that we need three things
  • Technical Testing
  • QA Program (M1003)
  • AAR Approval (service trials)

Technical Testing:
I know that we need to do several technical testing for Pressure and materials used.​
  • Do we have to finish our technical testing before we apply for our QA program?

QA Program:
​​We are currently in the starting phases of writing our QA Manual and getting the QA program on its feet.
  • ​What is the relationship of the M1003 and the Semi-Annual meeting (April and October)?

AAR Approval:
From what we know, the AAR meets in April and in October. We should have our design done however the QA will most likely not be approved.
In the "Process for Obtaining AAR Approval" Document it states: "Product designs can be presented to the appropriate committee at semi-annual meetings​"​. Does this mean the following:
  • Can we present in front of the AAR in APRIL without having our QA M1003 certification?
  • Do we have to finish our technical tests before we show our designs to the AAR in their semi annual meetings?
  • Can we get any sort of conditional approval from the AAR without having M1003/Technical Testing done? (I.e. they say "get this stuff done and then you'll be approved for two year trials")
  • Can you tell us a bit more about this process?

Costs:
We received some numbers from various sources about costs.

Application fee: $720
Audit: ~$5000
Technical testing: ~$10,000 - $50,000 (outside of AAR)

I would be greatly appreciate any input on the M1003 regarding these questions or any thing else that can help us.

Thank you!
 
M

Mixtrate

Hey, so we've made a few calls to people in the AAR and some talked to some consultation companies about this and here are some answers that we got back. Maybe this info can help someone in the future.

Question: Can we present in front of the AAR in APRIL without having our QA M1003 certification?
Answer: Yes. However you don't need to present to the AAR committee, you can instead send your application and designs to the AAR anytime and they will approve it. About $250 and a few months.

Question: Do we have to finish our technical tests before we show our designs to the AAR in their semi annual meetings?
Answer: Yes it's recommended that you finish technical testing before hand.

Question: Can we get any sort of conditional approval from the AAR without having M1003/Technical Testing done? (I.e. they say "get this stuff done and then you'll be approved for two year trials")
Answer: Yes. Your device can get approved without your company having an M1003. You can then take your product and start manufacturing it at a certified M1003 manufacturer.
 
Last edited by a moderator:
Thread starter Similar threads Forum Replies Date
I Setting Bioburden Limits for ETO Other Medical Device Related Standards 1
Bev D Development Process: FMEA, Critical Characteristics, Spec Setting and Controls Misc. Quality Assurance and Business Systems Related Topics 0
P Setting Cleanroom Alert and Action Limits Manufacturing and Related Processes 0
S Setting AQL Levels with Multiple Suppliers Supplier Quality Assurance and other Supplier Issues 3
qualprod Setting a goal in % with few events ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
J Setting up a service center in the EU ISO 13485:2016 - Medical Device Quality Management Systems 2
Z Setting the Control limits on Minitab Using Minitab Software 4
S HELP in setting-up QMS Quality Tools, Improvement and Analysis 4
Awais Setting up Kitting Cells Manufacturing and Related Processes 0
K ISO 9001 Auditing in a Healthcare setting Process Audits and Layered Process Audits 15
J Setting accuracy limit for a read out General Measurement Device and Calibration Topics 4
B Setting flexible packaging specification limits ISO 14971 - Medical Device Risk Management 4
I Setting action completion dates Nonconformance and Corrective Action 3
S Qualification question - ISO 13485 - Setting up a small lab Reliability Analysis - Predictions, Testing and Standards 2
S Heat Sealers Upper and lower limit setting during OQ for Heat Sealer Qualification and Validation (including 21 CFR Part 11) 0
Ed Panek GDPR in Urgent Healthcare Setting Other ISO and International Standards and European Regulations 1
M Setting deadlines (ex. 45 days) for Document Registration & Review Cycle Document Control Systems, Procedures, Forms and Templates 3
Ashok sunder What are the criteria for setting a target KPI value against a quality objective? Benchmarking 7
K Setting Quality Objectives (for the first time) AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 17
R ISO 11137 Gamma sterilization validation, dose setting, dose audit Other Medical Device Related Standards 1
M Best Practice for setting tolerances on a Drawing Inspection, Prints (Drawings), Testing, Sampling and Related Topics 14
T Setting up a quality department in an Engineering Firm Quality Management System (QMS) Manuals 11
B Software for setting up New Warehouse Manufacturing and Related Processes 0
S Setting up the process - First piece inspections Statistical Analysis Tools, Techniques and SPC 3
A Add-On software for VMC to calculate setting time, Idle Time, OEE etc.. Manufacturing and Related Processes 2
G Setting Up a Basic Quality Lab for a small manufacturing company General Measurement Device and Calibration Topics 2
A Setting initial Expiry Date of an IVD per BS EN 23640:2015 Other Medical Device Related Standards 12
Q Setting Quality Objectives with a Timeframe ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
Proud Liberal Setting up Prolink's QC-Gage to a Keyence IM-6225 Vision System Statistical Analysis Tools, Techniques and SPC 2
P Setting Acceptance Quality Limits (AQL) for New Medical Devices ISO 13485:2016 - Medical Device Quality Management Systems 4
Hami812 Cpk Setting Tolerance - Cart before the Horse? (Wifi Routers) Capability, Accuracy and Stability - Processes, Machines, etc. 3
K Bioburden 0 cfu for Dose Setting using the VDmax25 Other Medical Device Related Standards 9
A New company, no employees, Setting up a QMS ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
F Setting up a new sterilization unit in a new facility 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 6
C ISO 14001 Recertification without setting Targets ISO 14001:2015 Specific Discussions 3
T Guidance - Setting up an integrated quality & environmental management system Career and Occupation Discussions 12
A Setting up a Medical Device Distributor in Malaysia Other Medical Device Regulations World-Wide 17
R Irradiation Sterilization Dose Setting and Dose Audit Flow Charts ISO 13485:2016 - Medical Device Quality Management Systems 0
J Setting Up New QMS - New US Location ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
A Setting air gauging outside of a part tolerance Capability, Accuracy and Stability - Processes, Machines, etc. 2
S Target Setting - Internal metric(s) to drive Internal Processes Six Sigma 1
S MSA Help or guidelines - Plastics - Setting up an MSA on a multi cavity fixture Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 2
G Setting up a corporate umbrella QMS ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
T Setting Quality Objectives ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
W Setting up from scratch - Looking for help (ISO9001 / ISO13485) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
F Setting up a New QMS for Certification when ISO 9001 is about to Change ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 23
P New to AS9100 Rev. C - Setting KPIs and FAI Reports AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 14
B Setting Lower Control Limit on Attributes Charts Statistical Analysis Tools, Techniques and SPC 9
J Lean 5S - Setting Min/Max Inventory Levels Lean in Manufacturing and Service Industries 3
V Setting Specification Limits for UOD (Uniformity) for Live Bacteria or Spores Pharmaceuticals (21 CFR Part 210, 21 CFR Part 211 and related Regulations) 4

Similar threads

Top Bottom