Should I perform Gage R&R only at the beginning of a new project?

Graciel

Involved In Discussions
#1
Dear all,

should I perform R&R only at the beginning of a new project. Will I never need to reproduce again? (If it´s based on IATF, does it say exactly when?)

Thank you.
 
Elsmar Forum Sponsor

Jim Wynne

Leader
Admin
#2
MSA should not have to be repeated unless there have been significant changes in the system. The object is to demonstrate that a particular measurement system, including devices and operators, is appropriate for measurement of a particular dimension or feature.
 

Ninja

Looking for Reality
Trusted Information Resource
#3
Jim is correct, but consider what he says in detail...

If you've done a GRR for measurements by this method for 1-4 inches before...but the new project is using the same method for measuring 12 inches...
Consider that things like this may be "significant changes in the system"...even if the technique and tools remain the same.
 

Miner

Forum Moderator
Leader
Admin
#4
should I perform R&R only at the beginning of a new project.
Please clarify what you mean by new project. Do you intend a new product introduction, or are you referring to a continuous improvement project such as Six Sigma?
 

Graciel

Involved In Discussions
#5
Please clarify what you mean by new project. Do you intend a new product introduction, or are you referring to a continuous improvement project such as Six Sigma?
hI, I´m refering if I need to perform MSA to each new product, product change or process change.
 

Ninja

Looking for Reality
Trusted Information Resource
#6
I used a drop gage to measure the thickness of product ranging from 12um through 1.1mm...same gage, same technique.

I used product from 12um through 0.010" (~250um) for the GRR, and included a "known" sheet of Mylar at 75um as one of the 10 parts.

When it came time to do 1.1mm (1100um) I considered how the gage worked (linear displacement up to 1.000inch) and chose to do a 2x2x5 R&R on parts from 0.010" through 1200um. Saw no issue, and moved on.
In the mean-time, we launched at least 60 new products in the 12um - 250um range...never even considered doing 60 more GRR's.
Apply logic...the goal is to have accurate enough measurement to know good from bad...

After establishing a "known good measuring system within these parameters"...product changes and process (for making the product) changes have nothing to do with the measurement system.
 

Miner

Forum Moderator
Leader
Admin
#7
I agree with the previous comments. The only reason to redo an MSA is if :
  • there is a fundamental change in the measurement system,
  • you are using the measurement system to measure a fundamentally different feature (width vs. diameter),
  • Using the device in a different way (outside diameter to inside diameter to step height for calipers)
  • measuring in an entirely different range of the device. Note: this would normally be covered by Linearity, but could have an impact on R&R for certain devices. For example, the size of the feature might affect how an operator holds the product and gage.
 
Thread starter Similar threads Forum Replies Date
F Should I perform several Gage R&R for every caliper to cover all specs range of use? Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 9
B AS9102 FAI & Lower Level Drawings - How should we perform the FAI? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 1
E Should companies that perform calibration services be ISO 17025 accredited? ISO 17025 related Discussions 13
V Product Audits - Who should perform Product Audits? IATF 16949 - Automotive Quality Systems Standard 17
B Should we perform Equipment final calibration-Operations closing ISO 13485:2016 - Medical Device Quality Management Systems 8
M Customer is also my supplier - Should I perform an audit to his process? IATF 16949 - Automotive Quality Systems Standard 6
E Please help! ! I AM FRASTRATED SO MUCH! Should inactive ingredient be included in the unit formula if it is removed during the manufacturing process? US Food and Drug Administration (FDA) 0
I IEC 60812 or ISO 14971 for PFMEA? What should we use? ISO 14971 - Medical Device Risk Management 3
qualprod Do sum of results of quality objectives should met a high level goal? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
E Opening meeting for Third-Party Audit--Who should say what? General Auditing Discussions 22
8 MSA--Should I Use Parts or Gage Pins? Gage R&R (GR&R) and MSA (Measurement Systems Analysis) 2
B Should I buy IEC 62304:2006, IEC 62304:2006/AMD 1:2015 or both? EU Medical Device Regulations 1
W "Accurate to ±2%" means "64% of measurements should be within 2% of the actual value"? US Medical Device Regulations 4
H Should we stop inspecting a part if its never been rejected? Reliability Analysis - Predictions, Testing and Standards 6
D What distributor requirement should we (manufacturer) require from the Distributor? EU Medical Device Regulations 0
M Should there be another column in the Optimization section (step 6) of AIAG-VDA DFMEA form? FMEA and Control Plans 1
C By when should harmonized standards be complied with? EU Medical Device Regulations 5
W Strategy for determining which components from a system should be "ME EQUIPMENT" -- home healthcare environment IEC 60601 - Medical Electrical Equipment Safety Standards Series 6
B Documented information - Should be controlled? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
Q Is engineering a process and should it have its own process turtle? IATF 16949 - Automotive Quality Systems Standard 7
P Which MDCG Document should I use for PMS Plan and PSUR? EU Medical Device Regulations 2
M Who should quality representative report to? ISO 13485:2016 - Medical Device Quality Management Systems 5
H When should the first PSUR be issued? EU Medical Device Regulations 5
I If i do not want to be an initial importer should i register with FDA? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 0
O Should a Covid vaccine and testing policy be included as part of ISO9001 or AS9100 risk management? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
B UKRP to what level should you audit Class I Technical Documentation? UK Medical Device Regulations 0
C When should you quit programming? Job Openings, Consulting and Employment Opportunities 9
C Should resolution be included in uncertainty budget for digital caliper or micrometer calibration? Measurement Uncertainty (MU) 5
Ed Panek External Standards List - Should this document include previously revised standards? ISO 13485:2016 - Medical Device Quality Management Systems 4
T How should I approach REACH, CM, etc. as a job shop? RoHS, REACH, ELV, IMDS and Restricted Substances 18
A Should we assign the PRRC before the date of application of MDR (26 May 2021)? EU Medical Device Regulations 0
J UDI-DI how should we interpret Device version or model to determine if a new UDI-DI is needed? EU Medical Device Regulations 0
Sidney Vianna Interesting Discussion Should ISO 9004 be changed from a guidance document to a requirements standard? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 13
A Should I take an online course for a career in Occupational Health and Safety? Career and Occupation Discussions 2
J Should a Class 1 medical device with an option to measure body weight be considered Class 1m? EU Medical Device Regulations 0
K Should APQP/PPAP has its own section in a QM? Quality Management System (QMS) Manuals 1
S What should i choose for "testing procedure" characteristics? (N95) General Information Resources 0
P Should eIFU link per ISO 15223-1:2016 be added to labels out of scope of Reg 207/2012? EU Medical Device Regulations 1
S Which Sampling Plan(s) Should I Use? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 13
A Document release vs its related training. Which should come first? ISO 13485:2016 - Medical Device Quality Management Systems 18
S Which department should prepare the control plan? could you show me a standard regarding to this matter. FMEA and Control Plans 17
J Help settle a disagreement: Should external providers of preventive maintenance be on your ASL? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 5
N Master Samples - What should we be keeping? IATF 16949 - Automotive Quality Systems Standard 9
G Supplier delivered recent PPAP, should he deliver yearly layout inspection? IATF 16949 - Automotive Quality Systems Standard 7
John Broomfield Should ISO 9004 Become a Requirements Standard? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 70
A Capability Study - in the beginning of your career what should you have known about the tool Quality Tools, Improvement and Analysis 11
J Should Loading and Unloading be Included in Cycle Times? Lean in Manufacturing and Service Industries 14
E Manufacturers should develop a testing device for covid19 Service Industry Specific Topics 0
T 510(k) submission - Which name should I use in the submission? Other US Medical Device Regulations 3
N ISO 19011:2018 - 5.4.2 "...audit program should engage in appropriate continual development..." Training - Internal, External, Online and Distance Learning 4

Similar threads