Supplier Approval Process – Should the Quality Department be Excluded?

L

LesPiles

#1
Hello everyone,

We are an EMS and have several PCB suppliers.


The problem for us (the Quality Department) with the PCBs is that PCB’s are rather a "technical" domain. Nevertheless, we can learn (we are not idiots!).

Since the R & D department is “stronger" than us (in human resources), they succeed at imposing their choice of pcb suppliers. The Purchasing Dpt also “suffer” (they must go where the RD tells them to go), as well as the Quality Dpt. (by having numerous nonconformance at receiving).

What makes me jump is when I see an internal e-mail that mentions "The approval of a new supplier will be done by someone who knows our PCB suppliers [a person in the R & D department]".


Shouldn’t a Quality Department participate in the supplier approval process ? In the ISO standard, we talk about selection, evaluation and re-evaluation ... why we do not use the term "approval" ? Should I let this issue go and "choose my fights"?


Thank you in advance !


Les Piles
 
Elsmar Forum Sponsor
G

gretzles

#2
Re: Supplier Approval Process – Quality Dpt Excluded ?

IMO you want the people who know the most about it to make the decision. It doesn't matter what department someone work.
But there is more than one consideration when approving your suppliers. R&D may have some input into the technical side and Purchasing may have some input into the pricing and account arrangements etc.

Who gets to 'win' these negotiations depends on what the priorities of the organization are. Hopefully the same people who set these priorities are the same people who have to review supplier evaluations when/if purchasing and quality issues arise.
 

Sidney Vianna

Post Responsibly
Staff member
Admin
#3
Re: Supplier Approval Process – Quality Dpt Excluded ?

Should I let this issue go and "choose my fights"?
I would NOT let this issue go, because your organization's future (thus your job) is at stake here. As previously mentioned, supplier selection and approval should be a multi-disciplinary evaluation. A supplier that might be able to provide you with a batch of 10 complex, multi-layer PCBs (used by R&D for D&D V&V), might not be able to consistently deliver 10,000 of these same PCB's per month, when your customer and you need to ramp-up production. Many times, as I am sure you know, the processes/equipment/tooling used to produce a small batch of PCBs are not the same used for volume production.

So, absolutely, I would insist that your department/function input is sought, valued and acted upon, during the supplier selection process. Sorting of incoming product, especially when you are dealing with high volumes is NOT a smart way to control the quality of parts being received. If the quality department is misunderstood as the inspection department, you know you are in a world of hurt.

Good luck.
 
Last edited:

normzone

Trusted Information Resource
#4
Re: Supplier Approval Process – Quality Dpt Excluded ?

My experience in this matter?

R&D can do whatever they damn well please until the company begins selling parts.

Purchasing should be able to buy those parts from whoever best meets their requirements for quality, price, and delivery schedule. R&D should have no say in the matter.

All the QA function should do is assess and report on the capabilities of the suppliers chosen. If Purchasing wants to use a turkey for a supplier, the QA function should go on the record as advising against that turkey, and be able to provide objective evidence demonstrating why that supplier is a turkey, and other evidence showing the availability of a superior supplier.

Sure, it would be nice if QA could choose the suppliers. If you have a big enough department and budget to do that, with support and commitment from the top, more power to you. It rarely works out that way though.

I try not to tell the coaches how to play the game - I throw the flags and assign the penalties and let the kids play where possible.

Perhaps too much coffee today ... :rolleyes:
 

hogheavenfarm

Quite Involved in Discussions
#5
I do the same a Norm - Purchasing buys from the absolute lowest bidder, and the quality is usually pretty bad. I keep the Approved Vendor list and it is fed live performance information which rates the suppliers. I make it known that certain suppliers are "bad" and the list shows the performance data (and highlites them as RED), but purchasing will still use them anyway. I have done my part in supplier analysis and providing them with up to date data, if they choose to ignore it, they can explain why to the auditor. When the boss freaks out because we received a load of defective product, I point to the list and question why purchasing is using them when they are listed as a bad supplier. Sometimes you need to carefully apply leverage to get where you need to be....
 

Golfman25

Trusted Information Resource
#7
These days, as a supplier, I don't want Purchasing anywhere near the selection process. Too a lesser extent, I don't want QA either. Both are too "numbers" orientated. What I want is someone who knows and understands the process they are buying. If they have a solid understanding of what we do, how we do it, and the challenges we face, things usually go very well. JMO.
 
R

randomname

#8
Should QA be involved for selecting a supplier of liability insurance for a consulting firm, or cloud IT services for an insurance services, etc.

A multidisciplinary team is often useful due to their different perspectives. But I would never say that QA must be involved with selection of all suppliers.
 
Thread starter Similar threads Forum Replies Date
T ISO 9001 Clause 7.4.1 Purchasing Process (Supplier Approval) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 12
V Supplier?s PPAP - Production Process Control Plan Review, Evaluation and Approval? FMEA and Control Plans 5
F Who should Sign Supplier PPAP (Production Part Approval Process) documents? APQP and PPAP 13
B No Supplier PPAP or PSO (process approval) Requirement APQP and PPAP 3
was named killer AS9100 Supplier Approval Requirements AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 10
K ISO 9001 Requirements for Raw Material Supplier Assessment and Approval ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
B Approval of Supplier with ISO 9001 (Automotive) General Auditing Discussions 18
N Raw Material Supplier Approval (Inks, Resin, Masterbatch etc) Supplier Quality Assurance and other Supplier Issues 4
B Supplier Approval of electronic document storage service ISO 13485:2016 - Medical Device Quality Management Systems 8
L Chrysler's Supplier Request for Engineering Approval Form Quality Manager and Management Related Issues 4
S Supplier Approval Problem - Off-the Shelf Parts ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 3
V Ford SREA (Supplier Request for Engineering Approval) 2007 revision Document Control Systems, Procedures, Forms and Templates 2
T ISO 14001 Implementation Help & Question about Supplier Approval ISO 14001:2015 Specific Discussions 5
K How to fill out an SREA (Supplier Request for Engineering Approval) form at Ford? APQP and PPAP 3
E PPAP PSW Approval: Customer Drawing or Supplier Drawing APQP and PPAP 4
V Repercussions for Interim Approval of Supplier PPAP's APQP and PPAP 3
R Responsibility and Authority in a QMS - Approval of Supplier Accreditation Quality Manager and Management Related Issues 5
B Supplier Approval for Distributors of Equipment Misc. Quality Assurance and Business Systems Related Topics 5
J Supplier Purchase Order Review and Approval Requirements IATF 16949 - Automotive Quality Systems Standard 3
M Supplier Evaluation and Approval of a Translation company ISO 13485:2016 - Medical Device Quality Management Systems 6
K Questions about SREA (Supplier Request for Engineering Approval) Customer and Company Specific Requirements 4
M Researching Supplier Approval Processes - When Two Companies Merge Supplier Quality Assurance and other Supplier Issues 5
B PPAP approval based on information supplied by the supplier APQP and PPAP 2
B General SREA (Supplier Request for Engineering Approval) form for all OEM's? IATF 16949 - Automotive Quality Systems Standard 4
T Vendor (Supplier) Approval Procedure - Scope of the procedure ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
sonflowerinwales FDA approval required for a supplier to a medical device manufacturer? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 4
A Supplier approval for special services Supplier Quality Assurance and other Supplier Issues 2
C Supplier Evaluation and Approval forms - Discussion and Evaluation Examples Supplier Quality Assurance and other Supplier Issues 37
R Select the 1 Supplier based on the Parts Durability from 6 Supplier Samples using Minitab Using Minitab Software 7
K Why does load cell supplier requires force verification General Measurement Device and Calibration Topics 3
D Question and advice for a supplier self audit questionnaire ISO 13485:2016 - Medical Device Quality Management Systems 6
D Special IATF audit of sub-supplier IATF 16949 - Automotive Quality Systems Standard 5
S IATF 16949 Supplier selection criteria 8.4.1.2 IATF 16949 - Automotive Quality Systems Standard 2
M Supplier approved list - Notified body, regulatory body Supply Chain Security Management Systems 4
N Making improvements in supplier relationship last? Supplier Quality Assurance and other Supplier Issues 6
K Supplier Qualification for Engineering Consultant? Supplier Quality Assurance and other Supplier Issues 3
M Supplier evaluation Supplier Quality Assurance and other Supplier Issues 5
briteme4 ASL - AS9100 / Supplier Survey Supplier Quality Assurance and other Supplier Issues 3
A System for Supplier Documents Quality Assurance and Compliance Software Tools and Solutions 7
T IMDS submission without supplier's input? RoHS, REACH, ELV, IMDS and Restricted Substances 0
J Supplier not responding to PPAP request APQP and PPAP 5
D Supplier audit Medical Device and FDA Regulations and Standards News 2
lanley liao Does all of the suppliers need to integrated into the supplier list qualified of the company? Oil and Gas Industry Standards and Regulations 2
S Distinction between a critical supplier and a Virtual manufacturer EU Medical Device Regulations 2
R AS9102 FAI Change in Material / Process Supplier AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
John Broomfield Five ways to botch your supplier management program Misc. Quality Assurance and Business Systems Related Topics 7
C Supplier survey - 200 to 250 duppliers Supplier Quality Assurance and other Supplier Issues 3
J Where is the definition of a critical supplier? ISO 13485:2016 - Medical Device Quality Management Systems 5
U Approved Vendor (supplier) List Supplier Quality Assurance and other Supplier Issues 8
M Supplier requirements - Major supplier is a Non-Profit registered with ICCBBA (FDA UDI) Supply Chain Security Management Systems 12

Similar threads

Top Bottom