Our supplier is not capable to 1.67 Cpk on a number of SC/CC’s on the print. We would like them to initiate 100% sort, but they brought up a concern that running 100% of their parts over their gage would cause gage wear and probably result in out of spec parts being shipped.
Is there an alternative to 100% sort over a check fixture?
Could begining of run/end of run layouts satisfy these criteria?
How would you respond to this suppliers concerns?
They have to get PPAP’s and we have to PPAP to our customer.
Is there an alternative to 100% sort over a check fixture?
Could begining of run/end of run layouts satisfy these criteria?
How would you respond to this suppliers concerns?