AVCM Bill
I have a question about the Pull System and how Quality Control fits in. We have a new VP and he is really breathing some new life into the company. One of they many ideas he has introduced us to, is the pull system. I am very excited and ready to help incorporate it in to our daily routine.
That being said when it comes to Quality I think that production and Quality should remain independent of each other. The performance of our job should not be influenced by the production schedule.
So here is where my problem lies. If a part has to ship by 1400 and its not to shipping by 1300, the shipping guy calls to see if Quality has it. If we don't, then the baton is passed and we go to the production guy to see if he has it and so on and so on. With my belief system on how Quality operates, I am struggling with my inspectors running around looking for parts. Any insight would be greatly appreciated. Thanks
That being said when it comes to Quality I think that production and Quality should remain independent of each other. The performance of our job should not be influenced by the production schedule.
So here is where my problem lies. If a part has to ship by 1400 and its not to shipping by 1300, the shipping guy calls to see if Quality has it. If we don't, then the baton is passed and we go to the production guy to see if he has it and so on and so on. With my belief system on how Quality operates, I am struggling with my inspectors running around looking for parts. Any insight would be greatly appreciated. Thanks