Timing to certify new plant to IATF 16949

mindytanner

Starting to get Involved
Question, we have 28 plants certified to TS 16949 and transitioning to IATF 16949, what are the requirements for certification if we build a new facility? How long would it take to get certification?
 

jfries2

Involved In Discussions
The IATF Rules 5th edition address this in 6.5.1c). You will need both a Stage 1 and Stage 2 audit for your new facility. Before the Stage 1 audit can be conducted, you must have 12 months data for key indicators and performance trends, among other items. The Stage 2 audit is conducted within 90 days after confirmation that Stage 1 shows sufficient readiness. If you allow 8-12 weeks to obtain a certificate after the Stage 2 audit, you should plan on your new plant becoming certified 17-18 months after start of production.

Having other certified plants will not help your cause, unless you are certified to a corporate scheme in which case the number of audit days may be adjusted.
 

mindytanner

Starting to get Involved
Yes, we are certified to a corporate scheme. Stage 1 and 2 will have to happen our main concern is with the amount of evidence the auditors will need to see for certification. Thank you for your input. Have a great day!
 