D
davis007
I was hired as a quality engineer. My back ground in Chemical Engineering and I have worked in R&D up to this point in my career. Moving into manufacturing has been a shock, but not necessarily a surprise. When I was hired it was made clear that I was to promote 6 sigma and follow the DMAIC process in all my projects. Knowing absolutely nothing about either I have found this forum very helpful.
I have started a project to improve the quality of an self produced component in our final product. The component is a compounded plastic (poly propylene + filler) and is used to injection mold our product. One of the biggest complaints from the injection molding side of the plant has been that they often must make changes to there process to accommodate changes in the compound. Thus the project is to make the compound more consistent.
For project metrics I would like to track how often a change is required at the injection molder. However, the molding side of the facility seems to be unwilling to track this information. Very rarely they give up on a lot of compound and throw it out. They are willing to track this occurrence. Also, the product undergoes a final visual inspection. Defects are reported and can be sorted into categories that are related to the compound or not. So for project metrics I have decided to track lbs of compound scrapped per week, and number of defects found in the finished article related to the compound.
My problem is that these are both relatively rare occurrences. We may go through 120,000lbs/month of compound but scrap only 400-600 lbs. in the whole month, so many weeks have zero compound scrapped even without any improvement project. We produce 1,000,000 parts/week but may only have 700 parts identified with a compound related defect one week and 50 the next.
OK after a long explanation my question. Does it make sense to use these stand in metrics?
I have started a project to improve the quality of an self produced component in our final product. The component is a compounded plastic (poly propylene + filler) and is used to injection mold our product. One of the biggest complaints from the injection molding side of the plant has been that they often must make changes to there process to accommodate changes in the compound. Thus the project is to make the compound more consistent.
For project metrics I would like to track how often a change is required at the injection molder. However, the molding side of the facility seems to be unwilling to track this information. Very rarely they give up on a lot of compound and throw it out. They are willing to track this occurrence. Also, the product undergoes a final visual inspection. Defects are reported and can be sorted into categories that are related to the compound or not. So for project metrics I have decided to track lbs of compound scrapped per week, and number of defects found in the finished article related to the compound.
My problem is that these are both relatively rare occurrences. We may go through 120,000lbs/month of compound but scrap only 400-600 lbs. in the whole month, so many weeks have zero compound scrapped even without any improvement project. We produce 1,000,000 parts/week but may only have 700 parts identified with a compound related defect one week and 50 the next.
OK after a long explanation my question. Does it make sense to use these stand in metrics?