Hello,

I have a question, as I have never been in this position before.

We are going to have a BSI surveillance audit for the maintenance of the ISO 13485 Standard next week and we realised that one of the minor finding that was raised by the auditor last year is not yet completed and it's now overdue (it was due on Feb 22).
From your experience what's the consequence if one of the findings from BSI of last year remains not implemented?

Many thanks for your help
 
Elsmar Forum Sponsor

Randy

Super Moderator
#2
Hello,

I have a question, as I have never been in this position before.

We are going to have a BSI surveillance audit for the maintenance of the ISO 13485 Standard next week and we realized that one of the minor finding that was raised by the auditor last year is not yet completed and it's now overdue (it was due on Feb 22).
From your experience what's the consequence if one of the findings from BSI of last year remains not implemented?

Many thanks for your help
Easy, unless you can show evidence of trying to take positive action like cause analysis, some containment and planning to correct correct it, the NC will most likely be raised to a Major and your certificate be placed under risk of suspicion or revocation.

Did you send in a proposed corrective action like you were asked to or did you post one to the Portal?

If you've done nothing what you get is a self inflicted wound.

There is no mandate for complete closure, sometimes it takes time & resources to get something done. Now what do you mean it was due Feb 22? I know a wee bit about this and a totally completed CA isn't given a "due by date" only the initial CAP will have a due assigned to it with review at the next audit.............HAVE SOMETHING TO SHOW!!!!
 
Last edited:

Sidney Vianna

Post Responsibly
Leader
Admin
#3
Depending on the reasons behind the failure to effectively implement corrective action by the due date, the auditor is likely to escalate the issue to a major and give you a shorter timeframe to resolve it. And you will have the privilege to pay for their onsite visit to (hopefully) close the issue.
 

ire88

Starting to get Involved
#4
Thanks a lot for your response.
Yes, we did the investigation and we identified the RC, however, the QA team was under resources and we were not able to complete the implementation plan. The proposed corrective action was sent to BSI within the due date and our implementation plan was approved.
 

Randy

Super Moderator
#5
Thanks a lot for your response.
Yes, we did the investigation and we identified the RC, however, the QA team was under resources and we were not able to complete the implementation plan. The proposed corrective action was sent to BSI within the due date and our implementation plan was approved.
Well flitter you might be fine for a continuation based on other factors. Why did the QA team have to correct it? Did they own the process? Don't be surprised if you're asked about "Resources" and get another one for "lack of appropriate thereof" and maybe a lack of demonstrated "commitment"
 

ire88

Starting to get Involved
#6
Yep, QA was the owner of the process. The process is itself about findings.
Historically in the company, all the NCs were escalated to CAPAs. The result is a cumbersome process. The action for the finding raised by BSI was to review the process to use a risk-based approach to evaluate when an NC warrants a CAPA.
 

Randy

Super Moderator
#7
Yep, QA was the owner of the process. The process is itself about findings.
Historically in the company, all the NCs were escalated to CAPAs. The result is a cumbersome process. The action for the finding raised by BSI was to review the process to use a risk-based approach to evaluate when an NC warrants a CAPA.
So you're saying that some things for incorrect or "nonconforming" are left to whither on the vine?

Here's a risk based approach........"What could happen if the problem isn't fixed?...Worst case scenario
 

Tidge

Trusted Information Resource
#8
Easy, unless you can show evidence of trying to take positive action like cause analysis, some containment and planning to correct correct it, the NC will most likely be raised to a Major and your certificate be placed under risk of suspicion or revocation.
“Before I draw nearer to that stone to which you point, answer me one question. Are these the shadows of the things that Will be, or are they shadows of things that May be, only?”
 

Tata347

Starting to get Involved
#9
So quick and dirty; change your CAPA process to state external audits are reviewed, evaluated and documented on external auditors/customer documentation (or point to the external corrective action process in your CAPA process to an internal CAPA - for tracking and closing purposes only); realize that these two items are one in the same and it sounds like they were made to be two separate processes. Since you've obviously done the majority of the work; finish the documentation based on what you gave BSI originally (as long as its still sound) and note that audit CAPAs may be closed as part of subsequent audits by external sources. Define the difference is "CLOSED" and Documented... closed implies that you have verified effectiveness and the issue no longer exists.. since you haven't had a repeat audit from BSI - I would contend that the CAPA can't be verified for effectiveness and therefor not "CLOSED" yet as long as you've documented the plan and an ECD documented you may be able to squeak by. Do something even if its a "Draft" to submit for review; its' better than doing nothing - that will be an automatic MAJOR and 30 days to complete and implement.
 

Randy

Super Moderator
#10
So quick and dirty; change your CAPA process to state external audits are reviewed, evaluated and documented on external auditors/customer documentation (or point to the external corrective action process in your CAPA process to an internal CAPA - for tracking and closing purposes only); realize that these two items are one in the same and it sounds like they were made to be two separate processes. Since you've obviously done the majority of the work; finish the documentation based on what you gave BSI originally (as long as its still sound) and note that audit CAPAs may be closed as part of subsequent audits by external sources. Define the difference is "CLOSED" and Documented... closed implies that you have verified effectiveness and the issue no longer exists.. since you haven't had a repeat audit from BSI - I would contend that the CAPA can't be verified for effectiveness and therefor not "CLOSED" yet as long as you've documented the plan and an ECD documented you may be able to squeak by. Do something even if its a "Draft" to submit for review; its' better than doing nothing - that will be an automatic MAJOR and 30 days to complete and implement.
Not necessarily, unless you're more intimate with the process than I.
 
Thread starter Similar threads Forum Replies Date
C Unable to Demonstrate FIFO Methodology ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
A CE Certificate Expiring and NB unable to extend / renew as not in their scope as a NB EU Medical Device Regulations 34
N Calibration Lab unable to issue Accredited Certificate when error is too high? General Measurement Device and Calibration Topics 3
I Unable to obtain CSRs from Customer IATF 16949 - Automotive Quality Systems Standard 30
J Supplier Management - Unable to visit the suppliers Supplier Quality Assurance and other Supplier Issues 9
Coury Ferguson I heard it through the Grapevine - Changes to AS9104 - Unable to change auditor(s) Registrars and Notified Bodies 24
RoxaneB Manual Rejected - Unable to find "shall" to support rejection - Responsibility Matrix Miscellaneous Environmental Standards and EMS Related Discussions 50
S Question about 7.3.6 - Validation - We are unable to elicit the intended application ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 7
R To Close the RCCA or Verify Effectivenessof RCCA first? Nonconformance and Corrective Action 14
J Mechanical inspection techniques of close tolerance parts Inspection, Prints (Drawings), Testing, Sampling and Related Topics 4
I What kind of wine best complements the Friday that you close out your external audit findings? Opinions are welcome. Coffee Break and Water Cooler Discussions 12
L External power supplies: How close does the safety report have to match the end-use application? IEC 60601 - Medical Electrical Equipment Safety Standards Series 4
G Timing allowed by IATF to close a Remote Site Minor Nonconformance IATF 16949 - Automotive Quality Systems Standard 2
M Informational FDA Preps for Device Shortages as Another Sterilization Facility Will Close Medical Device and FDA Regulations and Standards News 0
S FDA Inspections and Pest Control - Pallets too close to walls 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 15
S When a deviation is opened but what does it mean to close a deviation? Misc. Quality Assurance and Business Systems Related Topics 1
S How to Politely Close out a Nuisance Customer Corrective Action? Nonconformance and Corrective Action 11
E Best Ways to Close a Project APQP and PPAP 3
Proud Liberal How long does your company take to close an 8D on average? Problem Solving, Root Cause Fault and Failure Analysis 12
S Why is it so hard to close out the CAPAs ? Nonconformance and Corrective Action 16
J KPI for time to close NCs (Nonconformances) Quality Manager and Management Related Issues 17
P Can the Auditor close down the Corrective Actions? Internal Auditing 12
J European Laboratories which can do IEC/EN 60601-2-50 Testing? (Close to Turkey) IEC 60601 - Medical Electrical Equipment Safety Standards Series 3
M Drilling Close Tolerance Holes - Advice needed on Sampling Inspection, Prints (Drawings), Testing, Sampling and Related Topics 9
Q How to close the circle QMS and ECO (Engineering Change Order)? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 5
Q Can I close a Complaint with only a Remedial Action? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 9
A How long does it take US FDA to issue a Warning Letter Close Out Letter Other US Medical Device Regulations 2
A To CAPA or not to CAPA? Requirement to close our Corrective Actions before Audit? Nonconformance and Corrective Action 8
S Corrective Action Audit Form to close a CAR Document Control Systems, Procedures, Forms and Templates 6
T TS 16949 Major CA Close Out Visit - What can the auditor look at? IATF 16949 - Automotive Quality Systems Standard 4
M Health Canada Device Classification - Close-off clip for use with a tubing set Canada Medical Device Regulations 9
S Corrective Action and Reporting using a High-Low-Close chart in Excel Nonconformance and Corrective Action 2
K Never been this close to a plane crash... Coffee Break and Water Cooler Discussions 38
T Training in or close to Toronto - Root Cause Analysis, Value Stream Mapping, SPC Problem Solving, Root Cause Fault and Failure Analysis 0
J Close relationships with customers? Philosophy, Gurus, Innovation and Evolution 6
R Valid Date to Close Internal Audit Non-conformance Internal Auditing 1
Marc Delphi to close, sell most plants under deal World News 0
Marc DaimlerChrysler Plans to Cut 10,000 Jobs, Close Plants World News 4
K When to Close a Corrective Action Report? Nonconformance and Corrective Action 31
Wes Bucey Aren't we a little old to believe in fairy tales? Whirlpool to close Maytag plants World News 13
Marc RadioShack to close up to 700 stores World News 8
C How long should you have to close out a major TS 16949 audit finding? IATF 16949 - Automotive Quality Systems Standard 9
S Gage pin clearance on close tolerance - Hole size is ?.8746 ? .0001 General Measurement Device and Calibration Topics 9
Marc Ford likely to close five North American plants World News 3
B Quality and Health & Safety. How close is this link? Document Control Systems, Procedures, Forms and Templates 8
S Shiny new CAPA system! - Easy way to close the old one? Nonconformance and Corrective Action 1
P ISO 13485:2003 6.4 vs 7.5.1.2.1 - For me these paragraphs are very close ISO 13485:2016 - Medical Device Quality Management Systems 1
H Repeated tests reproducibility - Regression line is close and good Bland Altman plots Quality Assurance and Compliance Software Tools and Solutions 1
T TQM (Total Quality Management) Team Close Out Process Preventive Action and Continuous Improvement 2
A Can we close an audit NCR by not taking any action? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 29

Similar threads

Top Bottom