Booker
Starting to get Involved
Hello,
I am just curious how to handle following situation in PFMEA.
Let's say supplier sent us products, where was one dimension out of specs. And this was first occurrence of problem. Supplier solved this issue properly along with the update of their PFMEA.
Should I consider to update our PFMEA based on this experience? For example, add in to Incoming Inspection potential failure mode such as particular dimension is out of specs and follow other items in PFMEA.
Seems strange to me.
Thank you.
I am just curious how to handle following situation in PFMEA.
Let's say supplier sent us products, where was one dimension out of specs. And this was first occurrence of problem. Supplier solved this issue properly along with the update of their PFMEA.
Should I consider to update our PFMEA based on this experience? For example, add in to Incoming Inspection potential failure mode such as particular dimension is out of specs and follow other items in PFMEA.
Seems strange to me.
Thank you.