Use TAKT time to optimize output of line - TAKT Time .xls

Q

qianzhongmin

Usually some production planner use average cycle time to make work order.sometimes production line will very busy and cann't meet customer demand,sometimes line will have many waste.:biglaugh:
 

Attachments

  • TAKT time.xls
    49 KB · Views: 1,468

harry

Trusted Information Resource
Re: Use TAKT time to optimize output of line

Welcome (huan ying),

I am sorry for not understanding your post. If you have a question, kindly rephrase it so that others can chip in. If you are sharing the spreadsheet with us, thanks for it.

We look forward for your active participation.
 

RoxaneB

Change Agent and Data Storyteller
Super Moderator
Hi

Has anyone worked on takt time in a call centre environment?

Many thanks

I did a quick search online and found:
  • shmula 1 - this link focuses on tax preparation (everyone's favourite activity!), but it might be a good starting point.
  • shmula 2 - focusing on call centres as queueing systems

Granted most of what I able to find appeared to deal more with using software to determine takt time (no matter the application) instead of explaining how to calculate it in a service environment - it's that whole give a person a fish, teach a person to fish situation.
 
A

arkady

Hello
I have one question. How to calculate potential gap on production. What is mean formula " Available time - sum(not achive target plan according Cyclr time)/1.56). What is mean 1.56

Thanks fo rhelp:thanx:
 