Validation of Processess

Manoj Mathur

Quite Involved in Discussions
#1
Manoj Mathur Manoj Mathur

According to 9K2K clause 7.5.2, Org. shall validate for processss, where the resulting output can not be varified by subsequent monitoring and measurement.
What are the examples of such type of processess and conditions.
Heat Treatment is such type or other.
Pl. Share your view to eloborate the topic.

Manoj Mathur
 
Elsmar Forum Sponsor
M

M Greenaway

#2
Monoj

Any process that cannot be verified by subsequent inspection would be what is commonly termed a 'special process'. You cannot really produce a definitive list of manufacturing processes that are special, because it also depends on any inspection processes available to the organisation.

Your example of heat treatment might be a special process if you have no hardness testing capability for example. In such instances you would need to qualify a set of process parameter settings, such as oven temperature, quench media, quench times, etc to prove that a material subjected to this process will produce the desired outcome.

Electro-plating is also often a special process as thickness measuring equipment is often very expensive, and adhesion testing is also often beyond most companies, however if you had these tests in house it would no longer be a special process.

Welding is often considered a special process also, and often defined by weld preparation geometry, filler material, weld geometry, etc.
 
R

Roger Eastin

#3
I agree with what Martin has said. It is interesting to note that with TS-2002 it doesn't matter whether your process is "special" or not, you have to follow the steps in 7.5.2 for any process.
 
S

Supich

#4
Manoj
For me, yarn spinning process would be under cl. 7.5.2, where the results will be shown fabric weaving process

supich
 
P

PeterL

#5
7.5.2 Validation

I would like to pose this question related to TS2 7.5.2.1. -Supplemental, which states: the requirements of 7.5.2 shall apply to all processes for production and service provision.

Does this mean that the "where" clause exclusion in 7.5.2 line one does not apply and therefore ALL processes for production and service provision need to be validated?

If not, what is the intent of the supplemental?

Peter
 
#6
Peter said;
"Does this mean that the "where" clause exclusion in 7.5.2 line one does not apply"

No. The word "any" in 7.5.2 is replaced by the word "all"


"and therefore ALL processes for production and service provision need to be validated?"

Validation of only those processes where the resulting output cannot be verified.

Verification methods are defined on the control plan. If you have an operation and no verification then you would need to show evidence of validation.
 
Thread starter Similar threads Forum Replies Date
mustomutlu Process Validation Final Report Other Medical Device and Orthopedic Related Topics 2
P Software verification and validation procedure IEC 62304 - Medical Device Software Life Cycle Processes 6
Y SaMD Verification and Validation SOP and Plan IEC 62304 - Medical Device Software Life Cycle Processes 3
C Spreadsheet Validation and Release Qualification and Validation (including 21 CFR Part 11) 2
M Packing Validation & Accelerated Aging Test ISO 13485:2016 - Medical Device Quality Management Systems 2
M Sterile packing validation tests to be performed and protocol Other Medical Device and Orthopedic Related Topics 1
S OEM full range calibrations vs Validation special test points Medical Device and FDA Regulations and Standards News 0
H Software Validation for FFS Packaging Machine Qualification and Validation (including 21 CFR Part 11) 1
Q ISO 13485 7.5.6 Validation - Off the shelf Software ISO 13485:2016 - Medical Device Quality Management Systems 3
M ERP / QMS related software standards for Validation IEC 62304 - Medical Device Software Life Cycle Processes 6
C ISO 19227 Validation Cost Other Medical Device Related Standards 2
A CNC Mill and Lathe - Validation Manufacturing and Related Processes 2
N Example for design and development planning,input,output,review,verification,validation and transfer Misc. Quality Assurance and Business Systems Related Topics 4
N Sterilization Protocol Change in Validation Process and further impacts ISO 13485:2016 - Medical Device Quality Management Systems 1
B Oracle Cloud ERP Validation during Quarterly Patch ISO 13485:2016 - Medical Device Quality Management Systems 1
D Software validation team Misc. Quality Assurance and Business Systems Related Topics 3
W LTPD, AQL, Ppk and Cpk validation sampling plan table Inspection, Prints (Drawings), Testing, Sampling and Related Topics 0
J Validation Sample Size for Tray Seal Qualification and Validation (including 21 CFR Part 11) 3
F AS9100 - Validation, FAIR's, ITAR and Sub-Contracting AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 3
R PCBA process validation Qualification and Validation (including 21 CFR Part 11) 2
A ISO 17025 - Methods validation and clients ISO 17025 related Discussions 3
S Sterilization validation after changing sterilization process provider Qualification and Validation (including 21 CFR Part 11) 3
B Sterilization Validation Plan Other Medical Device Related Standards 3
D Difference between Test Method Validation and Gage R&R Qualification and Validation (including 21 CFR Part 11) 18
T Laboratory Verification after validation ISO 17025 related Discussions 3
silentmonkey Rationalising the level of effort and depth of software validation based on risk ISO 13485:2016 - Medical Device Quality Management Systems 10
D Questions regarding process validation ISO 13485:2016 - Medical Device Quality Management Systems 6
Y We found out we have been using a equipment without validation for past 4 years Quality Manager and Management Related Issues 6
Z Is IQ necessary for laser marking validation? EU Medical Device Regulations 3
E 13485:2016, Sections 4.1.6, 7.5.6 and 7.6 - Validation of Software - Need some Advice please ISO 13485:2016 - Medical Device Quality Management Systems 3
A Validation of Forced Aeration Process ISO 13485:2016 - Medical Device Quality Management Systems 3
E Mentor for Test Method Validation (TMV) Design and Development of Products and Processes 2
M API 4F/7K/8C Design Package Validation Oil and Gas Industry Standards and Regulations 2
I ISO 2233:2000 Question - Medical Device Shipping/Transportation Validation Other ISO and International Standards and European Regulations 1
T Annual Validation as a detection mode on a PFMEA? FMEA and Control Plans 5
B TMV - Selection of TM's for Validation ISO 13485:2016 - Medical Device Quality Management Systems 5
S Forced ServiceNow validation - No change in our current user and functional requirements IT (Information Technology) Service Management 4
P Human Factors / Usability validation in the time of COVID Human Factors and Ergonomics in Engineering 17
C Template for Excel Validation Reliability Analysis - Predictions, Testing and Standards 6
M IT validation for a paper based MD repair company QMS ISO 13485:2016 - Medical Device Quality Management Systems 6
P Unrealistic Packaging Validation Sample Size 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 41
D Test summary report example for design validation wanted - ISO 13485 ISO 13485:2016 - Medical Device Quality Management Systems 1
M Is Validation of Plating Processes required and who is responsible? Qualification and Validation (including 21 CFR Part 11) 11
T ISO 13485 - Process validation at critical suppliers ISO 13485:2016 - Medical Device Quality Management Systems 7
K Software Validation for Measurement Tools used in Process Validation ISO 13485:2016 - Medical Device Quality Management Systems 2
Stoic Manual soldering processes - 100% verifiable, or always requiring validation? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 15
P Design verification driven by new equipment. How is this different than process validation? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
S Rees System Validation Qualification and Validation (including 21 CFR Part 11) 1
K PQ validation qualification - Asked to write a PQ protocol ISO 13485:2016 - Medical Device Quality Management Systems 6
Stoic Are any medical device companies using the 2011 FDA process validation guidance instead of GHTF/SG3/N99-10:2004? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1

Similar threads

Top Bottom