hi! im jericho, currently a BS Industrial Engineering student of the University of the Philippines. Im doing an internship here at Wyeth Philippines and one of the tasks given to me is to develop a value stream map for our plant.
Im wondering if anyone could help me out on how to do VSM.
Thanks/
Jericho,
This might be too late, but I will still post my comments.
When I created a VSM for the first time, I used these steps.
1.Use technical experts to identify products and steps used for each product to manufacture.
2. Sort the matrix based on common steps
3. Identify product families that make sense with the help of team
4. Add annual volume produced for each product type
5. Add volumes within each product family
6. Sort the matrix based on total volume by product family
7. Select product family based on this matrix to develop VSM
8. Start from customer demand and calculate Takt time
9. Identify type & frequency of communication from customer to Sales / Production Planning
10. Identify type & frequency of communication from Sales / Production Planning to Purchasing
11. Identify type & frequency of communication from Purchasing to Supplier(s)
12. Identify delivery frequency, mode of transportation and quantity within a batch of load delivered from supplier to the factory
13. Lay out process steps showing type of material flow (push mostly, pull, kanban, etc.) with WIP quantity between each step
14. Populate data boxes for each process steps
15. Show hidden factory where product comes back to a preceding step for rework and quantify them
16. Add Information flow from production planning to all process steps based on frequency
17. Identify low hanging fruits for improvement with the team.
NOTE: ALL THIS HAS TO BE DONE WITH THE TEAM ON A PIECE OF PAPER, POST IT NOTES, COLOR TAPES/MARKERS, etc.)