What is implied by a change in process. Does moving a molding machine across the aisle constitute a change? How about across the plant? The country? I have seen cases where suppliers move a machine across the hall and meesed up something and caused defects to be made. How about blocking off a cavity if it is damaged. How about two or three? What about changing pallates on an assembly line? You laugh but I have seen where containment marks have caused parts to be defective! Do my suppliers have to do a new PFMEA if they add a containment mark? Where should the line be drawn and what happens if Dan Reid comes into my plant and doen't like it?
 
Elsmar Forum Sponsor

Marc

Hunkered Down for the Duration
Staff member
Admin
#2
Well, Stan, are you sitting down?

If Dan Reid walked in I'd be shaking in my boots wondering just what financial motivation was at work.

A process change can be just about anything. Moving a piece of process equipment, different supplier of a material or subassembly, you name it. The question is what is considered a critical change and what isn't. And that definition is entirely up to your company to decide. One client of mine produced an array of products and much of the process equipment and assembly tables were mobile - they set the plant up nightly for the next days planned product. Since the products were mixed and several would run a day, the place set up to produce the assembly could be in several places. Since most was assembly equipment of a simple nature they did not consider changing location critical.

What ever you decide to to, get some kind of guidance from your US automotive customers' supplier QA folks as to what they (with consideration to YOUR company processes and what you supply to the US automotives) will accept (which you will find nearly impossible).

I wouldn't think blocking off a cavity would typically be a process change. But if the parameters were critical enough and let's say you have heated molds and a heated input, it could be argued that blocking off a cavity would throw off the thermal properties of the mold requiring requalification of the mold.

If you found containment marks as cause for rejection it shows a lack of communication with the customers. In the past when I went into containment I contacted customers about the problem(s) at hand and my intended identification scheme to preclude rejection. I wouldn't think a PFMEA change or control plan change would be driven by a containment mark but if you're in containment you would be looking at both the PFMEA and control plan any way.

I know this answer is not what you wanted to hear - there is no black & white, but here again logic plays a big part as does making sure all communications with your customer supplier QA folks is well documented - even if you just get a verbal from someone. Write down their name, the content of the conversation and the date/time of the telecon.

Isn't this stuff just dandy fun???
 
C

Christian Lupo

#3
One resources for deciding what constitutes a change is the PPAP Manual. I believe on page 3 or 4 it defines when you need to resubmit a PPAP. Chances are if you have to resubmit a PPAP, you've changed your process. It may not be foolproof but it's a good place to start.
 

Marc

Hunkered Down for the Duration
Staff member
Admin
#4
The PPAP manual is a good place to start but this all really revolves around a good relationship with your customer's supplier QA. Often only partial PPAPs are neccessary for changes - depends upon what the change is
 
S

Stan DeForest

#5
Where we really get into trouble on this is the differences in what our customer wants for the same part. e.g GM Mid-Lux wanting something different that GM Small car wants. Its not feasible to approach every customer and ask every possible question up front (Hey, were moving a machine, do you care? How about you? And you? etc.)
It would really be a nightmare, but, hey, gotta love automotive.
 

Marc

Hunkered Down for the Duration
Staff member
Admin
#6
If you want to get really picky I guess the extreme would be re-PPAP if you change operators...

I have seen where a customer bought different parts but when we made the same changes to the processes of the different parts the customer wanted something different for each. So - no matter what you do there can be a different request for any given change. From this I have taken the prelimianry stance that there is no rule - gotta ask each customer what they want for a given change before you do it.

I guess I leave it to the Product Manager (or whatever your company calls the person responsible for the product) to make sure s/he has communicated with significant customers and documented (notes of phone calls, etc.) their requirements. I rarely see a full PPAP requested.
 
Thread starter Similar threads Forum Replies Date
S What defines Top Management after a Merger? Quality Management Review (9.3.1) Management Review Meetings and related Processes 1
C IEC EN 60601-1-8: What defines a visual alarm? IEC 60601 - Medical Electrical Equipment Safety Standards Series 1
P What defines a campus? (Scope of ISO 14001 registration) ISO 14001:2015 Specific Discussions 4
H What defines a Quality Record ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 27
S Aerospace Standard - What document defines reliability concept AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 2
ScottK What defines the need for the ISO9001 Design & Development process? Design and Development of Products and Processes 15
N What Defines Flight hardware? AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 25
A NO2 Output - 4.5.1. How often to measure? Who defines an 'appropriate' period? Miscellaneous Environmental Standards and EMS Related Discussions 2
Marc IIA (Institute of Internal Auditors) Defines Internal Auditing Internal Auditing 25
S Special 510(K) - Labeling change from Rx to OTC Other US Medical Device Regulations 11
A Document Change Notice vs complete System re-write Manufacturing and Related Processes 4
S MDR Delay - MDD design Change? (before new MDR DOA) EU Medical Device Regulations 8
Jane's Like-for-like critical raw material change qualification - type of testing/ number of lots required ISO 13485:2016 - Medical Device Quality Management Systems 1
R Change Notification - Registrar vs Notified body ISO 13485:2016 - Medical Device Quality Management Systems 1
Marc Insects and Climate Change - 2020 World News 0
A UDI and Design Controls - Labeling change via the Design Control process 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
Q Company Ownership Change ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 13
Q Legal Manufacturing Address Change – multiple registrations at same address 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 2
I Is highlighting on a printed document considered a change? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 4
N China - Start manufacturing before change approval? China Medical Device Regulations 1
L 510K - Trade Name Change 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 0
D Change Control - Product Name Change and its associated labeling EU Medical Device Regulations 7
K Is a change that fixes a recalled device significant? Medical Device and FDA Regulations and Standards News 2
L Significant change notice for outsourced warehouse Medical Device and FDA Regulations and Standards News 2
U Change Management vs Change Control? Design and Development of Products and Processes 4
H New 510K VS Documents about design change. Other US Medical Device Regulations 1
P Change on Medical Device Classifications - Dental Crowns Other Medical Device Regulations World-Wide 2
D Are medical device companies required to document every change made to their website? Document Control Systems, Procedures, Forms and Templates 2
Ed Panek Relevant questions on Substantial Change Form CE Marking (Conformité Européene) / CB Scheme 3
K Reporting a Change of Contract Manufacturer for a 510(k) cleared device Other US Medical Device Regulations 5
R Software change control process and defect tracking ISO 13485:2016 - Medical Device Quality Management Systems 1
S Device name change and label color change EU requirement? Other Medical Device Regulations World-Wide 6
M CBE (Change Being Effected) 510(k) Submission Other US Medical Device Regulations 2
D Customer and Company Specific Requirements for notification of Customers of a change in Management or Key Personnel Customer and Company Specific Requirements 3
R Explain what "design change" is to people new to the industry ISO 13485:2016 - Medical Device Quality Management Systems 9
S Change value of target during a batch Capability, Accuracy and Stability - Processes, Machines, etc. 0
T Change in BRH (Brazilian Registration Holder) Technical Manager Other Medical Device Regulations World-Wide 2
G Saline solution change for soft contact lens potting CE Marking (Conformité Européene) / CB Scheme 0
M How to implement the 4M Change Management System Lean in Manufacturing and Service Industries 3
Ed Panek Is Shelf Life Change a significant change? CE Marking CE Marking (Conformité Européene) / CB Scheme 7
T Closing out CAR while waiting for design change Nonconformance and Corrective Action 12
I Is this a Major AS9100 QMS change - Quality Concerns AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 2
C E signatures on Engineering Change Notes AS9100 / AS9116 AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 3
K Interpretation of significant change - material change Canada Medical Device Regulations 3
Icy Mountain Engineering Change Order...Modification Order Document Control Systems, Procedures, Forms and Templates 18
J Change management with CFDA approved devices China Medical Device Regulations 1
L Managing design projects: New Medical Device Project or Change Design and Development of Products and Processes 1
S Is the document author required to be identified as part of Document Change Notice? ISO 13485:2016 - Medical Device Quality Management Systems 5
R How long to wait for Notified Body Response - Potentially significant change to a medical device CE Marking (Conformité Européene) / CB Scheme 6
Jim Wynne Some things never change Coffee Break and Water Cooler Discussions 2
Similar threads


















































Top Bottom