What defines a "change in process"

S

Stan DeForest

#1
What is implied by a change in process. Does moving a molding machine across the aisle constitute a change? How about across the plant? The country? I have seen cases where suppliers move a machine across the hall and meesed up something and caused defects to be made. How about blocking off a cavity if it is damaged. How about two or three? What about changing pallates on an assembly line? You laugh but I have seen where containment marks have caused parts to be defective! Do my suppliers have to do a new PFMEA if they add a containment mark? Where should the line be drawn and what happens if Dan Reid comes into my plant and doen't like it?
 
Elsmar Forum Sponsor

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#2
Well, Stan, are you sitting down?

If Dan Reid walked in I'd be shaking in my boots wondering just what financial motivation was at work.

A process change can be just about anything. Moving a piece of process equipment, different supplier of a material or subassembly, you name it. The question is what is considered a critical change and what isn't. And that definition is entirely up to your company to decide. One client of mine produced an array of products and much of the process equipment and assembly tables were mobile - they set the plant up nightly for the next days planned product. Since the products were mixed and several would run a day, the place set up to produce the assembly could be in several places. Since most was assembly equipment of a simple nature they did not consider changing location critical.

What ever you decide to to, get some kind of guidance from your US automotive customers' supplier QA folks as to what they (with consideration to YOUR company processes and what you supply to the US automotives) will accept (which you will find nearly impossible).

I wouldn't think blocking off a cavity would typically be a process change. But if the parameters were critical enough and let's say you have heated molds and a heated input, it could be argued that blocking off a cavity would throw off the thermal properties of the mold requiring requalification of the mold.

If you found containment marks as cause for rejection it shows a lack of communication with the customers. In the past when I went into containment I contacted customers about the problem(s) at hand and my intended identification scheme to preclude rejection. I wouldn't think a PFMEA change or control plan change would be driven by a containment mark but if you're in containment you would be looking at both the PFMEA and control plan any way.

I know this answer is not what you wanted to hear - there is no black & white, but here again logic plays a big part as does making sure all communications with your customer supplier QA folks is well documented - even if you just get a verbal from someone. Write down their name, the content of the conversation and the date/time of the telecon.

Isn't this stuff just dandy fun???
 
C

Christian Lupo

#3
One resources for deciding what constitutes a change is the PPAP Manual. I believe on page 3 or 4 it defines when you need to resubmit a PPAP. Chances are if you have to resubmit a PPAP, you've changed your process. It may not be foolproof but it's a good place to start.
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#4
The PPAP manual is a good place to start but this all really revolves around a good relationship with your customer's supplier QA. Often only partial PPAPs are neccessary for changes - depends upon what the change is
 
S

Stan DeForest

#5
Where we really get into trouble on this is the differences in what our customer wants for the same part. e.g GM Mid-Lux wanting something different that GM Small car wants. Its not feasible to approach every customer and ask every possible question up front (Hey, were moving a machine, do you care? How about you? And you? etc.)
It would really be a nightmare, but, hey, gotta love automotive.
 

Marc

Hunkered Down for the Duration with a Mask on...
Staff member
Admin
#6
If you want to get really picky I guess the extreme would be re-PPAP if you change operators...

I have seen where a customer bought different parts but when we made the same changes to the processes of the different parts the customer wanted something different for each. So - no matter what you do there can be a different request for any given change. From this I have taken the prelimianry stance that there is no rule - gotta ask each customer what they want for a given change before you do it.

I guess I leave it to the Product Manager (or whatever your company calls the person responsible for the product) to make sure s/he has communicated with significant customers and documented (notes of phone calls, etc.) their requirements. I rarely see a full PPAP requested.
 
Thread starter Similar threads Forum Replies Date
M Labelling - Is there a guidance or regulations that specifically defines the 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
S What defines Top Management after a Merger? Quality Management Review (9.3.1) Management Review Meetings and related Processes 1
C IEC EN 60601-1-8: What defines a visual alarm? IEC 60601 - Medical Electrical Equipment Safety Standards Series 1
P What defines a campus? (Scope of ISO 14001 registration) ISO 14001:2015 Specific Discussions 4
H What defines a Quality Record ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 27
S Aerospace Standard - What document defines reliability concept AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
ScottK What defines the need for the ISO9001 Design & Development process? Design and Development of Products and Processes 15
N What Defines Flight hardware? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 25
A NO2 Output - 4.5.1. How often to measure? Who defines an 'appropriate' period? Miscellaneous Environmental Standards and EMS Related Discussions 2
Marc IIA (Institute of Internal Auditors) Defines Internal Auditing Internal Auditing 25
I What revalidation is necessary if we change parts in a WFI loop ? Qualification and Validation (including 21 CFR Part 11) 1
Y Exporting data to the cloud is a "Significant Change"? EU Medical Device Regulations 5
A Design Change/ECO Related Question 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
S Reseller Request to Change UPC on Medical Device via Re-labeling Medical Device and FDA Regulations and Standards News 1
S Change management with FAA Federal Aviation Administration (FAA) Standards and Requirements 0
R Revalidation under VDmax25 following material change ISO 13485:2016 - Medical Device Quality Management Systems 2
D Change to labelling - does it require a new 510(k)? US Food and Drug Administration (FDA) 5
A How can we change a device trade name in 510(k) summary? US Food and Drug Administration (FDA) 0
L Change Notification Requirements for class 1 devices Medical Device and FDA Regulations and Standards News 1
R CB/Auditor Requiring a change in scope ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 8
Ed Panek Notified Body Substantial Change MDD EU Medical Device Regulations 1
A Purchasing Controls on Change Management of Literature/Labeling ISO 13485:2016 - Medical Device Quality Management Systems 3
A For software change - New Channel of interoperability CE Marking (Conformité Européene) / CB Scheme 5
JoCam IEC 60601-1 and 60601-1-2 retest after PCBA change IEC 60601 - Medical Electrical Equipment Safety Standards Series 3
N ISO 13485 7.3.9 Change control in medical device software ISO 13485:2016 - Medical Device Quality Management Systems 6
A ISO 13485 procedure change and reflect to legacy manufacture items ISO 13485:2016 - Medical Device Quality Management Systems 2
R AS9102 FAI Change in Material / Process Supplier AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 4
D Reports under change management | ISO 13485:2016 & ISO 9001:2015 ISO 13485:2016 - Medical Device Quality Management Systems 3
Q Time change via change of Time Zone Qualification and Validation (including 21 CFR Part 11) 3
T IEC 60601-1-8:2020 Is it necessary to change the alarm melody? IEC 60601 - Medical Electrical Equipment Safety Standards Series 1
M Change in Constitution / Ownership of firm -------ISO 13485 ISO 13485:2016 - Medical Device Quality Management Systems 1
U Power supply - Change From 160 to 300 Watts - Significant change? EU Medical Device Regulations 2
N Sterilization Protocol Change in Validation Process and further impacts ISO 13485:2016 - Medical Device Quality Management Systems 1
M Label change - 510(k) Medical Device and FDA Regulations and Standards News 5
M EMS change management ISO 14001:2015 Specific Discussions 2
E Document Change Request forms (or no forms)? ISO 13485:2016 - Medical Device Quality Management Systems 9
J Significant change related to design and intended use EU Medical Device Regulations 3
J Need Change Control Yes/No Decision Tree Template ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
S Cleaning process center change ISO 13485:2016 - Medical Device Quality Management Systems 4
U NOC - What is considered a "design change" EU Medical Device Regulations 5
qualprod What do CB´s change when doing a partial moving ? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
Y Algo change significancy Medical Information Technology, Medical Software and Health Informatics 3
Revision36 Engineering Change Order Industry Standards Other Medical Device and Orthopedic Related Topics 4
Z Iterative development and FDA change requests IEC 62304 - Medical Device Software Life Cycle Processes 13
D ECO (Engineering Change Order) process questions ISO 13485:2016 - Medical Device Quality Management Systems 7
R Medical Device - Change manufacturing plant Design and Development of Products and Processes 6
Tagin Template or Checklist for Process Change Document Control Systems, Procedures, Forms and Templates 5
R Do we need issue ECN (Engineering Change Notice) towards updated Material Specification? Design and Development of Products and Processes 2
A What does this line from MDCG 2020-3 (MDR art. 120 substantial change) mean to you? EU Medical Device Regulations 4
M Change management procedure when 7.3 is not applicable ISO 13485:2016 - Medical Device Quality Management Systems 5

Similar threads

Top Bottom