We have individuals here who want to update the control plan every time something differs from what is going on, even temporary changes, or "tests" to see if the process can be improved.

The changes I am concerned about is when we are going above what the control plan requires (ie: adding an inspection). The inspection is NOT a perminant change (as of right now) it is more of an experiment to see if it will improve our process.

I say that the control plan does NOT have to be altered for this temporary change. The change can be communicated in other ways such as a quality alert, or other postings. If the change is determined to be needed or perminant, THEN the control plan needs to be changed (and other supporting documentation IE: FMEA's) to reflect this addition to the control of our process.

Any thoughts on the subject?
 
Elsmar Forum Sponsor
N

noboxwine

#2
Re: Control Plans

km2red said:

I say that the control plan does NOT have to be altered for this temporary change. The change can be communicated in other ways such as a quality alert, or other postings. If the change is determined to be needed or perminant, THEN the control plan needs to be changed (and other supporting documentation IE: FMEA's) to reflect this addition to the control of our process.
KM2RED: YES :thedeal:
 

Russ

Quite Involved in Discussions
#3
KM2RED:
I agree with you within reason. However, you must be sure that this doesn't get abused or you will end up with all kinds of document conflicts when people just do as they please and things quickly go awry! So use extreme caution here!

:bonk: :frust: :bonk:
 

Mike S.

Happy to be Alive
Trusted Information Resource
#4
When doing an experiment, how about taking the existing control plan, having whomever is authorized make a handwritten change/addition to it (preferably in red) and also saying (writing) that this is a temporary engineering test to be done only on this batch, or on this day, or on this part (or some similar limitation)? That way, there is a record of what was done, and there are written instructions for the people doing the work, but there is no need for a formal revision of the control plan unless/until it is determined that the change should be made permanent.
 
#5
Time limit for the temporary changes

Hi km2red,

I agree that the control plan shouldn't have to be updated due to temporary changes.

Both Russ and Mike S make good points, however, and I would like to add one thing:

Temporary changes should be just that: Temporary. You may already be doing this, but I must stress the importance of setting a time limit for temporary changes. Our way of coping with this particular problem is to use temporary procedures, that can be valid for max 6 months (Usually less).

/Claes
 
B

Bill Ryan - 2007

#6
When doing an experiment, how about taking the existing control plan, having whomever is authorized make a handwritten change/addition to it (preferably in red) and also saying (writing) that this is a temporary engineering test to be done only on this batch, or on this day, or on this part (or some similar limitation)? That way, there is a record of what was done, and there are written instructions for the people doing the work, but there is no need for a formal revision of the control plan unless/until it is determined that the change should be made permanent.
I don't agree. The CP does not have to be changed for every "Process Improvement" excersise you are undertaking
(isn't that the one of the uses of NCM tickets???)

The changes I am concerned about is when we are going above what the control plan requires (ie: adding an inspection).
In my experience, doing more then the CP calls for has not been an issue with our registrar (as long as it is "temporary"). Of course there are limits as to how far you can push the "temporary" limits.

I agree with Mike S. only if you issue CPs to the floor. Why not just use "temporary" Operator Instructions?

RUSS & CLAES also make valid points (at least at my company). If someone doesn't watch what is going on, suddenly, you've got a process change that doesn't get documented correctly (oops!!! - a finding on an audit - HEAVEN FORBID!!).

"Bottom Line" is - I don't think you touch the control plan unless what you are trying becomes permanent (the PFMEA is a different matter and I think the "Recommended Actions" column should probably be updated just to address the Continuous Improvement clause in QS/ISO).

Just my opinion (now I see why everyone uses "IMHO")

Bill
 

Mike S.

Happy to be Alive
Trusted Information Resource
#7
My point is this: When a process is running the "normal way", the "normal way" must be clearly defined by either training, documentation, or a combination of the two. If no documentation exists -- i.e. the "normal way" is defined only by training of the operator, somehow the operator has to be instructed what to do differently for the "experimental way". This could be done verbally but this is dangerous IMO since it is more likely to create a misunderstanding and there is less likelyhood that the actions and results will be clearly documented for future reference. This verbal stuff can start a "wild west" mentality of "anything goes". A simple note explaining what is to be done differently, with the time limitations, etc. signed by the responsible person is quick and easy and can help avoid many pitfalls and provides a record that should prevent any auditor from issuing a NC.

If there is documentation that spells out the "normal way", again something must be done to explain to the operator what the "experimental way" is. I don't condone a verbal change to a documented procedure even for a one-time experiment. Again, it is a simple thing to document what is to be done for the experiment either by marking-up the existing document that spells-out the "normal way" or writing a short, simple note regarding the deviation including the time limit and authorized signature. I think this is what Bill called "temporary operator instructions".

To summarize: Describe the change in writing (somehow) and, as we all seem to agree, clearly establish the time limit. JMHO.
 
Thread starter Similar threads Forum Replies Date
K Must I update the Quality Policy? (ISO 9001:2008) ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 15
T What does AS9100 mean when it says you must establish a process to do X? AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 24
B IATF16949 audit requirement - Auditor request UCL and LCL must be show Xbar-R, IATF 16949 - Automotive Quality Systems Standard 7
A Read instruction manual - What Graphic Symbol must I use? US Food and Drug Administration (FDA) 7
M What kind of instrument that must be calibrated? General Measurement Device and Calibration Topics 3
Q Must product name be listed the same name in FURLS, UDI, GUDID and Company Website? 21 CFR Part 820 - US FDA Quality System Regulations (QSR) 1
J Customer VDA Audit - We must provide refresher training? VDA Standards - Germany's Automotive Standards 4
J Any diverging opinions regarding audit findings or conclusions must be resolved no later than the closing meeting ISO 13485:2016 - Medical Device Quality Management Systems 13
I Sampling processes - Who must define the AQL level? AQL - Acceptable Quality Level 9
M Which documents must be updated upon product validation? Document Control Systems, Procedures, Forms and Templates 1
Q IATF 16949 - Product audit - Must each product be audited? IATF 16949 - Automotive Quality Systems Standard 6
G From an ISO 17025 auditor perspective must micrometer calibration check anvil flatness? General Measurement Device and Calibration Topics 4
C Must your reference standard provider be ISO17034 certified to meet your testing lab's ISO 17025 certification requirements? Other ISO and International Standards and European Regulations 2
R Changing Document Control software. Must I transfer EVERYTHING? Document Control Systems, Procedures, Forms and Templates 3
T Must all Disposable Medical Devices be DEHP Free for MDR? EU Medical Device Regulations 1
W Product Audit - It must be a separate and distinct activity (IATF 16949) IATF 16949 - Automotive Quality Systems Standard 4
P Quality objectives - must they include CAPA and internal audit topic? ISO 13485:2016 - Medical Device Quality Management Systems 28
S. Moore Record Retention - How long must a company keep the following records? Records and Data - Quality, Legal and Other Evidence 17
I Is risk acceptability really needed if all risks must be reduced as far as possible? ISO 14971 - Medical Device Risk Management 6
A ISO 9001:2015 Clause 9.3.2 - Management Review Inputs must be Documented? Management Review Meetings and related Processes 15
N Must Bioburden Sampling Procedures be Documented? Other Medical Device Related Standards 5
M Contacting a "Must Use" (aka Sole Source) Supplier's Registrar Supplier Quality Assurance and other Supplier Issues 6
T Auditor states my Oven Thermocouples must be Calibrated General Measurement Device and Calibration Topics 18
B Must a Design Outsourcing Company have ISO13485? ISO 13485:2016 - Medical Device Quality Management Systems 3
U Must every procedure be proceeded by a policy? Document Control Systems, Procedures, Forms and Templates 2
P Must all parts of a product be RoHS compliant? EU Medical Device Regulations 5
N Must electrodes for Rx/prescription stimulators be Rx only? Other US Medical Device Regulations 2
V Is there an approach to define the "must 'or' should" in supplier audits? US Food and Drug Administration (FDA) 2
F Electronic Signatures (21CFR Part 11) - Must They Appear on Printed Documents Document Control Systems, Procedures, Forms and Templates 9
R What are the "Must Have" Specs and Standards for AS9100 Certification AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 8
L Must we do Receiving Inspection for everything? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 15
U Once upon a QMS - Is a Statement of Uncertainty a must for ISO 17025 accredited labs? ISO 17025 related Discussions 8
C Must we identify steps taken to identify the Root Cause of a failure Nonconformance and Corrective Action 15
Y Must every Process have a Quality Objective? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 21
L Must the Signature on a Quality Record be Legible? Records and Data - Quality, Legal and Other Evidence 33
N Must Employees Be Evaluated Annually? Training - Internal, External, Online and Distance Learning 19
AshleyE Calibration system must meet ISO 10012, ISO 17025 or ANSI/NCSL Z540? ISO 17025 related Discussions 38
D How long must we provide service parts to Ford? IATF 16949 - Automotive Quality Systems Standard 7
E Must Patent Numbers be Shown on Product Labels? Other Medical Device and Orthopedic Related Topics 18
Ronen E FDA Must Have New Authorities to Regulate Pharmacy Compounding US Food and Drug Administration (FDA) 8
P Trip to the USA - Must-Eat Food? Holiday Planning Coffee Break and Water Cooler Discussions 57
Colin What QMS Internal Audits must cover and ISO 9001 Internal Auditing 19
R Is insulation between F type applied part and other parts a must? IEC 60601 - Medical Electrical Equipment Safety Standards Series 4
D Must Forms be referenced in applicable Procedures? Supplier Quality Assurance and other Supplier Issues 6
U Must We Audit Critical Suppliers? How often? Supplier Quality Assurance and other Supplier Issues 7
S Integrating a Multi-Management System - What documents & records must we have? Various Other Specifications, Standards, and related Requirements 6
R Risks which must be Distinctly Identified - Harm, Hazard, Severity ISO 14971 - Medical Device Risk Management 7
O ISO 9001 requirements for what Internal Audits must cover Internal Auditing 7
Q Who must write Quality Manual as per ISO 9001 Clause 5.5.2? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 23
C Is an Initial Environmental Review a must while implementing ISO 14001 ISO 14001:2015 Specific Discussions 5

Similar threads

Top Bottom