When a company I worked for went from QS to TS, I was tasked with redoing the FMEA's. The the audit found the RPN's were ridiculously low and did not reflect the defects being recorded. Using data from the previous 5 years I set up the first FMEA. In the meeting to go over the FMEA everyone was shocked. I showed the data to back it up and the AIAG manual to show it was done correctly. Managements decision was to cut the occurrence rate so we showed the RPN above 100 on only a few items they chose. That was a tough day.
 
Elsmar Forum Sponsor

Stijloor

Staff member
Super Moderator
#12
When a company I worked for went from QS to TS, I was tasked with redoing the FMEA's. The the audit found the RPN's were ridiculously low and did not reflect the defects being recorded. Using data from the previous 5 years I set up the first FMEA. In the meeting to go over the FMEA everyone was shocked. I showed the data to back it up and the AIAG manual to show it was done correctly. Managements decision was to cut the occurrence rate so we showed the RPN above 100 on only a few items they chose. That was a tough day.
Thanks for sharing your FMEA story.

Yes, and that's how the sad FMEA game is played. Hung up on RPN's. :mad:

The current AIAG FMEA manual provides somewhat better guidelines with respect to FMEA analysis, prioritization and possible actions to be taken.

Stijloor.
 

Jim Wynne

Staff member
Admin
#13
From various experience , 100-150 is a common value but there is not a precise rule.
However , you should take action when severity is classified 9 or 10:bigwave:
Taking action on things with high severity ratings won't help anything if the occurrence (especially) and detection ratings are low.
 

qusys

Trusted Information Resource
#14
Taking action on things with high severity ratings won't help anything if the occurrence (especially) and detection ratings are low.
Hi.
This is related to my work experience ( internal auditor, second part auditor) and some benchmarking done.
There were also some requests from Customer in this sense: provide actions in case of high severity
 

AgnieszkaSz

Involved In Discussions
#16
I am a bit confused. Shouldn't we use the manual? :read: In Chapter IV, in section "Determining Action Priorities" there is an unequivocal statement that the cases with highest severity (9 or 10) go first; for severity 8 or less, the sorting criteria are occurence or detection. In next section there is a statement in bold that the use of RPN threshold is NOT a recommended practice for determining the need for actions; then the explanation why follows.
 
R

Rand T

#17
Not all industries are required to follow the AIAG criteria. FMEA's are broad based and can be applied to many different processes.

Also regarding the actions taken on Severity of 9 & 10. Since the severity is the one ranking that can't be reduced without a design change, any actions will only have the effect of reducing the occurance or detection. If those are already at very low rankings, than realistically there is probably little more that can be done.
 
T

TShepherd

#18
TR Shepherd here,

My experience has shown me that selecting an RPN bogey doesn't make a great deal of sense.

Most knowlegable companies now use the rolling top 3 or 5 or 10 whatever within a FMEA and the number selected is based on the actual RPN values and a number of other things including available resources.

The RPN number only has relative value within a specific FMEA and to the team that is using the document.

The final word comes from your customer, if they have a customer specific target regardless if it makes sense or not - that's the number - adjust accordingly.

Tom:rolleyes:
 
Last edited by a moderator:
S

Sturmkind

#19
I agree with many of these posts. Some commodities that are directly safety related (brake systems, airbags, seat belts, etc.) with major design changes or new designs will have very high RPN numbers until testing allows for a reduction in SEV, OCC, or DET.

Chrysler LLC in the 'Blue Dot' series of documents always reviews the top 5 RPN numbers regardless of numeric value.

GM requires an RPN reduction plan regardless of numeric value.

Arbitrary values can limit both continuous improvement and the 'flinching' mentioned earlier to keep the value below a set ceiling.
 
P

playhard

#20
We conduct annual reviews or RPN reduction teams to review all PFMEA's and focus on the top 5 what ever the number is.

We also will review the top 5 when we use the PFMEA in our corrective action reviews.
 
Thread starter Similar threads Forum Replies Date
M Requiring action on factors alone of RPN in FMEA APQP and PPAP 7
C How to handle Action Results in a new FMEA Review once we have a new RPN? FMEA and Control Plans 1
E FMEA Action Plan Threshold (RPN) - Auditor says Action Plan for an RPN > 84 IATF 16949 - Automotive Quality Systems Standard 21
T RPN of Action Results per the AIAG FMEA manual FMEA and Control Plans 5
J FMEA RPN Number and When to Recommend to Take Action FMEA and Control Plans 3
S Process FMEA (PFMEA) RPN Corrective Action Plan FMEA and Control Plans 6
S FMEA RPN Corrective Action Plan QS-9000 - American Automotive Manufacturers Standard 1
Ashok sunder Is it possible to reduce FMEA Occurrence and Detection Ranking after corrective action taken for customer complaints? FMEA and Control Plans 6
M FMEA Corrective Action target date changed ISO 14971 - Medical Device Risk Management 1
P FMEA Risk Analysis Recommended Action Priority FMEA and Control Plans 2
V Linking the FMEA Causes & Action Plan with DOE Experiments or Experimentation Design FMEA and Control Plans 1
H Corrective Action: When to update the Process FMEA (PFMEA) FMEA and Control Plans 15
T Recommended Action(s) Column - Process FMEA FMEA and Control Plans 17
R Updated Process FMEA: How much detail? Closure of an External Corrective Action FMEA and Control Plans 3
A Corrective Action vs. FMEA Occurance, Detection, Severance Nonconformance and Corrective Action 5
Raffy Preventive Action - Does generating an FMEA help future containment? Preventive Action and Continuous Improvement 2
nadhar2 Classification of Action Items Misc. Quality Assurance and Business Systems Related Topics 3
C If it doesn't prevent a non-conformance, is it a preventive action? IATF 16949 - Automotive Quality Systems Standard 13
G Assignable cause/corrective action list for SPC Software Statistical Analysis Tools, Techniques and SPC 3
Q Tips for Action Requests on Communication and Leadership ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 1
S Can we provide training plan as corrective action for IATF 16949 Non conformity? IATF 16949 - Automotive Quality Systems Standard 9
P Corrective Action Response for Missed bumps on brake press Manufacturing and Related Processes 2
R Evaluating the need for preventive action Preventive Action and Continuous Improvement 3
B Stakeholder Initiated Corrective and Preventive Action Misc. Quality Assurance and Business Systems Related Topics 5
B Corrective and Preventive Action (CAPA) A Key Process of the Quality Management System Dec 17... Training - Internal, External, Online and Distance Learning 0
I When exactly can a corrective action be closed? Nonconformance and Corrective Action 3
M Informational TGA – Australian regulatory action on breast implants and breast tissue expanders Medical Device and FDA Regulations and Standards News 0
M Informational Medical Device Safety Action Plan: Protecting Patients, Promoting Public Health Medical Device and FDA Regulations and Standards News 0
Juby Tan Action on Customer Replacement (Nonconforming Product - ISO 9001) Customer Complaints 2
Q Add new action plans in CA, while waiting effectiveness - Same problem reappears ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 13
M Informational The FDA Takes Action to Protect Patients from Risk of Certain Textured Breast Implants; Requests Allergan Voluntarily Recall Certain Breast Implants a Medical Device and FDA Regulations and Standards News 0
L What to do if a Corrective Action requires several extensions Nonconformance and Corrective Action 7
Q Best criteria to measure Corrective Action effectiveness - Poor Maintenance ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
Ashok sunder Is it possible to reduce Risk likelihood and impact Post control Ranking after corrective action taken for risk? FMEA and Control Plans 1
E CAR (Corrective Action Report) with questionable Root Cause ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 14
B How to reply NCR on ineffectiveness of corrective action during IATF external audit? This is repeated issue whereby some mistake was done. IATF 16949 - Automotive Quality Systems Standard 7
C Detection Action for Failure Effects - AIAG 4th Edition Layout FMEA and Control Plans 5
I AS9100D Non-conformance for 10.2.1 b 2 and 10.2.1. b 3 e and f - Corrective Action AS9100, IAQG 9100, Nadcap and related Aerospace Standards and Requirements 10
R Linking the Processes of Continual Improvement, Change Management, Risk Management, Action Planning, etc? Preventive Action and Continuous Improvement 5
M Informational TGA – Action Plan for Medical Devices Medical Device and FDA Regulations and Standards News 0
M Informational EC – Guide for referencing standards in public procurement in Europe (JIS Action 11) Medical Device and FDA Regulations and Standards News 0
I Corrective Action Tracking for Product and Process in the same system? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 6
S Health Canada's Action Plan on Medical Devices - 2019 milestones Canada Medical Device Regulations 0
G When preventative action is prohibited by cost in 8D problem solving Problem Solving, Root Cause Fault and Failure Analysis 1
M Medical Device News Joint Action On Market Surveillance Of Medical Devices (JAMS) Releases Progress Update EU Medical Device Regulations 0
G When preventative action is prohibited by cost in 8D problem solving Problem Solving, Root Cause Fault and Failure Analysis 8
R CIP (Corrective Action) requirements - ISO 9001 clause 10.2 ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 10
E CAR (Corrective Action Request) Due Dates ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 17
C ISO 7010 m002 mandatory action - Color requirements on Packaging IEC 60601 - Medical Electrical Equipment Safety Standards Series 1
E Corrective Action or Customer Complaint ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 16
Similar threads


















































Top Bottom