Hi all,
First time posting so please excuse me,
During our last surveillance audit for ISO9001:2000, the auditor suggested that we develop a work plan for our Internal Audit programme to make it more manageable.

I thought our programme was manageable.

The programme is based on the clauses of ISO9001, with our processes detailed within these clauses. Also utilised are process breakdowns, risks to the business, previous non conformance or areas that are known to be a bit shaky. We try to audit our processes annually.

Does anyone out there have a plan in place to assist in the progression of audits as per plans / schedules or able to shed some light on what an auditor might be suggesting by this?
I have tried to get a further explanation, but to no avail.

Anyway, thanks for taking the time to read this and I welcome all responses.

Cheers
:thanx:
 
Elsmar Forum Sponsor
P

Phiobi

#2
I think a little bit more information may be of help here. Is your current method documented? Can you demonstrate how effective you are at covering all required internal audits?
 
M

Migre

#3
Hi all,
First time posting so please excuse me,
During our last surveillance audit for ISO9001:2000, the auditor suggested that we develop a work plan for our Internal Audit programme to make it more manageable.

I thought our programme was manageable.

The programme is based on the clauses of ISO9001, with our processes detailed within these clauses. Also utilised are process breakdowns, risks to the business, previous non conformance or areas that are known to be a bit shaky. We try to audit our processes annually.

Does anyone out there have a plan in place to assist in the progression of audits as per plans / schedules or able to shed some light on what an auditor might be suggesting by this?
I have tried to get a further explanation, but to no avail.

Anyway, thanks for taking the time to read this and I welcome all responses.

Cheers
:thanx:
When you say you try to audit your processes annually, does your programme clearly state when each of these will actually be audited? If not, perhaps this is what the auditor is trying to suggest. The audit programme I inherited here simply stated when individual sections would be audited, despite each section containing a whole host of procedures and work instructions. I revamped the programme (in conjunction with the section managers) stating quite clearly when each individual procedure/WI would be audited. As a result, I now believe our audit programme is much more manageable.

Regards,

Mick
 
J

JaneB

#4
Petervan,

It's a bit hard to make comments without seeing your program. But your auditor did, and is suggesting improvements.

I would never - ever! - base an audit program on the 'clauses of ISO 9001'.
Ever.

I would always look to structure it around your business processes. Big difference.

And I'd base it on issues such as risk (what's most risky in our business? least?), importance (which are our really critical processes/areas? where will it really bite us if we get it wrong etc).

And when I hear someone say they 'try' to do whatever... I am strongly reminded of the wisdom of Yoda.
There is no try. There is only Do or Not Do.
 
#5
Hi all,
First time posting so please excuse me,
During our last surveillance audit for ISO9001:2000, the auditor suggested that we develop a work plan for our Internal Audit programme to make it more manageable.

I thought our programme was manageable.

The programme is based on the clauses of ISO9001, with our processes detailed within these clauses. Also utilised are process breakdowns, risks to the business, previous non conformance or areas that are known to be a bit shaky. We try to audit our processes annually.

Does anyone out there have a plan in place to assist in the progression of audits as per plans / schedules or able to shed some light on what an auditor might be suggesting by this?
I have tried to get a further explanation, but to no avail.

Anyway, thanks for taking the time to read this and I welcome all responses.

Cheers
:thanx:
Apart from Jane's comment about the clauses of ISO, I think you've got what sounds to be the right idea! What made the CB auditor state such a 'throw away' comment? In my experience, some CB auditors don't have a very realistic clue about audit scheduling, and the best places for guidance is in ISO 9004! Are you not getting to all of the audits? Without knowing what sparked the comment by the auditor, we're flying blind here and you may have nothing to 'fix'.
 
J

JaneB

#7
I didn't, by the way, mean to suggest with my Yoda quote that if you plan it, by jingo, you have to jolly well do it or you're a bad person/in breach of ISO/whatever.

Indeed, I advocate (and most particularly in smaller organisations with more limited resources usually) allowing yourself a degree of flexibility in scheduling audits. For example, some companies strap themselves into a monthly audit, whereas it may work better to schedule them per quarter or even half-year. But you do have to make sure, of course, that audit doesn't become a constantly slipping 'when we get time' task...

I do second Andy's comment - I'd want rather more info from the auditor before making major changes, especially if you see what you're doing as manageable. If s/he doesn't, then some better light needs to be shed on why and what the comment is based on.
 
Thread starter Similar threads Forum Replies Date
S Support Process - Procedure or Control Plan or ??? IATF 16949 - Automotive Quality Systems Standard 4
Y SaMD Verification and Validation SOP and Plan IEC 62304 - Medical Device Software Life Cycle Processes 2
D Quality plan for moving locations ISO 13485:2016 - Medical Device Quality Management Systems 3
V ISO 10360-5: 2020 Gap analysis and Action plan Excel .xls Spreadsheet Templates and Tools 1
S Which Sampling Plan(s) Should I Use? Inspection, Prints (Drawings), Testing, Sampling and Related Topics 7
A Prototype control plan FMEA and Control Plans 2
S ISO9001:2015 Implementation / update plan template ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 2
K Do I need a "State of the art" plan? CE Marking (Conformité Européene) / CB Scheme 1
S Which department should prepare the control plan? could you show me a standard regarding to this matter. FMEA and Control Plans 17
G Control Plan & PFMEA Review Procedure? FMEA and Control Plans 1
L Sampling Plan Risks AQL - Acceptable Quality Level 6
Felony Melony Project Milestone Plan-Development to Mass Production APQP and PPAP 2
A Sampling plan for in-process QC (medical devices) Inspection, Prints (Drawings), Testing, Sampling and Related Topics 13
Q Contingency plan - IATF Sanctioned Interpretation 17 IATF 16949 - Automotive Quality Systems Standard 4
M Does the ISO 9001:2015 standard require a disaster recovery plan or emergency response plan ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 16
D Continuous Improvement Plan - Plastic injection molding IATF 16949 - Automotive Quality Systems Standard 1
M IVDR and Performance Evaluation Plan CE Marking (Conformité Européene) / CB Scheme 2
A The requirement of the PMS plan--suitable indicators and threshold values EU Medical Device Regulations 0
W LTPD, AQL, Ppk and Cpk validation sampling plan table Inspection, Prints (Drawings), Testing, Sampling and Related Topics 0
E BCP (Business Continuity Plan) Call Tree Business Continuity & Resiliency Planning (BCRP) 13
P IATF 16949 requirement - error-proofing in control plan IATF 16949 - Automotive Quality Systems Standard 3
B Biological evaluation plan and report Other Medical Device Related Standards 5
B Sterilization Validation Plan Other Medical Device Related Standards 3
earl62 What is the best way to control special characteristics in Control plan? Is it Mandatory to have SPC for IATF 16949? IATF 16949 - Automotive Quality Systems Standard 12
R Electrical contractor Project Quality Management Plan Quality Manager and Management Related Issues 1
M Clinical Development Plan - Advice Requested EU Medical Device Regulations 11
I Control Plan (Product/Process specification/ Tolerance) acceptance FMEA and Control Plans 27
J Control Plan use on the manufacturing floor FMEA and Control Plans 4
E Change in control plan - Do I have to do sampling? IATF 16949 - Automotive Quality Systems Standard 1
S Is using ANSI/ASQ Z1.4-2008 the correct sampling plan to determine Pass/Fail of Apparel measurements? AQL - Acceptable Quality Level 4
D All Dimensions listed on control plan FMEA and Control Plans 10
DuncanGibbons Resources for aiding in procedure, work instruction and manufacturing plan development and management AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 0
Q Internal audit plan template Internal Auditing 12
C Gobys for operations documentation plan Oil and Gas Industry Standards and Regulations 4
N Sampling Plan for Internal Audits - ISO 2859 or 3951 - Or Neither? Internal Auditing 6
DuncanGibbons Manufacturing Plan vs Material Specification vs Control Plan Manufacturing and Related Processes 5
K %GRR was between 10-30% so we have to have a "backup plan" per auditor IATF 16949 - Automotive Quality Systems Standard 15
R Reduced sampling plan for sterial products APQP and PPAP 0
S PMS (Premarket Submission) and PMCF Plan EU Medical Device Regulations 5
M Clinical Evaluation Plan vs. PMCF Plan EU Medical Device Regulations 24
qualprod Corona virus Contingency plan - What have you done in your company? ISO 9000, ISO 9001, and ISO 9004 Quality Management Systems Standards 25
S Should safety checks be included in the Control Plan? IATF 16949 - Automotive Quality Systems Standard 5
J Requested Validation plan and reports Manufacturing and Related Processes 4
T Defining sampling plan for different AQL AQL - Acceptable Quality Level 3
T Reaction Plan To Drive suppliers to IATF 16949 registration IATF 16949 - Automotive Quality Systems Standard 6
adir88 MDR requirement: Risk Management Plan for "each device" ISO 14971 - Medical Device Risk Management 5
B AS9100D Sampling Plan AS9100, IAQG, NADCAP and Aerospace related Standards and Requirements 2
D Supplied Product on Control Plan - Lot ranging in 40,000 pcs per product FMEA and Control Plans 3
M Can someone share a scrubbed version of Clinical Evaluation Plan (CEP) EU Medical Device Regulations 8
S EU MDR Annex XIV - Clinical Evaluation Plan - What do these methods mean? EU Medical Device Regulations 16

Similar threads

Top Bottom