The Elsmar Cove Business Standards Discussion Forums More Free Files Forum Discussion Thread Post Attachments Listing Elsmar Cove Discussion Forums Main Page
Welcome to what was The Original Cayman Cove Forums!
This thread is carried over and continued in the Current Elsmar Cove Forums

Search the Elsmar Cove!

Wooden Line
This is a "Frozen" Legacy Forum.
Most links on this page do NOT work.
Discussions since 2001 are HERE

Owl Line
The New Elsmar Cove Forums   The New Elsmar Cove Forums
  Measurement, Test and Calibration
  MSA AND CONTROL PLAN

Post New Topic  Post A Reply
profile | register | preferences | faq | search

UBBFriend: Email This Page to Someone! next newest topic | next oldest topic
Author Topic:   MSA AND CONTROL PLAN
chen
Forum Contributor

Posts: 19
From:dongguan,guangdong,p.r.china
Registered: Nov 98

posted 05 April 1999 09:28 PM     Click Here to See the Profile for chen   Click Here to Email chen     Edit/Delete Message   Reply w/Quote
"Appropriate ststistical studies shall be conducted to analyze the variation present in the results of each type of measuring and test equipment system. this requirement shall apply to measurement systems referenced in the control plan." - #46 of QS9K

my question is:
now we only performed MSA on the measurement systems using to measure the characteristics
of product.
do we need to perform MSA on the measurement systems using to measure the characteristics of process?

have a nice day! Apr.,06/1999

IP: Logged

Batman
Forum Contributor

Posts: 111
From:Kane, PA 16735
Registered:

posted 05 April 1999 11:30 PM     Click Here to See the Profile for Batman   Click Here to Email Batman     Edit/Delete Message   Reply w/Quote
Hi Chen.
Yes, and no. If you list a measurement device in your control plan, in the "Evaluation / Measurement Technique" section, assuming you are using the APQP Control Plan format, you must have an "...analysis of the linearity, reproducibility, repeatability, stability, and accuracy of the measurement system..." Page 43 of APQP and Control Plan manual.

It should probably read "and / or" because some gage systems just won't have R&R, for instance. We have had no trouble with the "process" gages - temperature, pressure, timers, etc - listed on the control plan, as long as there was a record that they were calibrated [or standardized] on time according to our (or manufacturer) recommendations.

If you refer to your FMEA, from where most of your control plan comes, there should be some consideration (effort) given to the reliance and criticality of those gages measuring high RPN valued features - process or product. Lower RPN values indicate less of a failure mode. If you are having trouble with the process gages in this regard, you may consider stating in a work instruction that a particular "process" gage is monitored, but some other measurement is performed that is easier to perform MSA on.

My 2 cents...group?

IP: Logged

All times are Eastern Standard Time (USA)

next newest topic | next oldest topic

Administrative Options: Close Topic | Archive/Move | Delete Topic
Post New Topic  Post A Reply Hop to:

Contact Us | The Elsmar Cove Home Page

Your Input Into These Forums Is Appreciated! Thanks!


Main Site Search
Y'All Come Back Now, Ya Hear?
Powered by FreeBSD!Made With A Mac!Powered by Apache!