Booker
Starting to get Involved
Hello,
I am working at small company 50 employees.
We have been audited last month with three minor NCs.
One of them is:
"Internal Audit process not fully implemented, QMS was not covered in its entirety during the last 12 month period. Production process not audited in the last 12 month."
Frankly said we miss them for no special reason. Just I was lazy auditor, whatever.
Can anyone advise me some "good" root cause, why these audit haven't be performed.
Sorry for english.
I am working at small company 50 employees.
We have been audited last month with three minor NCs.
One of them is:
"Internal Audit process not fully implemented, QMS was not covered in its entirety during the last 12 month period. Production process not audited in the last 12 month."
Frankly said we miss them for no special reason. Just I was lazy auditor, whatever.
Can anyone advise me some "good" root cause, why these audit haven't be performed.
Sorry for english.