Good morning for all,
I am asking about how to calculate OEE indicator for a workshop ( 15 machines)
We have downtime by machine during a week; production by product, quality reject, OEE by machine; but we have to calculate the indicator for the hole activity; is it the product of OEE?
thanks!
I am asking about how to calculate OEE indicator for a workshop ( 15 machines)
We have downtime by machine during a week; production by product, quality reject, OEE by machine; but we have to calculate the indicator for the hole activity; is it the product of OEE?