C
Chris Skowron
Here is a “real-life” example: There is a drawing specification for parallelism: 0.005”. The target is zero, the upper specification limit is 0.005”.
The manufacturing produces components with the actual parallelism 0.002” – 0.004”.
How to assess the capability of this process? What formulas should be used to calculate indices? What are the acceptability criteria?
The manufacturing produces components with the actual parallelism 0.002” – 0.004”.
How to assess the capability of this process? What formulas should be used to calculate indices? What are the acceptability criteria?