Dear All,
VDA 6.3 standard says that during potential analysis of any supplier the process to be evaluated & it is inline with the similar product or process required by the customer.... But few of my suppliers supplies both stamping & precision machining parts from the same plant..So should i do 2 process audits separately covering the both parts...?
And how to conduct process audit for the supplier who supplies around 50 different types of machined parts...? how to cover all the parts?
And we do VDA 6.3 for potential analysis (** questions), & P2, P3, P4 for before SOP & P5,P6,P7 for after SOP..But when will we audit all the questions from P2 to P7..is there any specific reqt to conduct all questions?..
I am having lot of doubts about this VDA 6.3..will ask u one by one..Pl reply for this now..Thanks
VDA 6.3 standard says that during potential analysis of any supplier the process to be evaluated & it is inline with the similar product or process required by the customer.... But few of my suppliers supplies both stamping & precision machining parts from the same plant..So should i do 2 process audits separately covering the both parts...?
And how to conduct process audit for the supplier who supplies around 50 different types of machined parts...? how to cover all the parts?
And we do VDA 6.3 for potential analysis (** questions), & P2, P3, P4 for before SOP & P5,P6,P7 for after SOP..But when will we audit all the questions from P2 to P7..is there any specific reqt to conduct all questions?..
I am having lot of doubts about this VDA 6.3..will ask u one by one..Pl reply for this now..Thanks