J0anne
Joanne
An EU auditor has given my client 90 days to complete NCs raised at audit.
Does anyone know where the NB got their 90 day rule from?
I am guessing it's one of their internal procedures?
Although I can't see how it can be possible to apply.
For example if a manufacturer needed a new injection moulding machine it's likely to take a lot longer than 90 days. In this example the manufacturer will have to close the business as the NB is threatening to withdraw certification if the machine hasn't arrived and actions aren't completed in 90 days!
Does anyone know where the NB got their 90 day rule from?
I am guessing it's one of their internal procedures?
Although I can't see how it can be possible to apply.
For example if a manufacturer needed a new injection moulding machine it's likely to take a lot longer than 90 days. In this example the manufacturer will have to close the business as the NB is threatening to withdraw certification if the machine hasn't arrived and actions aren't completed in 90 days!