Is there a limit to the time between your audit and when your CARs must be accepted by the CRB? For instance..If you were audited in May - Could your CARs be accepted in Nov?
AS9100 Certification Audit. The first audit (5 days) began Mar 31- and ended April 4th with corrective action due May19...CARs were submitted at the beginning of June w/ auditor returning July 30-31, the final assessment report submitted to us by auditor recommednded certification.
Is this the same issue that you'd previously posted about the long wait and you not getting your certificate? I had assumed that you'd taken it up with the CB management and it had been resolved. Are you still in the same boat?