Hi. I have a question. Maybe someone outthere can answer.
Clause 4.11 states that MSA studies has to be deployed for all measure systems documented in control plans. This is done using the Evaluation/Measure Technique column in the Control Plan Format.
How can you deploy a MSA study on a visual inspected appearance variable ? (In the APQP / CP booklet there is an example of this kind of variables).
What about go / no go issues ? Are they similar ?.