I have a question regarding the supplier selection process clause 8.4.1.2.
The clause states that the process shall include relevant quality and delivery performance. How can this be achieved if you have yet to buy from the supplier ? You can ask the supplier in question to provide their own data but, in many cases, they are unwilling to provide this. Would a trial period be acceptable, during which you monitor and assess the supplier's quality and delivery performance ?
Any advice on this would be appreciated. Thanks in advance.
The clause states that the process shall include relevant quality and delivery performance. How can this be achieved if you have yet to buy from the supplier ? You can ask the supplier in question to provide their own data but, in many cases, they are unwilling to provide this. Would a trial period be acceptable, during which you monitor and assess the supplier's quality and delivery performance ?