Hello. I am new to the Forum and would appreciate some help. I have established timestudies for Work Content/Total Cycle Time for each workstation. The question is that each Station is above the Establish Takt time. Would the number of Stations required be Cycle Time/Takt Time? Also how would you determine the required crew size at each station?
Thanks for the Help,
AggieRob02
The PFT Powerpoint was great, thanks! However, The Calculation for Manpower variable "L" is unknown. The Total Equation is:
Dr= (Dc x L)/(H x S)
Would you be able to help? I also estimate that Dc represents the Takt Time. Would you please be able to help? Thanks again,
AggieRob02
I could not able to open the document .. What could be the problem