For medical devices, is there a standard or guidance that dictates the order of approval of a document?
For example, must the Author approve before the Reviewers, and only then can the Approvers sign?
It seems that that would be an ideal order. But a situation where all parties are geographically (and time zone) separated can generally make this take longer than a process where, once everyone has agreed (verbally, etc) to the final version, it is signed as early as possible by the signatories. This might mean that an Approver would sign before the Author.
Any signatory could apply their own judgement on pre-conditions; e.g. they're not going to sign until they've seen particular other signatures. But, that would be above-and-beyond the
As far as I see, ISO 13486 and the QSR only require that records be signed by the appropriate authorities - the do not impose any requirements or expectations on the order/dates of the signatures.
Am I missing something in regulations or guidance that prescribe a particular order? Or, is there some inherent danger in allowing approvals to happen in any order?
Thanks!
For example, must the Author approve before the Reviewers, and only then can the Approvers sign?
It seems that that would be an ideal order. But a situation where all parties are geographically (and time zone) separated can generally make this take longer than a process where, once everyone has agreed (verbally, etc) to the final version, it is signed as early as possible by the signatories. This might mean that an Approver would sign before the Author.
Any signatory could apply their own judgement on pre-conditions; e.g. they're not going to sign until they've seen particular other signatures. But, that would be above-and-beyond the
As far as I see, ISO 13486 and the QSR only require that records be signed by the appropriate authorities - the do not impose any requirements or expectations on the order/dates of the signatures.
Am I missing something in regulations or guidance that prescribe a particular order? Or, is there some inherent danger in allowing approvals to happen in any order?
Thanks!