I've recently joined the company and am working on transition prep, a big concern is that the internal audit schedule has not been adhered to in a big way.
I raised an internal non conformance, devised a new plan and started up the audits, however there is still a massive gap.
I am new to this, but understood that the external auditor will be expecting to see 12 months of internal audit, is there anything else i can do?
I raised an internal non conformance, devised a new plan and started up the audits, however there is still a massive gap.
I am new to this, but understood that the external auditor will be expecting to see 12 months of internal audit, is there anything else i can do?