I'm looking for some feedback on how you guys would/ have handled Calibration Postponement.
We have a sampling machine for thermal conductivity, which was due to be calibrated in week 5 (Very expensive involving the a company representative coming over from Europe to the UK), but as we were purchasing a second model it was decided to postponement, the calibration until the new model arrived when we would have both done at the same time.
The calibration had therefore been booked in for week 16, however due to delays with the manufacturing of the new model the calibration will not be conducted until week 25.
We have an external surveillance audit coming up in the next couple of week. I don’t think this will prove to be a problem for us as we have a planned calibration date and the machine is checked on a weekly basis against reference samples prior to use.
What i am looking for is how you would handle this;
Just a note in the calibration file or
Formal document (Deviation) signed off by the Quality Manager or
Some other way?
in advance
We have a sampling machine for thermal conductivity, which was due to be calibrated in week 5 (Very expensive involving the a company representative coming over from Europe to the UK), but as we were purchasing a second model it was decided to postponement, the calibration until the new model arrived when we would have both done at the same time.
The calibration had therefore been booked in for week 16, however due to delays with the manufacturing of the new model the calibration will not be conducted until week 25.
We have an external surveillance audit coming up in the next couple of week. I don’t think this will prove to be a problem for us as we have a planned calibration date and the machine is checked on a weekly basis against reference samples prior to use.
What i am looking for is how you would handle this;
Just a note in the calibration file or
Formal document (Deviation) signed off by the Quality Manager or
Some other way?