Prototype Build Process per TS 16949 Clause 7.3.6.2 and APQP

P

pharmarton

Hello everyone!!
I have read through all of the 7.3.6.2 and APQP regards points to prototype bulild process and I created a process map.
Could anyone out there give me some feedback or thoughts about yhr map?
:thanks:
Pharmaton
 

Attachments

  • MP031.vsd
    93.5 KB · Views: 204

AndyN

Moved On
Re: Prototype build process

Hello everyone!!
I have read through all of the 7.3.6.2 and APQP regards points to prototype bulild process and I created a process map.
Could anyone out there give me some feedback or thoughts about yhr map?
:thanks:
Pharmaton

Could you post this as a .pdf, since not everyone will have Visio?
 
S

Sturmkind

Re: Prototype build process

Hi, pharmarton!

I took the liberty of scanning your flowchart and had a couple of questions:

If 'Automotive' = Y, then isn't a Team Feasibility needed before DFMEA or Control plan can be done?

After 'Create prototype samples' isn't a dimensional and/or appearance check needed before sending to the customer?

Otherwise, looks pretty good to me!
 

Attachments

  • DDP_Flow.pdf
    56.1 KB · Views: 282
P

pharmarton

Re: Prototype build process

Thank for your ideas,
I included your suggestion in the APQP process map, but I forgot in the prototype. I attached a pdf file with these modifications, Thoughts???
Pharmaton
 

Attachments

  • MP031.pdf
    9.1 KB · Views: 205
K

kekoukele

hello, i have read your post.
1\ APQP用于新品开发
used for new production.
2\你需要认真阅读APQP手册,知道谁先谁后
you should read APQP reference manual clearly and know who first who after.
3、CP来源于DFMEA?PFMEA?FLOW CHART?
Does CP Origin DFMEA?PFMEA?Flow chart?
4、过程流程图在哪里?
Where is preliminary process flow chart?
5、MSA SPC 在哪里?
where is MSA? SPC?
6、特殊特性清单在哪里?
Where is special product and process characteristics.
just my viewpoint.
 
P

pharmarton

:bigwave:Thank you for your feedback.
This procedure is only cover the prototype building, is a subproces of the DDP process.
Pharmaton
 